Title: COST AS AN INDEPENDENT VARIABLE CAIV Information Briefing
1COST AS AN INDEPENDENT VARIABLE (CAIV)
Information Briefing
Jeffery Bongard x72042 DRM, Cost Analysis
Division
2WHAT IS CAIV?
- CAIV simply means making performance and schedule
a function of available (budgeted) resources - Three program parameters
- SCHEDULE
- PERFORMANCE
- COST (PRICE)
- Two of these variables must depend on the third
- CAIV requires performance based contracting
- Requires user/developer participation in Cost
Performance Integrated Product Teams (CPIPTs)
3 WHY CAIV WILL WORK ?
- DoD SHIFT TO PERFORMANCE SPECS
- Requirements Stating Basic Warfighter Needs ---
Not Detailed Designs/Mfg Processes - Provides Necessary Trade Flexibility Without
- Compromising Basic Objectives
- MilSpec Reform
- Adoption of COTS and Commercial Practices
- SHIFT TO IPT MANAGEMENT APPROACH
- BUDGET REALITIES/CHANGED THREAT
- Provides the Compelling Need
- We Have No Other Choice
4 WHAT TO EXPECT FROM CAIV?
- Substantial Reductions in the Cost of DoD
Products (e.g. 2-to-1 or better) - Shorter Program Cycle Times
- Clearer, Innovative Design, Manufacturing,
Support and Contracting Approaches - Quality Products that Fully Meet the Warfighters
True Needs
5KEY CAIV INGREDIENTS
- Establish thresholds and objectives in
Performance Requirements - Implement Integrated Product Teams (IPTs)
- Continuous search for tradeoff opportunities
SETTING REALISTIC BUT AGGRESSIVE COST OBJECTIVES
THROUGHOUT THE LIFE CYCLE
6CAIV IN THE REQUIREMENTS PROCESS
- PERFORMANCE REQUIREMENTS
- Thresholds are the minimum acceptable system
characteristics or capabilities - Key Performance Parameters (KPPs)
- Non-KPPs
- Objectives include desired/preferred
characteristics/capabilities above thresholds
KEY CONCEPT TRADE SPACE EXISTS BETWEEN THRESHOLD
AND OBJECTIVE VALUES FOR KPPs AND NON-KPPs
7EVALUATING TRADESPACE
Possible significant advantage
Possible significant advantage
OBJ1
OBJ3
Possible advantage
Possible advantage
TRADESPACE
TRADESPACE
KPP1
KPP2
NON- KPP3
Possible advantage
Possible trade-offs but viewed as disadvantage
8CAIV IPTs
- INTEGRATED PRODUCT TEAMS (IPTs)
- Multidisciplinary work teams comprised of all
essential acquisition activities to optimize the
design, manufacturing and supportability
processes - Through cooperation, teams must be empowered to
make sound and timely decisions
9CONTINUOUS SEARCH FOR TRADE OFF OPPORTUNITIES
CONTINUOUS SEARCH FOR TRADE OFF OPPORTUNITIES
- Aggressive cost goals are needed at program
inception and pre-ORD stage - Program manager and contractors must be empowered
to make trades during all phases of the program - Program plans should incentivize this process
- Technological advances, competitive forces, and
well structured incentives evoke cost reduction
on a continuous basis throughout the life cycle!
