Title: CHALLENGES OF THE SCL DELAY AND DISRUPTION PROTOCOL
1CHALLENGES OF THE SCL DELAY AND DISRUPTION
PROTOCOL Tony Farrow Trett Consulting www.trett.c
om
2AGENDA
- Background (Contracts, Delays, Analysis, Claims,
Disputes, Resolution) - The Protocol (Structure)
- The Protocol (Aims and Achievements)
- Challenges in Implementing the Protocol
3Contracts and Project Delays
- Contracts have completion dates and liquidated
damages are tied to completion date - Extension of Time clauses maintain LD provisions
where there has been breach by Employer - If Employer causes a delay and there is no EOT
clause, time can (not universal) become at
large and LD clause fails. - EOTs also relate to financial matters including
bonus situation
4Contracts and Project Delays
- Contract provisions define the basis of
entitlement - Contracts are imprecise as to how to demonstrate
delay and prove entitlement - Debate about actual delay and contractual
entitlement - Hence Delay Analysis Methodology has developed
- SCL Protocol advances Delay Analysis
- Delay to be on the critical path
5Extension of Time Methods
- Estimate or Model Methods (investigate the EVENT
and its potential impact) - Actual Methods (identify the DELAY period and
investigate what caused it)
6Model Based Methods
- Global and Net Impact Methods
- As-Planned Impact
- As-Planned But For
- Collapsed As-Built (As-Built But For)
- Time Impact Analysis (Impact / Update)
7Actual Based Methods
- As-Planned vs As-Built
- Windows / Snap-Shot
8Model Based Analysis
1
2
3
4
5
6
7
8
9
10
11
Activity
ACTIVITY A
OriginalCompletion
ACTIVITY B
ACTIVITY C
9Actual Based Analysis
1
2
3
4
5
6
7
8
9
10
11
Activity
ACTIVITY A
OriginalCompletion
ACTIVITY B
ACTIVITY C
10Prospective and Retrospective Approaches
- P looks forward and anticipates delay
(Preventative forward looking) - R looks back and establishes cause of delay
(Curative allocation of blame) - SCL Protocol offers another approach to R put
yourself back at the time of the event and
re-assess what might have happened had things
been done differently.
111
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
PLANNED PROGRAMME
Original Overall Duration 7 Weeks
Critical Path runs through activities A and B
12Dur
Activity
Completion Date Week 7
A 8 wks
B 1 wk
C 5 wks
D 4 wks
AS-BUILT PROGRAMME
As-Built Overall Duration 10 Weeks
Critical Path ran through activities C, D and B
13Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 8 wks
B 1 wk
C 5 wks
D 4 wks
DELAYING EVENTS
Events d1, d2 and d4 Owner Delays
Event d3 Contractor Delay
141
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Uses planned programme
151
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
161
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
171
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
- 1 Week Critical Delay
181
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
- 1 Week Critical Delay
Add in 2nd delay to occur (d2)
- No Critical Delay
191
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
- 1 Week Critical Delay
Add in 2nd delay to occur (d2)
- No Critical Delay
Add in 3rd delay to occur (d3)
201
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
- 1 Week Critical Delay
Add in 2nd delay to occur (d2)
- No Critical Delay
Add in 3rd delay to occur (d3)
- 2 Weeks Critical Delay
211
2
3
4
5
6
7
8
9
10
11
Dur
Activity
A 6 wks
B 1 wk
C 2 wks
D 2 wks
AS-PLANNED IMPACTED
Add in first delay to occur (d1)
- 1 Week Critical Delay
Add in 2nd delay to occur (d2)
- No Critical Delay
Add in 3rd delay to occur (d3)
- 2 Weeks Critical Delay
Add in 4th delay to occur (d4)
- No Critical Delay
22Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 8 wks
B 1 wk
C 5 wks
D 4 wks
COLLAPSED AS-BUILT
Uses as-built programme logic linked
23Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 8 wks
B 1 wk
C 5 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and first employer delay
removed
24Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 8 wks
B 1 wk
C 2 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and first employer delay
removed
25Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 8 wks
B 1 wk
C 2 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and first employer delay
removed
1 Weeks Critical Delay Allocated to d1
26Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 8 wks
B 1 wk
C 2 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay
removed
1 Weeks Critical Delay Allocated to d1
27Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 7 wks
B 1 wk
C 2 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay
removed
1 Weeks Critical Delay Allocated to d1
1 Weeks Critical Delay Allocated to d4
28Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 7 wks
B 1 wk
C 2 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay
removed
1 Weeks Critical Delay Allocated to d1
