Chewuch Diversion Dam Renovation - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Chewuch Diversion Dam Renovation

Description:

Chewuch Diversion Dam Renovation – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 21
Provided by: rco97
Category:

less

Transcript and Presenter's Notes

Title: Chewuch Diversion Dam Renovation


1
Chewuch Diversion Dam Renovation
  • Managing an Innovative Design and Multiple
    Partners

2
Project Information
  • Project Sponsor Chewuch Basin Council (Chris
    Johnson Project Manager).
  • Partners Reclamation, WDFW, BPA, USFWS, Chewuch
    Canal Company, Methow Salmon Recovery Foundation,
    USFS .

3
Project Location
Chewuch Dam
Chewuch Dam
4
Other Information
  • Existing dam was a low flow passage impediment
    to Upper Columbia steelhead, Upper Columbia
    spring Chinook, and bull trout. (All ESA listed
    species)
  • Spring Chinook were spawning in 700 inlet canal

5
Project Finances
  • Project Cost - 513,770
  • Funding Sources
  • SRFB Grants 204,670
  • FRIMA grant - 74,400
  • BPA - 149,400
  • Douglas PUD 43,300
  • Private Sources-42,000

6
Project Benefits
  • Only two passage impediments on Chewuch River
    Chewuch and Fulton Dams.
  • This project opened approximately 50 R.M. to
    unimpeded low flow passage.
  • Eliminated dewatered Chinook redds in inlet
    canal.

7
Project History
  • Reconstructed in the 50s Chewuch Dam was
    undermined and failing.
  • Fish ladder was stranded at low flows.
  • Identified as a partial passage barrier (USFS,
    WDWF)
  • Consistent with Limiting Factors Report and draft
    UCSRP

8
Project History
  • 2003 - Chewuch Canal Company contacts
    Reclamation for design work
  • 2004 - Chewuch Basin Council begins funding and
    project management assistance for CCC

9
Project Design
  • Reclamation designers developed 7 alternatives
    (including rock v-weirs) Engineers from WDFW,
    NOAA Fisheries, and USFWS were consulted during
    Reclamations 1/4ly coordination process.
  • Permitting through coordinated Reclamation process

10
Project Implementation
  • Bid Process Open competitive bid
  • Contractor Boulder Creek Excavating
  • Materials Rock from USFS lands
  • Construction Oversight Reclamation under BPA
    contract.

11
Project Implementation
  • Construction from Oct.1, 2005 to January 15,
    2006. (Punch List in 2006)

12
Finished Product
  • 5 roughened channel 96 long
  • New dam crest 12 higher to eliminate flashboards
    except during extreme low flows.
  • Operable headgate to prevent unregulated flows
    down inlet canal
  • Adult fish exclusion to prevent spawning in inlet
    canal
  • Over 200 spring Chinook redds above the structure
    in 2006
  • Didson camera monitoring by USGS showed adult
    fish passing structure

13
A Reality Test - High flows 2006
  • Over 6000 c.f.s. a 13 year event.

14
(No Transcript)
15
After the Flood.
April 2006
July 2006
Hand Maintenance
August 2006
16
Current Condition
March 2007 Flows at 700 cfs /-
17
Ongoing Monitoring/ Adaptive Management
  • Measurements of roughened channel profiles
  • Upstream redd counts
  • Didson camera
  • Adaptive management

18
Management Lessons Learned
  • Understand your liability
  • Identify contingency funding sources before you
    start
  • Permit review and consultation need to be started
    during the design process

19
Construction Lessons Learned
  • When you play with sticks and stones in the river
    never assume one and done
  • Leave spare parts
  • If possible, leave your permits and funding open
    for at least one high water event.
  • Be forthright up front with owners about their
    long and short term maintenance responsibilities.

20
Questions?
By the way, if you were wondering what happened
to the other barrier.
Fulton was completed this winter as a full span
roughened channel opening unimpeded passage to
the entire Chewuch River.
Write a Comment
User Comments (0)
About PowerShow.com