Title: Lifting training presentation
1(No Transcript)
2Rigging and Lifting Course
3Course Objectives
- Understand rigging and lifting regulations and
personal responsibilities - Identify Safe Systems of Work for rigging and
lifting - Understand the importance of housekeeping
- Identify lifting equipment
- Understand the principles and terminologies used
in rigging and lifting operation
4Course Objectives Cont..
- Understand the importance of hand signals and
two-way radio in rigging and lifting operation - Understand crane operating principles,
conflicting activities, environmental factors,
manual handling, dynamic and static factors
5 Course Outline
- Module 1 Introduction
- Module 2 Rigging and Lifting Hazards
- Module 3 General Hoisting and Rigging Practices
- Module 4 Rigging Slings and Hitches
- Module 5 Rigging Hardware
- Module 6 Fiber Ropes, Knots, Hitches
- Written Assessment
- QA
6Introduction
- Rigging involves the use of cranes and other
large pieces of equipment to lift - OSHA heavily regulates this practice
- In crane operations, accidents do happen
- Majority of crane accidents resulting in
fatalities and injuries are preventable - More than 50 of all mobile crane accidents are
the result of mistakes made when the crane was
being set up. - All of these accidents are preventable by
following the manufacturers recommendations for
assembly and dismantling, by using the correct
components, and by observing the necessary
precautions.
7Rigging and Lifting Hazards
- Fall Hazards created by
- Uneven working surfaces.
- Wet and slippery working surfaces.
- Working surfaces not cleared of obstructions.
- Improper use of portable ladder.
- Unprotected sides, bulkhead openings, deck holes
more than 5 ft.
8Hazards Cont..
- Struck-by and Crushing Hazards created by
- Gear and equipment not properly inspected.
- Defective gear and equipment.
- Moving parts and equipment.
- Loads not safely rigged before being hoisted.
- Improper use of tag line allowing hoisting
material to swing out of control. - Loads swung or suspended overhead.
- Hazardous locations between a swinging load and
fixed object.
9Hazards Cont..
- Electrical Hazards created by
- Use of hoisting and hauling equipment near
energized lines. - Tools and equipment not properly grounded.
- Defective electrical tools.
- Worn or frayed electric cables.
10- General Hoisting and Rigging Practices
11Approved Code of Practice (ACoP) Duties of
Principal
- Principals engaging contractors are required to
take all practicable steps to ensure that - No employee of a contractor or subcontractor, or
- If an individual, no contractor or subcontractor
is harmed while doing any work that the
contractor was engaged to do.
12Approved Code of Practice (ACoP) Duties of
Self-Employed
- Every self-employed person shall take all
practicable steps to ensure that no action or
inaction of the self-employed person while at
work harms the self-employed person or any other
person.
13Approved Code of Practice (ACoP) Duties of
Employees
- Every employee shall take all practicable steps
to ensure - Their own safety while at work (including using
protective clothing and equipment) - That no action or inaction of theirs while at
work causes harm to any other person
14Rigging and Lifting RegulationsPersonal
Responsibilities
- Stay safe and remain alert in sites/facilities
- Understand and abide to company safety policies
- Abide to warning signs pasted in sites/facilities
- Use PPE and equipment as instructed
- Report all hazards
- Report and document all defects immediately
- Never throw items from height
- Only competent people are allowed to operate
equipment and machineries - No horseplay in sites/facilities
15Occupational Safety and Health Administration
(OSHA)
- Code of Federal Regulations (29 CFR)
- General Duty Clause
- (a) Each employer
- (1) Workplace free from recognized hazards
- (2) shall comply with occupational safety and
health standards - (b) Each employee shall comply with occupational
safety and health standards and all rules,
regulations, and orders - (c ) Equipment provided must be
- (1) Suitable for the intended use
- (2) Safe for use
- (3) Used only by competent people
- (4) Accompanied by suitable safety measures,
e.g., protective devices, markings, warnings
1629 CFR Occupational Safety and Health Regulations
(OSHA Standards)
- 1910 Occupational Safety and Health Standards
1926 Safety and Health Regulations for
Construction
- Subpart N Materials Handling and Storage
- 1910.179 - Overhead and gantry cranes.
- 1910.180 - Crawler locomotive and truck cranes.
- 1910.184 - Slings.
- Subpart N Cranes, Derricks, Hoists, Elevators,
and Conveyors - 1926.251 - Rigging equipment for material
handling. - 1926.550 - Cranes and derricks.