1 Weeks Critical Delay Allocated to d4
29Dur
Activity
Completion Date Week 10
Completion Date Week 7
A 6 wks
B 1 wk
C 2 wks
D 4 wks
COLLAPSED AS-BUILT
Critical Path Identified and next employer delay
removed
1 Weeks Critical Delay Allocated to d1
1 Weeks Critical Delay Allocated to d4
1 Weeks Critical Delay Allocated to d2
30Results from Model Based Methods
As-Planned Impact 1 week critical delay no
critical delay 2 weeks critical delay no
critical delay
Collapsed As-Built 1 week critical delay 1 week
delay no critical delay 1 week critical delay
Delay d1 (VO) d2 (bad weather) d3 (lack
resources) d4 (late info)
31Dur
Activity
Completion Date Week 7
A 8 wks
B 1 wk
C 5 wks
D 4 wks
AS-PLANNED vs AS-BUILT
As-Built Overall Duration 10 Weeks
Critical Path ran through activities C, D and B
32Dur
Activity
Completion Date Week 7
A 8 wks
1
2
3
B 1 wk
C 5 wks
D 4 wks
AS-PLANNED vs AS-BUILT (WINDOWS)
Programme divided into time slices and analysed
progressively
33Dur
Activity
Completion Date Week 7
A 8 wks
1
B 1 wk
C 5 wks
D 4 wks
AS-PLANNED vs AS-BUILT (WINDOWS)
Programme divided into time slices and analysed
progressively
34Dur
Activity
Completion Date Week 7
A 8 wks
2
B 1 wk
C 5 wks
D 4 wks
AS-PLANNED vs AS-BUILT (WINDOWS)
Programme divided into time slices and analysed
progressively
35Dur
Activity
Completion Date Week 7
A 8 wks
3
B 1 wk
C 5 wks
D 4 wks
AS-PLANNED vs AS-BUILT (WINDOWS)
Programme divided into time slices and analysed
progressively
36The planned programme is reconstructed and
divided into snap-shot periods
TIME IMPACT ANALYSIS
37Delays occurring within the first snap-shot
period are added and the programme is re-analysed
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Planned Finish Date
Ground Works
Basement
Delay Influenced End Date
Floor 1
1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
38The actual progress within thesnapshot period is
researched
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Planned Finish Date
Ground Works
Basement
Delay Influenced End Date
Floor 1
1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
39The planned programme is updated to reflect the
actual progress within the snapshot period and
then re-analysed
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Planned Finish Date
Ground Works
Basement
Delay Influenced End Date
Floor 1
1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
40The next snapshot period is analysed
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Ground Works
End Date as at end of 1st snapshot period
2
Basement
Floor 1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
41Delays occurring within the 2nd snap-shot period
are added and the programme is re-analysed
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Ground Works
2
End Date as at end of 1st snapshot period
Basement
Delay Influenced End Date
Floor 1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
42The actual progress within the snapshot period is
researched
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Ground Works
2
End Date as at end of 1st snapshot period
Basement
Delay Influenced End Date
Floor 1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
43The planned programme is updated to reflect the
actual progress within the snapshot period and
then re-analysed
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Ground Works
2
End Date as at end of 1st snapshot period
Basement
Delay Influenced End Date
Floor 1
Floor 2
Floor 3
TIME IMPACT ANALYSIS
44Programme Float
45Two Main Types
46Contract Completion Date
10 days
10 days
15 days
47Who Owns the Float ?
48Contract Completion Date
10 days
TERMINAL FLOAT
10 days
49Contract Completion Date
TERMINAL FLOAT
50Contract Completion Date
10 days
TERMINAL FLOAT
10 days
51Contract Completion Date
10 days
TERMINAL FLOAT
10 days
52CONCURRENCY
53(No Transcript)
54(No Transcript)
55(No Transcript)
56(No Transcript)
57Contractors Fault
Employers Fault
581 Week EOT
591 Week no LE/ 1 week LDs
60Employers Fault
Contractors Fault
612 Weeks EoT
621 Week Prolongation costs
63THE SCL PROTOCOL
64THE PROTOCOL (STRUCTURE)
- CORE PRINCIPLES
- GUIDANCE NOTES
- S1. Explains the Core Principles
- S2. Deals with Programming and Record Keeping
- S3. Extensions of Time (Prospective)
- S4. Extensions of Time (Retrospective)
- APPENDICES
- A. Definitions
- B. Model Specification Clause (Programmes)
- C. Model Specification Clause (Records)
- D. Illustrations
65CORE PRINCIPLES
- Good Programme Systems and Management
- Good Record Systems and Management
- Contemporaneous, incremental, assessment of
delays and award of Extensions of Time - Time Impact Analysis is the preferred methodology
- Float Project owns, Contractor receives
compensation - Concurrency Contractor receives Time but no
Money - Retrospective delay analysis Re-live the
Project contradicts usual assessment of damage?
