PRETENDER PLANNING - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

PRETENDER PLANNING

Description:

Clause 36(3) of GCC-If suspension is more than 3 months at a time . Why not re-imburse' taxes paid than have rates inclusive of all taxes? ASSESSMENT OF QUANTITY ... – PowerPoint PPT presentation

Number of Views:954
Avg rating:3.0/5.0
Slides: 42
Provided by: LATA
Category:

less

Transcript and Presenter's Notes

Title: PRETENDER PLANNING


1
PRE-TENDER PLANNING
2
WHEN TO FLOAT TENDER
  • Float tender when you are Ready to Execute.
  • Clause 36(3) of GCC-If suspension is more than 3
    months at a time .. The contractor may treat it
    as an abandon of the contract by the Railway.

3
CALLING OF TENDER BEFORE SANCTION OF ESTIMATE
  • In extremely urgent cases with prior concurrence
    of Associate Finance and personal approval of
  • DRM for works costing upto Rs. 50 lakhs
  • PHOD for works costing upto Rs. 1 crore
  • GM for works costing more than Rs. 1 crore
  • Sanction of detailed Estimate is necessary before
    award of contract
  • REF Bds Lr. No. 94/CE-I/Ct/4 dt. 17.9.97

4
STAGES IN PRE-TENDER PLANNING
  • Site Survey
  • Scope of Tender
  • Design
  • Drawings
  • Selection of items
  • Rate Analysis
  • Assessment of Quantity

5
STAGES IN PRE-TENDER PLANNING
  • Preparation of Schedule
  • Time of completion
  • Type of tender
  • Tender conditions other tender documents
  • Eligibility Conditions
  • Notice Inviting Tender

6
SITE SURVEY
  • Topography
  • Ground conditions including soil and drainage
  • Existing structures and their disposal
  • Access to site
  • Space for keeping material, camp etc.
  • Availability of material

7
SITE SURVEY
  • Availability of skilled and unskilled labour
  • Transport arrangement
  • Local restriction forest,traffic etc.
  • Local body regulations
  • Disposal of construction waste

8
CONSIDERATIONS FOR DECIDING SCOPE OF TENDER
  • Geographical suitability
  • Technical feasibility
  • Availability of contractors their financial and
    technical competence
  • Economics of scale
  • Tender Value
  • Risk involved
  • Fund availability

9
DESIGN
  • Design should cater to the requirement of user.
  • Design should take into account the constraints
    of site.
  • Design should be executable and, normally, there
    should be no need for changes during execution.
  • Design should utilise local and commonly
    available materials to the extent possible.
  • Special precaution to be observed should be
    highlighted.

10
DRAWINGS
  • Should be available in time for estimation,
    tendering and execution
  • Should be sufficient in detail
  • Should conform to specifications and special
    conditions
  • Approval of other departments should be taken
    wherever required.

11
PREPARATION OF SCHEDULE
  • If possible select from master schedule
  • Language to be simple
  • Meaning of words to be taken as in trade
  • Description of items to correlate with
    specifications
  • Description should avoid expressions like as
    required/ as necessary.
  • Testing requirement and acceptance criteria to be
    clearly indicated.

12
PREPARATION OF SCHEDULE
  • Dismantling and removing of existing track
    including turnouts of any classification,including
    hauling of materials such as rails,sleepers(excep
    t concrete sleepers) and fittings etc. as per the
    direction of Rly.Engineer including dismantling
    of concrete / masonary foundations with all
    contractors labour, materials,transport
    arrangement ,tools and plants etc.(Note Payment
    shall be released after material is transported
    and stacked in Rlys Depot)

13
PREPARATION OF SCHEDULE
  • Due care should be taken while incorporating NS
    Items no ambiguityattributes, specifications
    and system of measurements to be laid down
    adequately.
  • Normally rate should be inclusive of only those
    activities which have been considered in rate
    analysis
  • Generally, rate should not be sweeping-incl. Of
    all lead, lift,crossing of lines etc.Specify
    lead etc.Pay for extra
  • No overlap ( of activities etc)

14
NINETY FIVE PERCENT SYNDROME
  • Contractors complete major items of work
    amounting to about 95 of contract value but tend
    to avoid/delay minor finishing works which cost
    about 5 of contract value.
  • Frame payment conditions to link and hold part of
    payment of related main item(s) of work with
    execution of these items.