- 29 CFR 1926 Subpart CC, Cranes and Derricks in
Construction
17OSHA 1910.184 -ASME B30.9
- Reasons
- Ensure safe equipment
- Gain knowledge and experience
- Nature of lifts being made
- Sling usage
- Operator competence
- Inspections
- Daily / Periodic before use
- Minimum annual with records
- Frequently, as warranted
- Record Keeping
- Most recent report
- Test certificates
When was the last INSPECTION performed?
18Management Of Health Safety at Work Regs. 1992
- Risk Assessment
- Record findings of that assessment
- Assessment reviewed and modified
- Suitable and sufficient risk assessments should
- - be carried out by a competent person
- - ensure all relevant risks or hazards are
addressed - - determine the likelihood of injury or harm
arising - - take into account any existing control
measures.
19Safe Systems of WorkPermit to Work (PTW)
- What is PTW?
- Formal written authority to operate a planned
procedure, which is designed to protect personnel
working in hazardous areas or activities. - PTW validity?
- Lasts for one working shift or should not exceed
16 consecutive hours
20Safe Systems of WorkPermit to Work (PTW)
- Receiver of PTW?
- Company employees certified by department head to
sign and receive work permits - Sponsoring organization heads (contractor)
- Cancellation/Suspension of PTW
a. Job safety does
not meet the conditions specified on the work
permit.
b. Emergency situation.
21Safe Systems of WorkToolbox Talk
- What is Toolbox Talk?
- Safety lecture to educate workers about safe work
conditions - Also knows as Toolbox Meeting or Tailgate
Meeting - Required to be carried out for all work with
significant safety exposure - Final check in the hazard assessment process and
the start of work implementation
22Safe Systems of WorkToolbox Talk
- When does it take place?
- Must take place at job site with all workers
before starting the work - Must take place at job site when major changes or
different phases of work is started
23Safe Systems of WorkToolbox Talk
- What are being discussed/covered
- Work plan
- Hazards and Controls
- Roles and Responsibilities
- Emergency procedure
- Personal protective equipment
Previous
incidents and lesson learn - Questions resolution of issues raised by worker
-
24Safe Systems of WorkToolbox Talk
- What are being discussed/covered
- Work plan
- Hazards and Controls
- Roles and Responsibilities
- Emergency procedure
- Personal protective equipment
Previous
incidents and lesson learn - Questions resolution of issues raised by worker
-
25Safe Systems of WorkExample of Toolbox Talk
Checklist
26- Importance of Good Housekeeping
- Housekeeping must be carried out before, during
and after rigging and lifting activity. - Good housekeeping
- Ensure items are securely stored to avoid
hazardous situations e.g. fire hazards - Ensure equipment and accessories are well kept
and maintained with time - Reduce injuries e.g slipping and tripping due to
oily/wet floor
27Examples of Good Housekeeping
Poor housekeeping and work procedures due to
inadequate site and work area supervisions
Equipments and materials are organized and stored
28Examples of Good Housekeeping
Good housekeeping ensures safe workplace
29Lifting Hardware and Equipment
- Lifting Equipment comprises of
- Lifting Appliances (equipment performing the
lifting) - Lifting Accessories (devices which connect the
load to the Lifting Appliance) - Lifted Equipment
30Lifting Accessories
- Wire rope
- Shackle
- Webbing sling
- Container
- Chain block, lever hoist and tirfor
- Hook
- Eyebolts
- Snatch block
31Components of Lifting Equipment
3/4 - 6 x 19 - FC 5/8 - 6 x 37 - IWRC
32Components of Lifting Equipment
33Components of Lifting Equipment
Ferrule
- SWL (safe working load)
- Serial Number
- Date Manufactured
- Color Code
34Wire Rope Safe Working Load
- Specified Breaking Strength
- Safety Factor
35(No Transcript)
36Kinking is caused by Loops that have been drawn
too tightly as a result of improper handling
Kinks are permanent and will require that the
rope, or damaged section, be taken out of service
Wire Rope Defects of Wire Rope Sling
37Wire Rope Defects of Wire Rope Sling
- Bird caging is caused by the rope being twisted
or by a sudden release of an overload - The rope, or the affected section, must be
replaced
38Wire Rope Defects of Wire Rope Sling
- Corrosion is often due to
- Inadequate lubricant
- Improper type of lubricant
- Improper storage
- Exposure to acids
- Core protrusion can be caused by shock loads
and/or torsional imbalance - This condition requires that the rope be taken
out of service
39Wire Rope Defects of Wire Rope Sling
- This is often the result of heavy loads over
small sheaves. These breaks being caused by
strand nicking resulting from the heavy loads.
