Reaction Control System - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Reaction Control System

Description:

Open Problem Records and Residual Risk. System Readiness. NMP / EO-1. NMP EO-1 RED TEAM REVIEW ... No Hysteresis. 2 Counts Maximum Error. 0.2% FS ... – PowerPoint PPT presentation

Number of Views:108
Avg rating:3.0/5.0
Slides: 31
Provided by: mikemcc3
Category:

less

Transcript and Presenter's Notes

Title: Reaction Control System


1
Section 21 Reaction Control System
. . . Michael McCullough Swales Aerospace, Inc.
2
Contents
  • System Overview
  • Test Verification Matrix
  • Component and Subsystem Level Testing
  • System Level Testing
  • Subsystem Level Reviews
  • Status of Launch Site Procedures
  • Status of Launch Site GSE
  • Open Problem Records and Residual Risk
  • System Readiness

3
Reaction Control System
4
EO-1 RCS Performance Requirements
  • Documented in SAI-SPEC-110, released March 27,
    1997
  • Propellant capacity 22.3 kg
  • System mass not to exceed 11 kg
  • Thrusters provide velocity control for S/C
  • Thrusters provide attitude control authority
    during D V
  • Thrusters meet performance specification of OAC
    MR-103G
  • System must meet requirements of EWR 127-1

5
Verification Matrix
21 - 5
6
Accumulated Power On Time for EO-1 S/C
Components
7
RCS Verification Matrix Items
  • Alignment - by Analysis
  • Thruster alignment maintained by control of
    manufacturing tolerances
  • Static Load - Qualification by Similarity
  • Proof Pressure - Test
  • Proof Pressure Tests conducted at component and
    subsystem level
  • Mass Properties - Weighed
  • Weighed at the subsystem level including Zenith
    Deck
  • Interface Verification - Test
  • Interfaces tested during spacecraft IT process
  • Functional - Test
  • Tested at the component and subsystem Level

8
RCS Component Verification
  • Propellant Tank
  • Determination of Volume
  • Proof Pressure Test
  • Internal and External Leakage Test
  • Radiographic/Penetrant Inspection
  • Visual Inspection and Cleanliness
  • Fill/Drain Valves
  • Inspection and Cleanliness
  • Proof Pressure
  • Internal and External Leakage
  • Operational Cycles
  • Filter
  • Proof Pressure Test
  • External Leakage
  • Bubble Point and D-P
  • Visual Inspection and Cleanliness
  • Latch Valve
  • Internal and External Leakage Test
  • Operating Cycles
  • Visual Inspection and Cleanliness
  • Vibration
  • Thrusters
  • Hot Fire Performance
  • Proof Pressure, Vibration
  • Internal and External Leakage
  • Pull-In and Drop-Out Voltage
  • Visual Inspection and Cleanliness
  • Pressure Transducer
  • Vibration and Proof Pressure Test
  • Calibration
  • Electrical Characteristics

9
RCS Verification at Primex
  • System Welds
  • Leak Checked, Dye Penetrant and Radiographic
    Inspection
  • Proof Pressure Checks
  • High Pressure Proof Pressure Test (820 psig)
    excl. Tank
  • Complete System Proof Pressure Test (480 psig)
  • Internal Valve Leak Checks
  • Thruster and Latch Valve Seats Checked
    Individually
  • Electrical Component Resistance and Isolation
    Checks
  • System Level Functional Checks
  • Thrusters, Latch Valve, Pressure Transducer and
    Thermostats

10
RCS Checks at Swales
  • Electrical Component Resistance and Isolation
    Checks
  • System Integration with Spacecraft
  • System Level Functional Checks
  • Pre- and Post-Integration
  • Thrusters, Latch Valve, Pressure Transducer,
    Thermostats and Thermistors
  • Thruster Phasing with Gas Flow at 15 psig

11
RCS Environmental Test Program
  • The EO-1 RCS was fully integrated with the
    spacecraft for Shock, Vibration and Acoustic
    Testing
  • RCS Functionality verified during CPT 5
  • arcs1.prc - exercised thruster valves
  • arcs2.prc - powered catalyst bed heaters
  • arcs3.prc - exercised the latch valve
  • RCS Integrity verified during Pressure Transducer
    Calibration and Valve Leak Checks
  • Thermal Vacuum / Thermal Balance Testing Verified
    Proper Operation of the RCS Thermal Control
    System.
  • Temperatures maintained between 18C-24C during
    cold case tests
  • No heater activity during hot case testing

