Title: Reaction Control System
1Section 21 Reaction Control System
. . . Michael McCullough Swales Aerospace, Inc.
2Contents
- System Overview
- Test Verification Matrix
- Component and Subsystem Level Testing
- System Level Testing
- Subsystem Level Reviews
- Status of Launch Site Procedures
- Status of Launch Site GSE
- Open Problem Records and Residual Risk
- System Readiness
3Reaction Control System
4EO-1 RCS Performance Requirements
- Documented in SAI-SPEC-110, released March 27,
1997 - Propellant capacity 22.3 kg
- System mass not to exceed 11 kg
- Thrusters provide velocity control for S/C
- Thrusters provide attitude control authority
during D V - Thrusters meet performance specification of OAC
MR-103G - System must meet requirements of EWR 127-1
5Verification Matrix
21 - 5
6Accumulated Power On Time for EO-1 S/C
Components
7RCS Verification Matrix Items
- Alignment - by Analysis
- Thruster alignment maintained by control of
manufacturing tolerances - Static Load - Qualification by Similarity
- Proof Pressure - Test
- Proof Pressure Tests conducted at component and
subsystem level - Mass Properties - Weighed
- Weighed at the subsystem level including Zenith
Deck - Interface Verification - Test
- Interfaces tested during spacecraft IT process
- Functional - Test
- Tested at the component and subsystem Level
8RCS Component Verification
- Propellant Tank
- Determination of Volume
- Proof Pressure Test
- Internal and External Leakage Test
- Radiographic/Penetrant Inspection
- Visual Inspection and Cleanliness
- Fill/Drain Valves
- Inspection and Cleanliness
- Proof Pressure
- Internal and External Leakage
- Operational Cycles
- Filter
- Proof Pressure Test
- External Leakage
- Bubble Point and D-P
- Visual Inspection and Cleanliness
- Latch Valve
- Internal and External Leakage Test
- Operating Cycles
- Visual Inspection and Cleanliness
- Vibration
- Thrusters
- Hot Fire Performance
- Proof Pressure, Vibration
- Internal and External Leakage
- Pull-In and Drop-Out Voltage
- Visual Inspection and Cleanliness
- Pressure Transducer
- Vibration and Proof Pressure Test
- Calibration
- Electrical Characteristics
9RCS Verification at Primex
- System Welds
- Leak Checked, Dye Penetrant and Radiographic
Inspection - Proof Pressure Checks
- High Pressure Proof Pressure Test (820 psig)
excl. Tank - Complete System Proof Pressure Test (480 psig)
- Internal Valve Leak Checks
- Thruster and Latch Valve Seats Checked
Individually - Electrical Component Resistance and Isolation
Checks - System Level Functional Checks
- Thrusters, Latch Valve, Pressure Transducer and
Thermostats
10RCS Checks at Swales
- Electrical Component Resistance and Isolation
Checks - System Integration with Spacecraft
- System Level Functional Checks
- Pre- and Post-Integration
- Thrusters, Latch Valve, Pressure Transducer,
Thermostats and Thermistors - Thruster Phasing with Gas Flow at 15 psig
11RCS Environmental Test Program
- The EO-1 RCS was fully integrated with the
spacecraft for Shock, Vibration and Acoustic
Testing - RCS Functionality verified during CPT 5
- arcs1.prc - exercised thruster valves
- arcs2.prc - powered catalyst bed heaters
- arcs3.prc - exercised the latch valve
- RCS Integrity verified during Pressure Transducer
Calibration and Valve Leak Checks - Thermal Vacuum / Thermal Balance Testing Verified
Proper Operation of the RCS Thermal Control
System. - Temperatures maintained between 18C-24C during
cold case tests - No heater activity during hot case testing
12RCS Thermal Control (1)
13RCS Thermal Control (2)
14RCS Pressure Transducer Calibration
- End-to-end Test Performed, Propellant Tank to
Ground System Display - No Change in Scale Factor
- 100 psi/volt
- Offset Adjusted by 1.3 psi
- No Hysteresis
- 2 Counts Maximum Error
- 0.2 FS
- Calibration will be repeated as part of Launch
Site Processing
15RCS Internal Leak Check
- Performed Internal Leak Check on All RCS Valves
- Series Redundant Valve Seats Checked Individually
- Checked At MEOP (320 psig)
- Total of 9 Valve Seats Checked
- System Level Performance is Acceptable
- Leak Check of Fill/Drain Valves Added to System
Level Test in Response to RFA 14.27 - Next System Flight Level Pressurization Test
Planned as Part of Launch Site Processing
16RCS Pressure Cycle Log
17Technical Peer Reviews
- Series of Requirements and Design Reviews
Conducted at Primex Aerospace - Attended by SAI Lead Engineers for Mechanical,
Electrical, Stress and Thermal Subsystems, QA,
S/C Systems, and Program Manager - EO-1 RCS Requirements Review
- January 21-22, 1997, Primex Handout 97-H-2355
- EO-1 RCS Preliminary Design TIM
- April 3-4, 1997, Primex Handout 97-H-2376
- EO-1 RCS Critical Design Review
- June 3-4, 1997, Primex Handout 97-H-2391
- EO-1 RCS Pre-Ship Review
- March 3, 1998, Data Package P/N 33400-965
18PSR RFA Status
- Three RFA Issued During EO-1 Spacecraft Pre-Ship
Review - RFA 14.17
- Completed
- RFA 14.27
- Completed
- RFA 14.28
- Completed
19RFA 14.17
- Specific Request RCS valve leakage criteria
should be revised lower (100 scc/hr is too high)
and leak rate for out of spec valve should be
trended. - Supporting Rationale I believe any valve leaking
at 100 scc/hr is so far out of family that it
should be replaced. If the out of spec valve
remains stable, it is probably OK. However, if
its leak rate increases significantly, it should
be replaced. - Project Response Valve leak rate acceptance
criteria revised downward to 30 scc/hr. Leakage
in excess of this rate shall be cause to review
flight worthiness and launch site latch valve
usage. SAI-PROC-309 revised to reflect new leak
rate criteria and capture requirement for review
of launch site procedures.
