Title: L2 Status


1
L2 Status
  • James T. Linnemann
  • MSU
  • PMG
  • September 20, 2001

2
Alpha
  • First Production 4-6 fully work break/fix
    about 1/week
  • Second Production
  • Pre-production boards work
  • DMA fixes incorporated in layout
  • Learned can successfully replace CIA BGA (better
    than unreliable socket!)
  • new supplier for raw boards, better assembly
    (failures diagnosed site visits)
  • 11 more being built now 5-7 arrive Sep 26
    remainder Oct 5
  • PIO to Alpha not working (firmware) early
    October
  • Need 15 for nominal system (7 for test stand)
  • concentrate on 1 Alpha/crate firstOK for low
    rate
  • Add processors to meet throughput demands as
    available
  • Beta replacement
  • prototype December 01, production Summer 02

3
MBTworkhorse I/O card
  • cards in hand
  • Before install stable SCL firmware Sept/Oct
  • firmware all written being debugged (good
    turnaround)
  • Scl_init sequence L1, L2 busy (easier)
  • Multi-card broadcast need testing at FNAL
  • 128 bit fanout needs testing at FNAL with
    Edmunds Oct
  • Some marginal timing being chased
  • Results write to Global needs to be
    re-integrated
  • tweaking output amplitude
  • Monitoring functions need to test at FNAL

4
FIC G-link receiver(all crates but muon)
  • FPGA code being tweaked
  • Some vme problems remain
  • commissioning modes only progress being made
  • G-link data problems fixed (tested BER lt E-10)
  • Need pin reassignment for monitoring FPGA
  • Will swap for faster chip (socketed)
  • FPGA compiler problems probably resolved
  • Fermilab/ESE support for commissioning
  • Met last week with Saclay experts
  • Consult on design fixed 3 dead channels

5
L2 Muon Cards
  • CIC (L2Mu input card) installed inputs
    cabled
  • SLIC (L2 Mu processor card) ready to cable up
  • Algorithms being downloaded already
  • SFO (fanout) all but 2 at Fermi
  • Needed by Muon system, and test stand
  • Very useful for commissioning
  • May have other uses during running
  • All cards work in most important modes
  • For one mode, have to hand-select cards
  • Only need 2 working in 112 fanout mode
  • Investigating why only half do, but half of 25 is
    plenty
  • why error rate different in Nebraska?

6
Miscellaneous Interface Hardware
  • 16 to 128 bit mux add-on to MBT (UMd)
  • Returns L2 trigger mask to L2HWFW Sep/Oct
  • L1HWFW to L2 Global (via FIC) (MSU)
  • Optical Split L1 trigger mask
    Aug/Oct
  • dummy content fixed event ID
  • Monitoring of Alphas by L1 Scalers (MSU)
  • Passive cable formatting card Oct

7
CommissioningAt Last
  • L1SCL-MBT-Alpha-VBD-L3 milestone met
  • One channel data, real frame software, in MCH
  • Need to verify format from SAM
  • Muon system has seen real inputs-CIC-SLIC
  • L1 format needs correction
  • Scint format OK but L2timing interfere errors
  • MDT format OK
  • PDT unformatted October?
  • Current tests
  • SCL_INIT for MBT-Alpha (for permanent MCH
    running)
  • Add 2nd channel of data (FIC-MBT-Alpha-VBD-L3)
  • real algorithms into SLIC timing Fwd Mu already
  • Muon 2nd or 3rd input CIC-SLIC-MBT-Alpha-VBD-L3
  • One event pushed through STT prototype vertical
    slice
  • FRC, STC, TFC CTT roads, SMT clusters, fit

8
Summary
  • Commissioning is underway in earnest
  • Some real inputsneed more to do physics
  • Mu, cal, ctt, cps is probable order
  • Most hardware in hand
  • Remaining alphas soon, I hope
  • Final cabling in October
  • Firmware written commissioning it now
  • MBT, Alpha, FIC
  • Crucial scale-up tests in coming weeks
  • All hardware in crates
  • Multiple inputs
  • Algorithm downloads coming
  • Muon started last week continue thru shutdown
  • code running in simulator already

9
Arrival of L2 Inputs
  • When inputs steadily available (subset, full)
  • L1 Trigger Mask to Global (August, October)
  • Cal (September?, November?)
  • Muon
  • Trigger (L2 software not tested) (June, November)
  • Detector (August,October?)
  • CTT,CPS (October,November)
  • FPS (November,December)
  • COOR programming September?

10
Online Software Plans
  • ?Event data flow late Aug
  • Worker with filter code Sept
  • Multi-alpha (as available) Oct/Nov
  • interrupts for speed as needed Dec/Jan
  • Coor script downloading via TCC Late Sept
  • Till then, configure from hand-edited file
  • Online and in TSIM
  • Data Flow Monitoring test Sept/Oct
  • Errorlogger to screen/S.E.S. Oct/Dec?
  • Global Preprocessor Oct-Nov
  • FILTERING! (if have enough inputs)
  • Verification online vs. TSIM
  • 1st version running now testing data capture
  • Needs pretty good data to be useful Oct/Nov?