12
RCS Thermal Control (1)
13
RCS Thermal Control (2)
14
RCS Pressure Transducer Calibration
  • End-to-end Test Performed, Propellant Tank to
    Ground System Display
  • No Change in Scale Factor
  • 100 psi/volt
  • Offset Adjusted by 1.3 psi
  • No Hysteresis
  • 2 Counts Maximum Error
  • 0.2 FS
  • Calibration will be repeated as part of Launch
    Site Processing

15
RCS Internal Leak Check
  • Performed Internal Leak Check on All RCS Valves
  • Series Redundant Valve Seats Checked Individually
  • Checked At MEOP (320 psig)
  • Total of 9 Valve Seats Checked
  • System Level Performance is Acceptable
  • Leak Check of Fill/Drain Valves Added to System
    Level Test in Response to RFA 14.27
  • Next System Flight Level Pressurization Test
    Planned as Part of Launch Site Processing

16
RCS Pressure Cycle Log
17
Technical Peer Reviews
  • Series of Requirements and Design Reviews
    Conducted at Primex Aerospace
  • Attended by SAI Lead Engineers for Mechanical,
    Electrical, Stress and Thermal Subsystems, QA,
    S/C Systems, and Program Manager
  • EO-1 RCS Requirements Review
  • January 21-22, 1997, Primex Handout 97-H-2355
  • EO-1 RCS Preliminary Design TIM
  • April 3-4, 1997, Primex Handout 97-H-2376
  • EO-1 RCS Critical Design Review
  • June 3-4, 1997, Primex Handout 97-H-2391
  • EO-1 RCS Pre-Ship Review
  • March 3, 1998, Data Package P/N 33400-965

18
PSR RFA Status
  • Three RFA Issued During EO-1 Spacecraft Pre-Ship
    Review
  • RFA 14.17
  • Completed
  • RFA 14.27
  • Completed
  • RFA 14.28
  • Completed

19
RFA 14.17
  • Specific Request RCS valve leakage criteria
    should be revised lower (100 scc/hr is too high)
    and leak rate for out of spec valve should be
    trended.
  • Supporting Rationale I believe any valve leaking
    at 100 scc/hr is so far out of family that it
    should be replaced. If the out of spec valve
    remains stable, it is probably OK. However, if
    its leak rate increases significantly, it should
    be replaced.
  • Project Response Valve leak rate acceptance
    criteria revised downward to 30 scc/hr. Leakage
    in excess of this rate shall be cause to review
    flight worthiness and launch site latch valve
    usage. SAI-PROC-309 revised to reflect new leak
    rate criteria and capture requirement for review
    of launch site procedures.

20
RFA 14.27
  • Specific Request Leak test fill and drain valves
    (at least primary seals)
  • Supporting Rationale Cycling fill and drain
    valves on the ground can potentially introduce
    contaminants into seals and cause leakage. Leak
    testing valves requires minimum resources and
    time and adds significant assurance to mission
    success.
  • Project Response SAI-PROC-309 has been revised
    to include a leak check on RCS fill and drain
    valves. This test will be conducted at the Range
    as part of the next scheduled RCS valve leak
    check.

21
RFA 14.28
  • Specific Request Perform a post environmental
    leakage test on the propulsion system.
    Recommendation pressurize with GN2 to TBD psia
    monitor pressure decay for longest duration
    possible.
  • Supporting Rationale
  • 1. The integrity of the welds, lines, components
    of the propulsion subsystem has not been verified
    after being stressed by environmental tests.
  • 2. Discovery of leakage during propellant loading
    ops is much too late in the timeline. Leakage
    after loading hydrazine poses safety hazard to
    personnel.
  • 3. With the delay in launch schedule, monitoring
    pressure for decay test may be feasible over 3-4
    months.
  • Project Response The RCS has been pressurized to
    40 psi (maximum allowed by DOT regulations) and
    pressure decay is being monitored. Pressure
    decay check will continue through until
    propellant loading, approximately two months.