20RFA 14.27
- Specific Request Leak test fill and drain valves
(at least primary seals) - Supporting Rationale Cycling fill and drain
valves on the ground can potentially introduce
contaminants into seals and cause leakage. Leak
testing valves requires minimum resources and
time and adds significant assurance to mission
success. - Project Response SAI-PROC-309 has been revised
to include a leak check on RCS fill and drain
valves. This test will be conducted at the Range
as part of the next scheduled RCS valve leak
check.
21RFA 14.28
- Specific Request Perform a post environmental
leakage test on the propulsion system.
Recommendation pressurize with GN2 to TBD psia
monitor pressure decay for longest duration
possible. - Supporting Rationale
- 1. The integrity of the welds, lines, components
of the propulsion subsystem has not been verified
after being stressed by environmental tests. - 2. Discovery of leakage during propellant loading
ops is much too late in the timeline. Leakage
after loading hydrazine poses safety hazard to
personnel. - 3. With the delay in launch schedule, monitoring
pressure for decay test may be feasible over 3-4
months. - Project Response The RCS has been pressurized to
40 psi (maximum allowed by DOT regulations) and
pressure decay is being monitored. Pressure
decay check will continue through until
propellant loading, approximately two months.
22Failure Free Operation Time
- No failures of RCS encountered during S/C IT
program - Total operating time
- Pressure transducer powered on with S/C
- Thruster and latch valve actuation limited to
select ACS phasing and S/C comprehensive tests - No configuration changes required
- No changes required in Test Plan
- No hardware or software changes required
23RCS Launch Site Procedure Status
- Two procedures considered hazardous by NASA/KSC
and air force 30SW - review and approval required - RCS checkout and leak test procedure SAI-PROC-309
- Hazardous due to pressures involved
- Submitted to range for comment
- Comments incorporated
- Ready for final range review approval
- EO-1/SAC-C propellant loading procedure PAC
IP-0645 - Hazardous due to propellants and pressures
involved - Submitted to range for comment
- Comments incorporated - TIM held to discuss
details - Final approval contingent on facility selection
24RCS Ground Support Equipment Status
- Propellant loading cart has been demonstrated
using PAC Procedure IP-0645 - Pressure test console and all associated
equipment has been calibrated and / or
proof-tested and will remain valid throughout the
launch campaign - Portable pressure monitor unit has been
functionally demonstrated - All export / ITAR issues associated with SAC-C
propellant loading have been resolved - SCAPE / PHE and Interscan training will be
accomplished shortly after arrival at the launch
site - Range safety has reviewed GSE design documented
in the EO-1 MSPSP SAI-SFTY-019 submitted to the
range 10/26/99 - Previewed by range safety prior to official
submittal
25RCS Statement of Readiness
- The EO-1 Reaction Control System is ready for
launch site processing - System integrity, performance and functionality
has been demonstrated - The EO-1 RCS Launch Site Procedures are ready for
launch site operations - Procedures have been demonstrated using GSE
- There are no obstacles to procedure approval by
the Western Range - The EO-1 RCS GSE is ready to support launch site
processing - Primex is ready to support EO-1 / SAC-C
propellant loading
26Problem Records and Residual Risk
- Problem Records
- No Critical Problem Records
- No Open Problem Records
- Residual Risk Items
- None
- Potential Redbook Items
- None
27Special Topic Leak Rate in RCS Valve
. . . Michael McCullough Swales Aerospace, Inc.
28Thruster Valve Leakage
- History - During RCS thruster valve leak checks,
one thruster (4) displayed unexpectedly high
leakage through the downstream valve seat. 13
scc/hr observed, 1 scc/hr expected. - Possible Cause - Valve seat contamination,
perhaps catalyst fines. - All testing has been performed with positive gas
flow during thruster valve cycling - Catalyst beds are below valve seats, limits the
opportunity for contaminants to percolate down
into valve seats
29Thruster Valve Leakage
- Ramifications for EO-1 Mission
- Gas leak rates as high as 30 scc/hr still
represent a liquid tight seal. This seat is still
functional - Thruster valve assembly (two seats) displays
zero gas leak rate, redundant liquid seals - Redundant thruster valve seat not required by
range safety - If thruster valve leak rate exceeds 30 scc/hr,
The thruster valve shall be considered failed and
thruster reliability is reduced from 0.9966 to
0.9956 For a 3 year mission - Corrective Actions
- Thruster valves exercised (with gas flow) during
CPT5 - Individual valve seats will be tested at the next
opportunity, when the RCS is again cycled to MEOP
of 320 psia.
30Thruster Valve Leakage
- Conclusion
- Failure of any individual valve seat, latch valve
or thruster valves, on EO-1 has been considered - Should any valve seat (thruster or latch valve)
exceed 30 scc/hr gas leak rate, planned launch
site activities shall be reviewed with respect to
this loss of redundancy