Title: Provident Park Square | Luxury Apartments in Kanakapura Road
1August 2021
2(No Transcript)
3(No Transcript)
4Tower 4A 4B
4A
4B
TOWER STATUS
MILESTONES ACHIEVED
- 4A terrace water proofing preparation in
progress. - 4A External painting north side in progress.
- 4B above terrace OHT wall concrete completed.
- 4B external sealant work in progress.
- 4A 14th floor doors fixing completed.
- 4A 14th floor Windows fixing completed.
- 4A internal painting in progress.
- 4B 9th floor tiles work in progress.
- 4B balcony railing 7th floor in progress.
- 4A installation of windows/doors up to 14th
floor completed. - 4B completion of flooring up to 7th floor
completed.
UPCOMING MILESTONES
- 4A - Completion of erection of lifts, common
lobbies and common staircases. - 4B - Completion of flooring up to 10th floor.
Actual site photograph
PROGRESS TIMELINE
April 21
May 21
June 21
July 21
August 21
Construction Updates
5Tower 5A 5B
5A
5B
TOWER STATUS
MILESTONES ACHIEVED
- 5A OHT top slab reinforcement in progress.
- 5A External sealant works in progress.
- 5B Above terrace OHT walls work in progress.
- 5A 9th floor doors fixing in progress.
- 5A 14th floor Windows fixing Completed.
- 5A internal painting in progress.
- 5B 3rd floor tiles work completed.
- 5B water proofing 7th floor in progress.
- 5A installation of external windows/doors up to
7th floor completed. - 5B Completion of terrace slab.
UPCOMING MILESTONES
- 5A installation of external windows/doors up to
10th floor. - 5B completion of flooring up to 3rd floor.
Actual site photograph
PROGRESS TIMELINE
April 21
May 21
June 21
July 21
August 21
Construction Updates
6Tower 3C, 3D 3E
3C
3D
3E
TOWER STATUS
MILESTONES ACHIEVED
- 3E Above terrace works in progress.
- 3C GF shear walls completed.
- 3D GF roof slab shuttering in progress.
- 3E internal waterproofing 6th floor in progress.
- 3E internal putty works 2nd floor in progress.
- 3E completion of terrace slab.
- 3C 3D Completion of 1st (first) slab.
- UPCOMING MILESTONES
- 3E completion of flooring up to 3rd floor.
- 3C 3D completion of 5th (fifth) slab.
Actual site photograph
PROGRESS TIMELINE
April 21
May 21
June 21
July 21
August 21
Construction Updates
7Tower 2C, 2D 2E
2C
2D
2E
TOWER STATUS
MILESTONES ACHIEVED
- 2E 8th floor roof slab in progress.
- 2C 4th floor roof slab in progress.
- 2D 4th floor roof slab in progress.
- 2E completion of 9th slab.
- 2C 2D Completion of 5th slab.
- UPCOMING MILESTONES
- 2E completion of 13th slab.
- 2C 2D completion of 9th slab.
Actual site photograph
PROGRESS TIMELINE
April 21
May 21
June 21
July 21
August 21
Construction Updates
8Tower 1B, 1C 1D
1B
1C
1D
TOWER STATUS
MILESTONES ACHIEVED
- 1B Basement roof slab completed.
- 1C Basement roof slab completed.
- 1D Basement roof slab completed.
- 1B, 1C 1D
- Completion of 1st (first) slab.
- UPCOMING MILESTONES
- 1B, 1C 1D
- completion of 5th (fifth) slab.
Actual site photograph
PROGRESS TIMELINE
April 21
May 21
June 21
July 21
August 21
Construction Updates
9Other Activities
Clubhouse
TOWER STATUS
- Clubhouse internal block work electrical works
in progress. - STP above truss work and internal water proofing
in progress. - UG Sump 2 excavation in progress.
- Podium pour1 concrete complete pour2 works in
progress.
Actual site photograph
PROGRESS TIMELINE
April 21
May 21
June 21
July 21
August 21
Construction Updates
10Site Office Provident Parksquare Judicial
Layout, Kanakapura Rd, Bengaluru, Karnataka
560062 Regional Office Provident Housing
Limited No.8, Ulsoor Road, Bengaluru- 560
042 Tel 080-44555544
Email crm_at_providenthousing.com (Subject line
Project name/ unit number) Call Us 91 -
80-67724001 / 1 860 208 0000
Web www.providenthousing.com RERA Registration
Number RERA Nos. - Phase 1
PRM/KA/RERA/1251/310/PR/180217/002476 Phase 2
PRM/KA/RERA/1251/310/PR/180507/001648 Phase 3
PRM/KA/RERA/1251/310/PR/180507/001671 Phase 4 -
PRM/KA/RERA/1251/310/PR/190129/002307