QUESTION 2
Which of the following is a tool or technique
used in the Monitor and Control Project Work
process? A. Expert judgment B. Rejected change
requests C. Earned value technique D. Change
control tools
Correct Answer A
http//www.passin1day.com/PMP-dumps.html
3PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 2
As you are creating the Activity List, which
technique is recommended for subdividing the
project into smaller components called
activities? A. Decomposition B. Rolling Wave
Planning C. Expert judgment D. Deconstruction
Correct Answer A
http//www.passin1day.com/PMP-dumps.html
4PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 3
The Create WBS process identifies the
deliverables at the __________ level in the Work
Breakdown Structure (WBS). A. Lowest B. Any C.
Tenth D. Highest
Correct Answer A
http//www.passin1day.com/PMP-dumps.html
5PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 4
Which of the following is not an organizational
process asset that is used during the Plan Human
Resource Management process? A. Template for
organizational charts B. Template for position
descriptions C. Standardized role descriptions D.
Standardized stakeholder list
Correct Answer D
http//www.passin1day.com/PMP-dumps.html
6PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 5
Perform Integrated Change Control includes
several configuration management activities.
Which of the following is not part of Perform
Integrated Change Control? A. Change request B.
Configuration Verification C. Configuration
Status Accounting D. Configuration Identification
Correct Answer A
http//www.passin1day.com/PMP-dumps.html
7PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 6
After brainstorming potential project risks, what
is the recommended method for prioritizing these
risks and their mitigation plans? A. RACI
chart B. Control chart C. Fishbone Diagram D.
Probability and impact matrix
Correct Answer D
http//www.passin1day.com/PMP-dumps.html
8PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 7
If you are influencing factors that create
changes to the cost of the project, which process
are you using? A. Negotiate Costs B. Estimate
Costs C. Control Costs D. Determine Budget
Correct Answer C
http//www.passin1day.com/PMP-dumps.html
9PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 8
A RACI chart is an example of a
_________________. A. Network B. Flowchart C.
Responsibility assignment matrix D.
Hierarchical-type organization chart
Correct Answer C
http//www.passin1day.com/PMP-dumps.html
10PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 9
The most detailed level of the WBS is called the
_______________ . A. WBS element B. Work
package C. Project scope D. Deliverable
Correct Answer B
http//www.passin1day.com/PMP-dumps.html
11PMP Dumps - Project Management Professional v5
Practice Exam Questions
QUESTION 10
Which of the following is a hierarchical
representation of project risks? A. Risk
Register B. Risk Mitigation C. Risk categories D.
Risk Breakdown Structure