66GUIDANCE NOTES - S1
- Definitions (Appendix A)
- Extension of Time principles
- Float
- Concurrency
- Mitigation (best endeavours)
- Variations
- Global Claims
- Overheads
- Profit
- Acceleration (does not address Constructive
Acceleration)
67GUIDANCE NOTES S2
- Form of Programme (Appendix B)
- Method Statement
- Timetables for issue (Initial and Agreed)
- Updates and Revisions
- Software
- Record Keeping (Appendix C)
68GUIDANCE NOTES S3
- Extensions of Time during the Project
(Prospective) - Time Impact Analysis
- Updated Programmes
- Revised Programmes
- Level of detail in any analysis
- Illustrations (Appendix D)
69GUIDANCE NOTES S4
- Extensions of Time after the Project
(Retrospective) - Four Methods
- Updated/Revised Programmes
- Balance taken re time/costs
- Consider the terms of the Contract
- Factual analysis or Entitlement driven?
- Placing oneself back at the time of the delay
70THE PROTOCOL -AIMS-
- Not intended as a contract document
- Offers specification terms for programme
management and record keeping - Offers guidance in the management of delay and
disruption that is, in the management of change - Extensions of Time should be dealt with at the
time - Time Impact Analysis is the recommended method
71THE PROTOCOL -ACHIEVEMENTS-
- Hoped that Contracting Parties would adopt its
recommendations Prospective X - Hoped/Attempted to have industry contracting
bodies adopt it Prospective X - Attempted to have the Courts adopt it
Retrospective X - Delay Analysts adopt it v
- Added to knowledge Great Debate!
72THE PROTOCOL -CHALLENGES-
- Must be Industry/Profession/Employer led
- Main Contractors would be unwise adopting it with
Subcontractors - It reduces risk pre-set rules/outcomes
- It increases risk assumes one solution for
all cases - Early delays tend to over-compensate the
Contractor - Protocol needs re-drafting to remove optional
aspects
73THE PROTOCOL -CHALLENGES-
- Needs to deal more practically with constructive
acceleration - Should advance a debate on the fairness of
condition precedent clauses - Does it amend the basis upon which damage is
normally assessed? - English law focussed need to consider other
legal systems.
74THE PROTOCOL -CONCLUSIONS-
- Drafting requirements
- Commercial implications risk issue
- Methodology greatly influences outcomes
- Practical implications skills and resources
required - Not widely adopted yet on live projects
- Authors to be complemented for creating Great
Debate
75DELAY CASE STUDY
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80Delay 4 Crane Delay
81Delay 4 Crane Delay
82Delay 4 Crane Delay
831
2
3
4
5
6
7
8
9
10
11
12
13
14
Slow Progress
PlannedCompletion
1 STEEL FRAME
Sub-Contractor A
2 WALLS ROOF
Main Contractor
Late Switchgear Delivery
3 SWITCH GEAR
Sub-Contractor B
Inherent Design Fault
Crane Delay
4 ACCESS GANTRY
Main Contractor
200T CRANE
Main Contractor
Approved Programme
84REVIEW
85Collapsed As-Built Method
86Collapsed As-Built Method
87Collapsed As-Built Method
88Collapsed As-Built Method
89Collapsed As-Built Method
Reverse the Sequence
90Collapsed As-Built Method
Reverse the Sequence
91Collapsed As-Built Method
92Collapsed As-Built Method
93Employers Liability for Week 11 12As-Planned
Impact Method
94(No Transcript)
95Dominant Delay - 2 Weeks Delay by Subcontractor B
Late Switchgear Delivery
96Answer 1 Month 11 - Subcontractor A Month 12 -
Main Contractor Month 13 - Subcontractor
B Answer 2 Month 11 - Subcontractor A Month 12 -
Subcontractor B Month 13 - Subcontractor
B Answer 3 Month 11 - Subcontractor B Month 12 -
Subcontractor B Month 13 - Subcontractor
B Answer 4 Month 11 - Employer's Liability Month
12 - Subcontractor B Month 13 - Subcontractor B