Title: PRETENDER PLANNING
1PRE-TENDER PLANNING
2WHEN TO FLOAT TENDER
- Float tender when you are Ready to Execute.
- Clause 36(3) of GCC-If suspension is more than 3
months at a time .. The contractor may treat it
as an abandon of the contract by the Railway.
3CALLING OF TENDER BEFORE SANCTION OF ESTIMATE
- In extremely urgent cases with prior concurrence
of Associate Finance and personal approval of - DRM for works costing upto Rs. 50 lakhs
- PHOD for works costing upto Rs. 1 crore
- GM for works costing more than Rs. 1 crore
- Sanction of detailed Estimate is necessary before
award of contract - REF Bds Lr. No. 94/CE-I/Ct/4 dt. 17.9.97
4STAGES IN PRE-TENDER PLANNING
- Site Survey
- Scope of Tender
- Design
- Drawings
- Selection of items
- Rate Analysis
- Assessment of Quantity
5STAGES IN PRE-TENDER PLANNING
- Preparation of Schedule
- Time of completion
- Type of tender
- Tender conditions other tender documents
- Eligibility Conditions
- Notice Inviting Tender
6SITE SURVEY
- Topography
- Ground conditions including soil and drainage
- Existing structures and their disposal
- Access to site
- Space for keeping material, camp etc.
- Availability of material
7SITE SURVEY
- Availability of skilled and unskilled labour
- Transport arrangement
- Local restriction forest,traffic etc.
- Local body regulations
- Disposal of construction waste
8CONSIDERATIONS FOR DECIDING SCOPE OF TENDER
- Geographical suitability
- Technical feasibility
- Availability of contractors their financial and
technical competence - Economics of scale
- Tender Value
- Risk involved
- Fund availability
9DESIGN
- Design should cater to the requirement of user.
- Design should take into account the constraints
of site. - Design should be executable and, normally, there
should be no need for changes during execution. - Design should utilise local and commonly
available materials to the extent possible. - Special precaution to be observed should be
highlighted.
10DRAWINGS
- Should be available in time for estimation,
tendering and execution - Should be sufficient in detail
- Should conform to specifications and special
conditions - Approval of other departments should be taken
wherever required.
11PREPARATION OF SCHEDULE
- If possible select from master schedule
- Language to be simple
- Meaning of words to be taken as in trade
- Description of items to correlate with
specifications - Description should avoid expressions like as
required/ as necessary. - Testing requirement and acceptance criteria to be
clearly indicated.
12PREPARATION OF SCHEDULE
- Dismantling and removing of existing track
including turnouts of any classification,including
hauling of materials such as rails,sleepers(excep
t concrete sleepers) and fittings etc. as per the
direction of Rly.Engineer including dismantling
of concrete / masonary foundations with all
contractors labour, materials,transport
arrangement ,tools and plants etc.(Note Payment
shall be released after material is transported
and stacked in Rlys Depot)
13PREPARATION OF SCHEDULE
- Due care should be taken while incorporating NS
Items no ambiguityattributes, specifications
and system of measurements to be laid down
adequately. - Normally rate should be inclusive of only those
activities which have been considered in rate
analysis - Generally, rate should not be sweeping-incl. Of
all lead, lift,crossing of lines etc.Specify
lead etc.Pay for extra - No overlap ( of activities etc)
14NINETY FIVE PERCENT SYNDROME
- Contractors complete major items of work
amounting to about 95 of contract value but tend
to avoid/delay minor finishing works which cost
about 5 of contract value. - Frame payment conditions to link and hold part of
payment of related main item(s) of work with
execution of these items.
15RATE ANALYSIS
- Take all activities of an item of work in account
- Take reasonable wastages of material and labour
into account - Incorporate all taxes/cess required to be paid
- If based on LARs take into consideration
- Location
- Currency
- Else, Base on current market rates
16RATE ANALYSIS
- Rate Analysis should correspond to the process
specified for execution. - Explore possibility of linking rate of supply
items with inflation. - Why not re-imburse taxes paid than have rates
inclusive of all taxes?
17ASSESSMENT OF QUANTITY
- Realistic assessment of quantities based on site
conditions and design/drawings - If practical, give location-wise quantities in
schedule - Units and method of measurement should be
indicated in unambiguous words - Avoid any unnecessary statements
18TENDER SCHEDULE
- These tender schedules may be approved by the
JAG/SAG officers.Vetting of tender schedule
should be necessary only in the rare urgent cases
where tenders are called without sanction of
detailed estimate.Pre-vetting will also not be
necessary in case of zonal works and revenue
works in Open-Line for which detailed estimates
are not to be framed. - System of indicating rates for individual items
in the schedule and asking the tenderer to quote
a common percentage for all the items in a
schedule/all schedules may be preferred
where-ever possible.
19TIME OF COMPLETION
- Should be reasonable
- Should take into account mobilisation time,
weather, availability of labour, clearances
required, diversion of utilities - To be workes out depending on the proposed
methodology for execution - Time frame for Railway to supply land, drawings,
materials etc. to be indicated ?
20TIME OF COMPLETION
- The work should be split into activities for
assessment of time required for execution - Apart from overall completion time milestones can
also be indicated in tender - May prescribe minimum number of men and machines
required to achieve the targets
21TENDER CONDITIONS
- Be careful with use of words e.g. summarily
rejected/liable for rejection. - Specify scope
- Specify site conditions
- Contractor to visit site before tendering
(undertaking) - Validity of Tender
- Meaning should be clear and unambiguous
22TENDER CONDITIONS
- Cost of work indicated in tender should be
realistic. - Tender to be floated For and on behalf of
President of India.