40Wire Rope Good Storage System
41Wire Rope Care and Maintenance
- Purpose of Lubrication
- Initial factory lubrication will not last
- Good Lubricant Characteristics
- Corrosion resistance
- Water repellant
- Penetrating ability
- Temperature stability
- Lubricant Frequency
- Recommended at least quarterly
- Depending on the usage
- Working environment
42Wire Rope Pre-Use Checks
- SWL is adequate for the load
- Color coding (where applicable)
- Plate number / ID mark
- Each individual leg along its entire length
Wear, corrosion, abrasion, mechanical, damage,
broken wires - Ferrule should be free from cracks or other
deformities - Examine master link assembly (wear, corrosion,
cracking)
43Shackle Types of Shackle
44Parts of Shackle
45Defects of Shackle
46Shackle Pre-Use Checks
47Shackle Unsafe Practices
48Shackle Good Storage System
49Webbing Sling Types of Webbing Sling
50Webbing Sling S.W.L/Safety Factors
51Defects of Webbing Sling
52Webbing Sling Pre-Use Checks
- SWL is adequate for the load
- Color coding (where applicable)
- Plat number / ID mark
- Cuts, tears or chafing
- Burst stitching (especially round the eyes)
- Chemical damage
- Ingress of foreign bodies into the fibers
- Distortion / wear in the metal eyes (where fitted)
53Webbing Sling Good Storage System
54Container Types of Container
55Markings on Container
56Markings on Container
57Container Pre-Slungs
58Chain Block - Functions
- Chain block is main for lifting
- Safety latches must be fitted on the hook
- Design for one person to pull
- Do not overload
- No suspended load
59Level Hoist - Functions
- Lifting devices operated with a handle instead of
hand chain - Not available in very high capacities (not more
than few tons) - Short load chain
- Used for short lifts
- Commonly abused (attempt to get more leverage by
extending the - handle with a piece of pipe)
60Level Hoist - Tirfor
61Chain Block - Pre-Use Checks
- Safe working load is adequate for the load
- Color coding is current (where applicable)
- Safety latches are fitted
- No sign of misuse
- Stretched hook
- Corroded casing
- Stretched/distorted chain.....etc.
62Chain Block - Defects of Chain
63Hooks Types of Hooks
64Hooks - Parts of Hook
Throat
Eye
Body
Saddle
65Defects of Hook
66Hooks Pre-Use Checks
67Eyebolts Types of Eyebolts
68Correct Use of Eyebolts
69Correct Use of Eyebolts
70Types of Eyebolts
71Snatch Block Types of Snatch Block
72Snatch Block Pre-Use Checks
73Snatch Block Inspection
- Side plate securing bolt cannot be fully
withdrawn - Manufacturer's certificate certificate of
application - Maintenance / inspection shall be according to
manufacturers recommendation - Ensure split pins, locking and secure pins are in
place - Ensure support structure is of adequate strength
- Consider total resultant forces acting supporting
structure
74Rigging Principles and Terminologies
Term Description
Working Load Limit (WLL) Stated capacity of lifting equipment
Safe Working Load (SWL) The load the equipment can safely lift
Breaking Strength (BS) The actual force required to pull rigging gear to destruction
Proof Loading Proof loaded by a certified body acceptable by relevant authority
Safety factors To calculate the WLL/SWL of different types of lifting equipment.
Tare weight (TW) Weight of empty container
Maximum Gross Weight (MGW) Total weight MGW TW SWL
Included Angle Angle created between the sling legs
75Angles and Tension in Slings
- Slings Angle
- 60º Attachment point A Slings length S
- 90º Attachment point A 2 x height of
triangle H - 120º Attachment point A ½ x Slings length
S
76Angles and Tension in Slings
77Weight of Load
- Maximum Load W.L.L. x angle factor x reeve
factor - 8 x 1.73 x 0.5
- 6.92 tones
- 6.9 tones
Sling SWL 8 Tones Angle is 60º, Factor
1.73 Reeve factor 0.5
78Weight of Load
- W.L.L. weight angle factor reeve factor
- 4 1.73 0.5
- 4.62 tones
- 4.6 tones
Weight 4 Tones Angle is 60º, Factor
1.73 Reeve factor 0.5
79Sling Angle Factor
SLING ANGLE CHART SLING ANGLE CHART
Angle fromHorizontal A S.A.F. L H
90 1.000
60 1.155
45 1.415
30 2.000
80Sling Angle Factor
81Centre of Balance
82Communication
- Proper rigging of load
- Supervision of the rigging crew
- Ensuring that the rigging material equipment
have the necessary capacity in safe condition - Ensuring correct assembly of rigging material or
equipment - Safety of the rigging crew and other personnel
- Correct signaling during the lifting operation
83Who are Qualified to be Banks man?