10RISK AREAS FOR IPT CONSIDERATION
- Starting EMD/Production with designs dependent on
Immature Technology - Failure to address product manufacturability
early - Failure to address supportability considerations
early - Allowing Edge-of-the-Envelope Performance
Requirements to become sacred - Designing for the ultimate, accepting the
resulting cost as a necessary consequence
Executing CAIV Addresses The Cost Impact of Risks
11CAIV IMPLEMENTATION EXAMPLES
- SINGARS - Established a price ceiling for unit
production cost - JSTARS - Established a price ceiling for unit
production cost - UM - Established first year spending limit due to
PMs funding shortfall - Firefinder Block II - Established CAIV target
weapon system unit cost during EMD and Production
phases - Combat ID Dismounted Soldier (CIDDS) -
Established a CAIV target weapon system unit cost
during production. Minimum preferred desired
requirements used as evaluation factors on Source
Selection -
12SINGARS
- Maximum unit cost established for enhancements to
radio - Use of modeling and simulation via communication
network aided in establishing common baseline for
contractors to explore design alternatives - Redesign opportunities and state of the art
manufacturing technologies resulted in - development of radio 1/2 the size and weight of
the existing radio with improved reliability - 140 million cost savings
13FIREFINDER BLOCK II SOW
- Contractor shall provide auditable Weapon System
Unit Cost based on Government Production CAIV
target - First Unit Cost, learning methodology used, and
Avg. Unit Cost for each year to be identified and
explained. - If CAIV Current Estimate exceeds CAIV Target,
contractor shall provide alternatives and
recommendations for potential tradeoffs.
14FIREFINDER BLOCK II SOW (CONT)
- CAIV Target vs. current estimates discussed at
IPT meetings. - If change projected to OS baseline established
by government, contractor will identify cause (s)
and impact and provide alternatives and
recommendations for possible trade-offs. - Contractor will generate data using life cycle
cost model and submit CAIV report to document
results of CAIV efforts.
15FIREFINDER BLOCK II SECTION L
- AFFORDABILITY- Offeror shall
- Provide EMD funding profile by fiscal years
- Provide all assumptions, methodologies,
performance trades, and supporting rationale for
achieving the Production Weapon System Unit cost.
- Identify CAIV cost and detail the management
plans and techniques to monitor and control. - Provide narrative on proposed design and
maintenance concept to minimize OS costs.
16FIREFINDER BLOCK II SECTION M
- Affordability evaluated by assessing
- feasibility and degree of compliance to projected
EMD funding requirements per year. - reasonableness of the offerors CAIV assumptions
and methodologies considering the proposed cost
of the EMD system. - OS cost impacts associated with offerors
proposed approach.
17CIDDS KPPs
18CIDDS NON-KPPs (preferred)
19CIDDS OBJECTIVE REQUIREMENTS (desired)
20CIDDS SECTION M
- Performance does not meet minimum requirement
(KPP) - rated a deficiency - Performance meets or exceeds a preferred
requirement (non-KPP) - rated an advantage or a
significant advantage - Performance does not meet a preferred requirement
(non-KPP) - rated a disadvantage - Performance meets a desired requirement
(objective) - rated an advantage
21WHERE ARE WE NOW?
- CAIV TRAINING EMPHASIS
- IPT ROLE
- PERFORMANCE BASED CONTRACTING
- INCENTIVES AND VE
- FORMAL CHARTERS FOR IPTs
- NEEDED
- TOTAL OWNERSHIP COST (TOC) -
- ROADSHOW VII (AUG 98)
- METRICS NEEDED
- FOR SUCCESS
22WHAT CAN YOU DO?
- PREVENT/AVOID REQUIREMENTS TAKING ON A LIFE OF
THEIR OWN - Look for tradeoff OPPORTUNITIES
- Better, Quicker, Cheaper
- KEEP PROGRAMS AFFORDABLE
- User wants / industry provides
- Are the appetite SUPPRESSER
OR
23WHAT CAN YOU DO?
- CONSIDER COST AS THE INDEPENDENT VARIABLE
- Design for Low Life Cycle Cost from the Start
- DONT AUTOMATICALLY SETTLE FOR LOWER PERFORMANCE
- Use Your Entire Team - Govt Industry IPT
- Be Innovative
- Be Creative
- Most Importantly, Start Implementing!!
24POINT OF CONTACTS
- Jeffery Bongard
- Jeffery.Bongard_at_mail1.
- monmouth.army.mil
- 732 - 427 - 2042
- DSN 987 - 2042
- Robert F. Dow, Jr.
- Robert.Dow_at_mail1.
- monmouth.army.mil
- 732-427-2733
- DSN 987-2733