15
RATE ANALYSIS
  • Take all activities of an item of work in account
  • Take reasonable wastages of material and labour
    into account
  • Incorporate all taxes/cess required to be paid
  • If based on LARs take into consideration
  • Location
  • Currency
  • Else, Base on current market rates

16
RATE ANALYSIS
  • Rate Analysis should correspond to the process
    specified for execution.
  • Explore possibility of linking rate of supply
    items with inflation.
  • Why not re-imburse taxes paid than have rates
    inclusive of all taxes?

17
ASSESSMENT OF QUANTITY
  • Realistic assessment of quantities based on site
    conditions and design/drawings
  • If practical, give location-wise quantities in
    schedule
  • Units and method of measurement should be
    indicated in unambiguous words
  • Avoid any unnecessary statements

18
TENDER SCHEDULE
  • These tender schedules may be approved by the
    JAG/SAG officers.Vetting of tender schedule
    should be necessary only in the rare urgent cases
    where tenders are called without sanction of
    detailed estimate.Pre-vetting will also not be
    necessary in case of zonal works and revenue
    works in Open-Line for which detailed estimates
    are not to be framed.
  • System of indicating rates for individual items
    in the schedule and asking the tenderer to quote
    a common percentage for all the items in a
    schedule/all schedules may be preferred
    where-ever possible.

19
TIME OF COMPLETION
  • Should be reasonable
  • Should take into account mobilisation time,
    weather, availability of labour, clearances
    required, diversion of utilities
  • To be workes out depending on the proposed
    methodology for execution
  • Time frame for Railway to supply land, drawings,
    materials etc. to be indicated ?

20
TIME OF COMPLETION
  • The work should be split into activities for
    assessment of time required for execution
  • Apart from overall completion time milestones can
    also be indicated in tender
  • May prescribe minimum number of men and machines
    required to achieve the targets

21
TENDER CONDITIONS
  • Be careful with use of words e.g. summarily
    rejected/liable for rejection.
  • Specify scope
  • Specify site conditions
  • Contractor to visit site before tendering
    (undertaking)
  • Validity of Tender
  • Meaning should be clear and unambiguous

22
TENDER CONDITIONS
  • Cost of work indicated in tender should be
    realistic.
  • Tender to be floated For and on behalf of
    President of India.

23
CONTRACT CONDITIONS
  • Normally in case of conflict
  • Spl Conditions prevail over GCC
  • Spl Specifications prevail over
    Std.Specifications
  • Foot notes below items of work/schedule prevail
    over Std. Specifications
  • This is to be clearly stated in the tender
    document.

24
SAMPLES OF TENDER CONDITIONS
  • The General Conditions of Contract.with up-to
    date correction slips shall form part of the
    Contract.
  • The plain cement concrete and reinforced cement
    concrete shall be carried out in accordance with
    Indian Railway Standard Concrete Bridge Code 1960
    with Correction Slips issued from time to time.

25
CONTRACT CONDITIONS
  • Conditions should be specificshould not be
    open-ended.
  • Suitably organised repeatition to be avoided
  • Details of Statutory clearances, taxes etc.,
    should be clearly indicated
  • Liability of tenderer to be clearly indicated
  • Mechanism for dealing with change.

26
CONTRACT CONDITIONS
  • In cases involving advance payments to private
    firms, the agreement should invariably contain
    penalty clause and payment of liquidated damages
    by defaulting firm by way of interest on the
    money advanced to it. (Bds Lr.No. 58-B (
    C)2498/II/7th Report dt 12-6-56 )

27
SPECIAL CONDITIONS GENERAL
  • Before calling the tenders for highly specialised
    work the special conditions for carrying out the
    special work should invariably be got approved
    from Headquarters office.(RefBds Lr.
    No.99/CE-I/CT/43 dt,5.8.99
  • Maintenance Period scope of maintenance (items
    covered under maintenance,conditions)
  • Construction and Maintenance of service roads
  • Responsibility of setting out
  • Disposal of dismantled debris
  • Methods of Measurement
  • Hidden measurements

28
SPECIAL CONDITIONS GENERAL
  • Tests
  • Organisations from whom test certificate/results
    are acceptable
  • Procedure for collection and sending of samples
  • Explosives
  • Procurement
  • Transport
  • Storage
  • Regulations for Blasting.