- Supervisor
- Foreman
- Team Leaders
- Bosun
84Hand Signals
85Hand Signals
86Hand Signals
87Two Way Radio- Walkie Talkie
- Disadvantage
- Communication break down due to
- Garbled message
- Weak battery
- Wave interference
- Interruption
- Background noise
- Advantage
- Provide accuracy of crane movement
- Confident to carry out the operation
- Commonly use for lifting at height / blind spot
night activities
88Awareness of Lifting Operation
Crane Operating Principles Centre of Gravity
- Centre of gravity -is the point around which an
objects weight is evenly balanced
89Leverage Cranes
- Principle to lift load. Rotation of the upper
works changes the location of the cranes centre
of gravity leverage point
90Stability
- Relationship of the load weight, angle of boom
and its radius to the centre of gravity of the
load
91Structural Integrity
- The crane main frame, boom sections attachments
are all considered part of the structural
integrity of lifting
92Conflicting Activities
- Lift Plan
- Location
- Nature of activities
- Hazard
- PTW
- Toolbox talk
- Communication
93Conflicting Activities
94Environment Factors
- Internal spaces of vessels and rigs
- Transferring equipment from vessels platforms
- Moving equipment around the deck at sea
- Submerging or recovering equipment in the sea
- Vessel motion and stability
- Weather, wind and sea forces
- Seabed suction and dynamic loading
- Noise, light, spray
95ARAMCO SAFETY INSTRUCTIONS (2)
- 6. A tag line shall be long enough for the worker
controlling it to avoid being struck by any
movement of the load. Tag lines must be in good
condition. Tag lines with excessive wear and tear
shall not be used. - 7. Personnel shall not be required or permitted
to work, stand, or pass under a suspended load. - 8. Personnel shall not be permitted to work,
stand, or pass between the winch mechanism and a
load being winched, nor in an area where the
worker may be injured due to winch line or winch
line mechanism failure. - 9. Personnel shall not be required or permitted
to work, stand, or pass within the length of a
cable under tension. - 10. The working load on winch mechanisms, gin
poles, hoists, lines, slings, grommets, hooks,
pad-eyes and fittings shall not exceed the
labeled / tagged Safe Working Load (SWL).
96ARAMCO SAFETY INSTRUCTIONS (2)
- 11. The SWL and unique identification number
shall be displayed on each lifting device and
each piece of rigging hardware in order to
facilitate tractability through the lifting
equipment registry. - 12. The current color code, as per SWIM /No.3
/RMHRE/Appendix No.2, shall be displayed on each
piece of lifting equipment. - 13. Winch mechanisms, lines, slings, grommets,
hooks, pad-eyes and fittings shall be thoroughly
inspected by the operator of the equipment before
use for evidence of overloading, excessive wear,
or damage. - Any rigging equipment found to be defective shall
be immediately removed from service and either
repaired and recertified prior to being returned
to service or destroyed. - 14. The SWL of a sling shall be marked on the
sling as per SA G.I. 7.029. If the SWL is
exceeded the sling shall be taken out of service
and destroyed per SA G.I. 7.029.
97ARAMCO SAFETY INSTRUCTIONS (2)
- 15. When using slings, softeners shall be
provided between the sling and sharp unyielding
surfaces of the load to be lifted. - 16. A sling shall not be pulled from under a load
when the load is resting on the sling. Cribbing
consisting of cut drill line, lumber, etc., shall
be used to support the load and provide a space
for sling removal. - 17. To eliminate shock loading, all slack in the
sling shall be taken up carefully by the crane
operator before beginning the lift. - 18. When using other than single leg slings for
straight vertical lifts, the rigger shall be
aware of the load rating changes that occur when
different hitches are used (i.e., basket, choker,
etc.) or when the angle of loading is changed in
multiple leg bridle slings. - 19. When using a choker hitch, the sling shall be
equipped with a protective thimble, protector arc
or sliding choker hook to reduce wear and
abrasion at the point where the loop contacts the
sling body.