22
Failure Free Operation Time
  • No failures of RCS encountered during S/C IT
    program
  • Total operating time
  • Pressure transducer powered on with S/C
  • Thruster and latch valve actuation limited to
    select ACS phasing and S/C comprehensive tests
  • No configuration changes required
  • No changes required in Test Plan
  • No hardware or software changes required

23
RCS Launch Site Procedure Status
  • Two procedures considered hazardous by NASA/KSC
    and air force 30SW - review and approval required
  • RCS checkout and leak test procedure SAI-PROC-309
  • Hazardous due to pressures involved
  • Submitted to range for comment
  • Comments incorporated
  • Ready for final range review approval
  • EO-1/SAC-C propellant loading procedure PAC
    IP-0645
  • Hazardous due to propellants and pressures
    involved
  • Submitted to range for comment
  • Comments incorporated - TIM held to discuss
    details
  • Final approval contingent on facility selection

24
RCS Ground Support Equipment Status
  • Propellant loading cart has been demonstrated
    using PAC Procedure IP-0645
  • Pressure test console and all associated
    equipment has been calibrated and / or
    proof-tested and will remain valid throughout the
    launch campaign
  • Portable pressure monitor unit has been
    functionally demonstrated
  • All export / ITAR issues associated with SAC-C
    propellant loading have been resolved
  • SCAPE / PHE and Interscan training will be
    accomplished shortly after arrival at the launch
    site
  • Range safety has reviewed GSE design documented
    in the EO-1 MSPSP SAI-SFTY-019 submitted to the
    range 10/26/99
  • Previewed by range safety prior to official
    submittal

25
RCS Statement of Readiness
  • The EO-1 Reaction Control System is ready for
    launch site processing
  • System integrity, performance and functionality
    has been demonstrated
  • The EO-1 RCS Launch Site Procedures are ready for
    launch site operations
  • Procedures have been demonstrated using GSE
  • There are no obstacles to procedure approval by
    the Western Range
  • The EO-1 RCS GSE is ready to support launch site
    processing
  • Primex is ready to support EO-1 / SAC-C
    propellant loading

26
Problem Records and Residual Risk
  • Problem Records
  • No Critical Problem Records
  • No Open Problem Records
  • Residual Risk Items
  • None
  • Potential Redbook Items
  • None

27
Special Topic Leak Rate in RCS Valve
. . . Michael McCullough Swales Aerospace, Inc.
28
Thruster Valve Leakage
  • History - During RCS thruster valve leak checks,
    one thruster (4) displayed unexpectedly high
    leakage through the downstream valve seat. 13
    scc/hr observed, 1 scc/hr expected.
  • Possible Cause - Valve seat contamination,
    perhaps catalyst fines.
  • All testing has been performed with positive gas
    flow during thruster valve cycling
  • Catalyst beds are below valve seats, limits the
    opportunity for contaminants to percolate down
    into valve seats

29
Thruster Valve Leakage
  • Ramifications for EO-1 Mission
  • Gas leak rates as high as 30 scc/hr still
    represent a liquid tight seal. This seat is still
    functional
  • Thruster valve assembly (two seats) displays
    zero gas leak rate, redundant liquid seals
  • Redundant thruster valve seat not required by
    range safety
  • If thruster valve leak rate exceeds 30 scc/hr,
    The thruster valve shall be considered failed and
    thruster reliability is reduced from 0.9966 to
    0.9956 For a 3 year mission
  • Corrective Actions
  • Thruster valves exercised (with gas flow) during
    CPT5
  • Individual valve seats will be tested at the next
    opportunity, when the RCS is again cycled to MEOP
    of 320 psia.

30
Thruster Valve Leakage
  • Conclusion
  • Failure of any individual valve seat, latch valve
    or thruster valves, on EO-1 has been considered
  • Should any valve seat (thruster or latch valve)
    exceed 30 scc/hr gas leak rate, planned launch
    site activities shall be reviewed with respect to
    this loss of redundancy
Write a Comment
User Comments (0)
About PowerShow.com