Title: Downtown Howell Draft Master Plan
1Downtown Howell Draft Master Plan Street
Program Update
September 15th 2009 Good Morning Livingston
2Downtown Master Plan
- Plan has not been reviewed and approved by the
City Council or DDA Board yet. - Plans to presented to Mayor City Council in
October 2009 - Still seeking input on plans
3Local City of Howell
41883
51899
61916
Terry Wilson
71942
8Today
9Downtown Vision Plan
10- A Streets
- No Driveways
- Buildings Up to the ROW
- Parking in Back
- Continuous Facade
- Front Doors on the Street
- High Transparency of Windows - eyes on the
street - Existing non-conforming sites should utilize
screening or other techniques. - B Streets
- Driveways Allowed
- Buildings Up to the ROW
- Parking in Back
- Front Doors facing the street.
A B Streets
11TOD/North Area
Library
CourthouseSquare
12Transit Oriented Development Old Depot Area
13TOD North Area / Old Depot - Sections
14TOD North Area / Old Depot Cut-A-Way
15(No Transcript)
16No TOD North Area / Old Depot
17(No Transcript)
18(No Transcript)
19Clinton Ave
Chesnut St
Library
Garage w/ Liner
Center St
Grand River
Walnut St
Additional Library Parking Garage
20Garage w/ Mixed-Use/Residential/Office
Walnut St
Garage Mixed Use Liner on Walnut Street
21Garage w/ Façade Liner
Clinton Ave
Center St
Better Crosswalks Back-In Angled Parking on
Center Street
22(No Transcript)
23(No Transcript)
24Michigan Ave
Clinton Ave
Walnut St
State St
Roundabout
Courthouse Square
Court St
Grand River
Grand River Michigan Courthouse Square
25State Court Streets Festival Street
Amphitheater
26State Court Streets Festival Street
Amphitheater
27Clinton Ave
State St
Michigan Ave
Amphitheater
Peanut Row
Courthouse Square
Grand River
Courthouse Square Festival Streets
Amphitheater
28(No Transcript)
29(No Transcript)
30(No Transcript)
31State Court Streets Festival Streets / Shared
Spaces
32What was heard during the Charrette..
- Improve pedestrian access across Grand River
- Add on-street parking on Grand River
- Maintain traffic volumes on Grand River
33Things that must happen before any changes in
Grand River Drive Lanes happen..
- Construction of the Latson Road Interchange
- Construction of National Street Extension
- City of Howell gain jurisdiction over Grand River
- All of these items will take years to complete..
34M-59
Grand River Ave
New Loop Road at National
I-96
New Interchange at Latson Road
Reclaim Grand River Avenue in Downtown
35Grand River Avenue - Existing
3670 wide street condition Vehicular
oriented Irregular street tree spacing Minimal
street furnishings
Grand River Avenue - Existing
37Construct sidewalk improvements Providing uniform
street tree and light spacing Improved planting
condition with structural soil Additional street
furnishings Improved walking environment
Grand River Avenue Phase 1
38Grand River Avenue - Existing
39Grand River Avenue Phase 1
40Grand River Roundabouts
- Are not part of the Citys current on-going
Street Program - Are the only traffic control solution that allows
for reduction in the number of lanes on Grand
River, while supporting current and future
traffic volumes. - Cannot occur until the other three issues are
addressed (Latson, Loop MDOT)
41(No Transcript)
42(No Transcript)
43(No Transcript)
449
12
12
12
45 Total
4512
12
24 total
46Grand River Avenue - Proposed
47Pedestrian Zone Grand River Avenue
4870 wide street condition Vehicular
oriented Irregular street tree spacing Minimal
street furnishings
Grand River Avenue - Existing
49Construct sidewalk improvements Providing uniform
street tree and light spacing Improved planting
condition with structural soil Additional street
furnishings Improved walking environment
Grand River Avenue Phase 1
50Re-stripe street providing 2 travel lanes,
center turn lane, 2 bike lanes, and back-in
angled parking Increase parking capacity Calm
traffic Multi-modal street
Grand River Avenue Phase 2
51Construct median, round-a-bouts, and drainage
improvements Providing additional street
trees/landscape in the median and round-a-bout
islands
Grand River Avenue Phase 3
52Grand River Avenue - Existing
53Grand River Avenue Phase 1
54Grand River Avenue Phase 2
55Grand River Avenue Phase 3
56Grand River Avenue - Proposed
57Grand River Avenue Proposed with 5-Lanes (Ex.)
58(No Transcript)
59Downtown Master Plan
- Plan has not been reviewed and approved by the
City Council or DDA Board yet. - Plans to presented to Mayor City Council in
October 2009 - Still seeking input on plans
60Other News Events
- Phase I of Street Program is on schedule.
- Phase II is in design and will begin in Spring of
2010 - Downtown Howell is maintaining strong occupancy
in this economy. - New Businesses opening or about to
- Razmatazz
- Livingston Business Forms relocation
- Alley Side Consignment Boutique
61Other News Events
- Business Recruitment team has been established
with video recruitment package developed. - Howell Main Street Program is recognized as
Michigan Main Street Program of the Year. - Celebrating the 175th anniversary of Howell in
2010.