98ARAMCO SAFETY INSTRUCTIONS (2)
- 20. When not in use, slings shall be stored in a
dedicated storage area (rigging loft) that will
protect the slings from damage by moisture,
extreme heat, corrosion, or physical abuse. It is
acceptable for rigging hardware that would create
a hazard while attempting to store said (large
slings for the BOP etc.), be stored in an
alternate area, provided that the area provides
protection to the equipment as stated above. - 21. Leaver Boomers shall not to be used on any
location, a Ratchet type Boomer is the only
approved device. - 22. Webbing, synthetic slings shall only be used
under the permit to work system with access
stringently controlled by storage in a secure
area - A. The individual identification number of each
webbing, synthetic sling to be used shall be
indicated on the Saudi Aramco Rig (SAR) Safe Work
Authorization Procedure (SWAP) or contractor
Permit to Work (PTW), refer to HSERM
/A/A-12/SWAP.
99ARAMCO SAFETY INSTRUCTIONS (2)
- B. Each webbing, synthetic sling shall be
inspected by a competent person before use the
person who inspected the slings shall be
indicated by inclusion of his full name on the
SAR SWAP or contractor PTW. - The term "Competent Person" is defined as A
person who, by possession of a recognized
pertinent degree or certificate of professional
standing or who, by extensive knowledge,
training, and experience, has successfully
demonstrated the ability to solve or resolve
problems relating to the subject matter at work. - C. Once the task involving webbing, synthetic
slings has been completed, the slings shall be
inspected by a competent person before the SAR
Safe Work Authorization Procedure (SWAP) or
contractor Permit to Work PTW) can be closed. The
person who inspected the slings shall be
indicated by inclusion of his full name on the
SAR SWAP or contractor PTW. The webbing /
synthetic sling shall be returned to the
designated secure storage area. Web slings should
be stored under lock and key conditions so as to
prevent unauthorized use. - 23. Certified chains shall be limited to MODU
Towing Systems, BOP Hoists, cold shucked make-up
chains on make-up tongs and Draw-works Catheads. - Note Certified chains are specifically
prohibited for use in Secondary Restraint
applications with the exception of compliant OEM
supplied jetting line caps.
100ARAMCO SAFETY INSTRUCTIONS (2)
- 24. Defective or damaged rigging hardware, or
rigging hardware without compliant OEM design
certifications, shall be immediately removed from
service and shall be destroyed to prevent further
use. All lifting equipment removed from service
shall be appropriately recorded in the SA Lifting
Equipment Registry maintained by the user. - 25. All sling types shall have identification
information permanently affixed with durable
identification tags or wire rope swages and shall
be maintained by the user so as to be legible
during the life of the sling. - 26. Compliant sling certificates defining the
Design Safety Factor (Minimum 51), SWL, and
Proof Load Test (200) shall accompany any sling
or Hoist/winch-wire, with a unique serial number
or ID, which shall be entered into the Lifting
Equipment Registry to ensure traceability. - 27. Slings shall be shortened, or otherwise
adjusted, only by methods approved by the sling
manufacturer.
101ARAMCO SAFETY INSTRUCTIONS (2)
- 28. Slings shall not be shortened or lengthened
by knotting, by re-splicing, or by wire rope
clips. - 29. Use of any slings that have been repaired or
modified is prohibited. - 30. Slings shall be hitched in a manner that
provides the best control of the load. - 31. Working conditions that may affect slings and
other rigging hardware shall be considered, with
special attention to temperatures, chemicals,
abrasions, etc. - 32. Aluminum Ferrules are specifically prohibited
on all wire rope slings as detailed in SA G.I.
7.029 Section-5.22. - 33. All attaching devices (i.e., rings, links,
coupling pins, etc.) shall be selected to provide
capacities equal to, or greater than, the slings
used. - 34. Fasteners manufactured in-house from bolts,
rods, pins, hooks, etc., shall not be used.
102ARAMCO SAFETY INSTRUCTIONS (2)
- 35. Only hooks with safety latches are to be
used. - 36. Horizontal sling angles less than thirty
degrees (30º) shall not be used. - 37. OEM Certified four (4) Part Shackles shall be
installed on all fixed pad-eye anchor points such
as cylinder racks, cargo baskets, HP Secondary
Retention Sling Clamps, Man Baskets, sheave block
anchor points, SRL anchor points and overhead
shackle installation applications. - Note
- Four (4) part shackles are intended for use on
permanent/semi-permanent installations and where
man lifting operations are taking place. - The use of two (2) part shackles is permissible
for standard rigging operations. - 38. All cargo baskets, cylinder racks, sub
baskets, tool baskets, etc., shall be an OEM
Certified 4-Point Lift Design, with a compliant
OEM designed data plate attached.