Title: Case Study: Landfill Excavation at Oliktok
1Case StudyLandfill Excavation at Oliktok
- For the 2008 Alaska Forum on the Environment
- by Tamar Stephens
- Alaska Department of Environmental Conservation
- Contaminated Sites Program
2Background
- With climate change, the sea ice is diminishing.
- As the ice recedes, it provides less buffering
from storm action, resulting in faster coastal
erosion. - Old landfills/dumps located along the coast are
at greater risk of erosion.
3Introduction
- This presentation is a case study of a landfill
at a North Slope Air Force facility, the Oliktok
Long Range Radar Station. - Old landfills on the north slope were probably
expected to stay frozen forever. - Storm action and erosion led to an interim action
at Oliktok a few years ago. - Increased coastal erosion and storm action
ultimately led to a decision to remove the
Oliktok landfill. - This case study illustrates the importance of
removing coastal landfills that are subject to
erosion, to protect the aquatic resources from
solid waste, hazardous materials, and
contaminated soil found within the landfill.
4Oliktok Long Range Radar Station
5Location of Landfill (LF001)
6Erosion from 2000 Storm
In 2001, an old dump site (LF001) was found to be
significantly eroded by a storm event that
occurred in 2000. Drums and other wastes were
washed into the Beaufort Sea and oil was
released.
7This area is used for subsistence activities.
The dump is directly adjacent to a fish camp, and
was used as a boat launch for whaling expeditions
until the 2001 erosion problems.
82001 Initial Response
Booms were used to capture sheen from drums
exposed by erosion.
92001 Emergency Response
A time critical removal effort stopped release of
PCB-containing oil from corroding drums.
10Erosion control was installed
Geo-fabric webbing was installed to help control
erosion.
11Erosion control
Erosion control was completed by covering the
webbing with clean backfill.
122007 Clean Sweep
- The Air Force Clean Sweep program was
implemented at Oliktok in 2007. - By this point in time, both DEC and the Air Force
had concluded that coastal erosion was a
significant force. - Clean Sweep included removal of the coastal
landfill (LF001).
13What we knew before excavating the LF001 landfill
- Previous erosion occurred petroleum sheen and
low levels of PCBs were detected. - Subsequent sampling identified an area with low
level PCB soil contamination in the middle of the
landfill. - Sampling also identified an area with petroleum
contamination surrounding the PCB area. - Sampling did not detect any significant
contamination in other areas of the landfill.
14Landfill was excavated in early spring 2007
Soil was still frozen. Frozen soil allowed better
vehicular access. Frozen conditions minimized
water problems.
15First was removal of an area known to have
PCB-contaminated soil
16Next was removal of a surrounding area with
petroleum-contaminated soil.
PCB soil in super sacks inside the hangar
Petroleum soil is stockpiled inside the hangar
This photo shows PCB soil in super sacks and
petroleum soil in a stockpile. Soil is
currently stored inside the hangar.
17Small ferrous (iron) items were removed with an
industrial magnet.
18Small non-ferrous items were removed by hand.
19Heating oily substance for easier removal
A drum with product is heated to make the
contents less viscous so it can be pumped into a
new drum for removal.
20Current Status
Floor of LF001 early fall 2007. The landfill was
excavated to permafrost. Sampling shows PCBs in
various places on the floor. Excavation to
remove remaining PCBs is planned for 2008.
21Sidewall and Floor Confirmation Sampling of LF001
landfill
PCBs gt 1 mg/kg
PCBs gt 10 mg/kg
POL gt method 1
22Potential hazardous waste was found throughout
the landfill.
- Drums with product
- Drums with oily residue
- Capacitors and small transformers (PCB sources)
- Transformer casings (PCB sources)
- Large fluorescent light ballasts (PCB sources)
- Nickel-iron batteries
- Lead-acid batteries
- Asbestos-containing material
23During excavation, presumed clean soil was in
stockpiled at one end.
- Confirmation sampling showed low levels of PCBs
throughout the stockpile of presumed-clean soil
in the landfill. Thus, entire volume, about
5,000 cubic yards, has to be managed as PCB soil. -
- Confirmation sampling showed PCBs in the
petroleum soil stockpile in the hangar thus
this soil also needs to be managed as PCB soil.
24New Stockpile Location
Stockpiled soil was removed from LF001 and LF002
and placed in a long-term stockpile in a location
not vulnerable to storm action, late summer 2007.
25Stockpiled soil from LF002 being moved to new
long term stockpile location
26Whats Next
- Additional excavation of the floor of the
landfill to remove remaining PCB-contaminated
soil later this winter (2008). - Evaluate options for managing stockpiled soil
with low levels of PCBs.
27Lessons Learned
- Landfill characterization cannot be done without
removing everything. - Assume that you dont know what is in the
landfill, and will need to characterize and
segregate as you go. - Sources of contamination are likely to be present
throughout.
28Thank you
- To the Air Force and to BEM Systems for
photographs and figures used in the presentation.
29The End
Tamar Stephens (907) 451-2131 tamar.stephens_at_alask
a.gov