23CONTRACT CONDITIONS
- Normally in case of conflict
- Spl Conditions prevail over GCC
- Spl Specifications prevail over
Std.Specifications - Foot notes below items of work/schedule prevail
over Std. Specifications - This is to be clearly stated in the tender
document.
24SAMPLES OF TENDER CONDITIONS
- The General Conditions of Contract.with up-to
date correction slips shall form part of the
Contract. - The plain cement concrete and reinforced cement
concrete shall be carried out in accordance with
Indian Railway Standard Concrete Bridge Code 1960
with Correction Slips issued from time to time.
25CONTRACT CONDITIONS
- Conditions should be specificshould not be
open-ended. - Suitably organised repeatition to be avoided
- Details of Statutory clearances, taxes etc.,
should be clearly indicated - Liability of tenderer to be clearly indicated
- Mechanism for dealing with change.
26CONTRACT CONDITIONS
- In cases involving advance payments to private
firms, the agreement should invariably contain
penalty clause and payment of liquidated damages
by defaulting firm by way of interest on the
money advanced to it. (Bds Lr.No. 58-B (
C)2498/II/7th Report dt 12-6-56 )
27SPECIAL CONDITIONS GENERAL
- Before calling the tenders for highly specialised
work the special conditions for carrying out the
special work should invariably be got approved
from Headquarters office.(RefBds Lr.
No.99/CE-I/CT/43 dt,5.8.99 - Maintenance Period scope of maintenance (items
covered under maintenance,conditions) - Construction and Maintenance of service roads
- Responsibility of setting out
- Disposal of dismantled debris
- Methods of Measurement
- Hidden measurements
28SPECIAL CONDITIONS GENERAL
- Tests
- Organisations from whom test certificate/results
are acceptable - Procedure for collection and sending of samples
- Explosives
- Procurement
- Transport
- Storage
- Regulations for Blasting.
29SPECIAL CONDITIONS GENERAL
- Tools and Plants to be hired from Railway
- Which machines can be offered on hire. No
obligation - Railways Driver/Operator
- Hire Charges Inclusive of consumable store?
- Period for charges Actual days uses or whole
period ?
30SPECIAL CONDITIONS GENERAL
- Site Facilities
- Land
- Electricity Water
- Availability
- Charges, Terms
- Liability in case of non-supply, delayed supply
etc.
31SPECIAL CONDITIONS SUPPLY OF MATERIAL BY
RAILWAY
- Which materials to be supplied by Railway
- Free of Cost/On chargesspecify charges
- Store from which material will be supplied
- Store to which material can be returned
- Assessment of weight as per standard weight or
as per actuals ?
32SPECIAL CONDITIONS SUPPLY OF MATERIAL BY
RAILWAY
- Length of rods to be supplied
- Wastage Permitted
- Disposal of wastage
- Rate for Recovery
- Safety and Custody of Material
33SPECIAL CONDITIONS FOR P.WAY CONTRACTS
- Progress of Work
- Program of work
- Speed Restriction
- Agreed Damages for Poor Progress (.to be
included after careful thought..) - Method for execution
- Caution order
- Traffic block
- Speed Restriction
34SPECIAL CONDITIONS FOR P.WAY CONTRACTS
- Quality Standards at various stages of progress
- Alignment Level
- Disposal of muck
- Track Parameters and Tolerances
- Weight of P-Way material
- Safe Working Practices.
35SAFE WORKING PRACTICES (PARA 826 OF IRPWM)
- Contractor not to start work in absence of Rly
Supervisor - Road vehicles/machinery not to cause infringement
Demarcate/Barricade - Contractors supervisor/Workmen to be counseled.
Certificate to Supervisor. - Unloaded material to be kept clear of moving
dimension and stacked.
36P-WAY CONTRACTSLIABILITY OF CONTRACTOR
- Speed Restriction
- Detention to Trains
- Accident
37SPECIAL CONDITIONS FOR P.WAY CONTRACTS
- Tools and Plants
- Materials
- Receipt
- Transportation
- Storage
- Security
- Indemnity/Bank Guarantee
38- Released material
- Prior survey
- Day to day safe custody
- Periodical accountal
- Night working
- Maintenance Period
39SPECIAL CONDITIONS FOR EARTHWORK
- List of specifications to be followed
- Significance of Guidelines for Earthwork
- Method to be prescribed for compaction
- Method to be prescribed for stacking of
cut-spoils - Allowance for shrinkage
- Slope for embankment and cutting
- Blanketting Materialprocess of blending etc.
- What if specified degree of compaction is not
achieved ?
40SPECIAL CONDITIONS FOR EARTHWORK
- Method of classification of soil
- Method of measurements
- Dealing with extra cuttings
- Tests and Acceptance Criteria
- Precautions during execution
- Conditions for use of explosives
41SPECIFICATIONS
- Avoid Non-Quantitative works like superior, to
the satisfaction of engineer etc. - Avoid specifications which cannot be estimated
- Avoid specifying a sole source
- Specify testing requirements and acceptance
criteria - Reference to Codes/Manuals.
- Mechanism to deal if specifications are not met.