29
SPECIAL CONDITIONS GENERAL
  • Tools and Plants to be hired from Railway
  • Which machines can be offered on hire. No
    obligation
  • Railways Driver/Operator
  • Hire Charges Inclusive of consumable store?
  • Period for charges Actual days uses or whole
    period ?

30
SPECIAL CONDITIONS GENERAL
  • Site Facilities
  • Land
  • Electricity Water
  • Availability
  • Charges, Terms
  • Liability in case of non-supply, delayed supply
    etc.

31
SPECIAL CONDITIONS SUPPLY OF MATERIAL BY
RAILWAY
  • Which materials to be supplied by Railway
  • Free of Cost/On chargesspecify charges
  • Store from which material will be supplied
  • Store to which material can be returned
  • Assessment of weight as per standard weight or
    as per actuals ?

32
SPECIAL CONDITIONS SUPPLY OF MATERIAL BY
RAILWAY
  • Length of rods to be supplied
  • Wastage Permitted
  • Disposal of wastage
  • Rate for Recovery
  • Safety and Custody of Material

33
SPECIAL CONDITIONS FOR P.WAY CONTRACTS
  • Progress of Work
  • Program of work
  • Speed Restriction
  • Agreed Damages for Poor Progress (.to be
    included after careful thought..)
  • Method for execution
  • Caution order
  • Traffic block
  • Speed Restriction

34
SPECIAL CONDITIONS FOR P.WAY CONTRACTS
  • Quality Standards at various stages of progress
  • Alignment Level
  • Disposal of muck
  • Track Parameters and Tolerances
  • Weight of P-Way material
  • Safe Working Practices.

35
SAFE WORKING PRACTICES (PARA 826 OF IRPWM)
  • Contractor not to start work in absence of Rly
    Supervisor
  • Road vehicles/machinery not to cause infringement
    Demarcate/Barricade
  • Contractors supervisor/Workmen to be counseled.
    Certificate to Supervisor.
  • Unloaded material to be kept clear of moving
    dimension and stacked.

36
P-WAY CONTRACTSLIABILITY OF CONTRACTOR
  • Speed Restriction
  • Detention to Trains
  • Accident

37
SPECIAL CONDITIONS FOR P.WAY CONTRACTS
  • Tools and Plants
  • Materials
  • Receipt
  • Transportation
  • Storage
  • Security
  • Indemnity/Bank Guarantee

38
  • Released material
  • Prior survey
  • Day to day safe custody
  • Periodical accountal
  • Night working
  • Maintenance Period

39
SPECIAL CONDITIONS FOR EARTHWORK
  • List of specifications to be followed
  • Significance of Guidelines for Earthwork
  • Method to be prescribed for compaction
  • Method to be prescribed for stacking of
    cut-spoils
  • Allowance for shrinkage
  • Slope for embankment and cutting
  • Blanketting Materialprocess of blending etc.
  • What if specified degree of compaction is not
    achieved ?

40
SPECIAL CONDITIONS FOR EARTHWORK
  • Method of classification of soil
  • Method of measurements
  • Dealing with extra cuttings
  • Tests and Acceptance Criteria
  • Precautions during execution
  • Conditions for use of explosives

41
SPECIFICATIONS
  • Avoid Non-Quantitative works like superior, to
    the satisfaction of engineer etc.
  • Avoid specifications which cannot be estimated
  • Avoid specifying a sole source
  • Specify testing requirements and acceptance
    criteria
  • Reference to Codes/Manuals.
  • Mechanism to deal if specifications are not met.
Write a Comment
User Comments (0)
About PowerShow.com