Title: CIMA G1 Braindumps
1Pass CIMA G1 - Management Accountant Gateway
exam in just 24 HOURS! 100 REAL EXAM QUESTIONS
ANSWERS CIMA G1 - Management Accountant
Gateway Buy Complete Questions Answers File
from http//www.exams4sure.com/CIMA/G1-practice-ex
am-dumps.html 100 Exam Passing Guarantee
Money Back Assurance
2- Question No 1
- You have received the following email from the
Group Finance Director, Felicity Bunyan - From Felicity Bunyan, Group Finance Director
To Senior Management Accountant - Subject Contract Costing
- Hi,
- I need your thoughts on two related matters.
- The Board is concerned that the Build Civil
Engineering subsidiaries are failing to achieve
their targets. The subsidiary directors claim
that this is due to poor contract costing and
budgeting arrangements. Profit targets for these
subsidiaries are established as follows - Build Civil Engineering has a sales force that
supports all four of the subsidiaries. The sales
forces responsibilities include makingedto
bidcontactforw construction contracts and also
monitoring advertised invitations to submit
bids. - Each opportunity to bid is evaluated by a
contract costing team of surveyors and other
experts who are employed by Bild Civil
Engineering. - When the team decides that there is a realistic
possibility of winning a contract and making a
profit they start to estimate the costs of
fulfilling the - contract.
- Once the total costs have been estimated, the
team adds a mark-up to cover administration and
marketing costs for both Bild Civil Engineering
and the subsidiary responsible for the contract.
The result is then combined with a target profit
to set the bidding price. The team allows for
likely bids from competitors when setting the
target profit. - Each subsidiary is required to report the profit
earned on each contract in progress during the
year. The subsidiarys directors are r each
contract and - also of the subsidiary as a whole. These reports
are collated and submitted to B board.
3- The latest report showed that 40 of the
contracts completed during the year had an
overall profit of less than 70 of target. Also,
55 of the contracts under way were reported as
being unlikely to achieve the targeted profit.
All of the subsidiary directo targets had been
unduly optimistic. - The subsidiary directors complain that a longer
term review shows that Bild is heavily affected
by the economy and changes in the economic
outlook can have a serious impact on their
ability to meet targets for signing up new
contracts. They have suggested that it is
inappropriate to manage the Bild Civil
Engineering subsidiaries as profit centres until
the economy has fully recovered from the
downturn and enters a period of strong growth. - I need you to draft a paper that I can submit to
the board that deals with the following - Firstly, please evaluate our contract costing
arrangements, paying particular attention to the
difficulties associated with setting realistic
profit targets. - Secondly, how valid is the argument that the
subsidiaries are subject to economic forces?
Which economic variables should we pay particular
attention to? - Thanks Felicity
- Question No 2
- The Group Finance Director, Felicity Bunyan, has
asked you into her office, where she tells you
the following - We have been asked to bid for a major Public Pri
have ever undertaken before. The government
wishes to build a new college on a greenfield
site on the outskirts of Capital City. They do
not have sufficient cash available to pay for
this outright so they have proposed that we work
with them on a PPP basis. - The construction work will take approximately
three years. We would normally set a price of
350 million for a project of this size, with our
own costs estimated at 300 million for the
construction work.
4- Once the construction work is over we will
maintain and operate the buildings and the site
itself. We will be responsible for all support
services, including landscaping, repair work,
cleaning and catering. The government will
appoint the academic and administrative staff
and will cover the costs of providing
educational services. - We will generate revenues from three sources.
Firstly, the government will pay an annual
facilities charge, which will cover both the cost
of leasing the college buildings and our
commitment to maintenance and upkeep. Secondly,
the site will include student accommodation.
Students will be able to rent rooms from us
during term time and we will be permitted to
charge a commercial rent. Thirdly, the college
catering will be a profit-making venture. We will
be able to charge staff and students for meals
and refreshments. - The proposed contract will run for 20 years after
the construction work has been completed. At the
end of that time we will sell the buildings,
including the student accommodation and catering
outlets, to the government for a nominal sum of
1. - This is by far the largest PPP project that we
have undertaken. I need you to email me your
views on the following - Firstly, how will Bild recognise profits from
this project? What matters will the company have
to consider when deciding how much profit we have
earned, if any, in any given year? - Secondly, what are the specific challenges
5- Question No 3
- Mark Grassington, Managing Director of Bild Civil
Engineering, has asked for your advice. - We have been receiving from some of our larger
complaints sub-contractors about our working
relationships. They feel that time and effort are
being wasted because we do not properly manage
our relationship with them. - To put this in perspective, Bild Civil
Engineering has seventeen major subcontractors
on its list of preferred suppliers. Some are
general builders who provide most of the major
trades, from digging foundations to bricklaying
and other trades. Others are more specialised
and focus on drainage or other specific tasks.
We find that the specialists are more expensive
than the general builders, but they have greater
expertise and so they may be used for difficult
tasks, such as installing drainage in unstable
soil. - The regional subsidiaries of Bild Civil
Engineering usually contract for a project and
then invite the subcontractors to tender for the
work. Subcontractors have very little input into
the contract specification itself. They also find
it difficult to manage their commitments because
they are often invited to tender for work by
more than one Bild subsidiary at the same time,
even though they would not have the capacity to
accept all of the work if all of their tenders
were successful. - There have been times when it has been difficult
to find a subcontractor for a project because
many of our preferred subcontractors would choose
to work with our competitors rather than with us
when they have a choice. - Could you give me some ideas that I can present
to the next board meeting? - Firstly, I have always been impressed by the
balanced scorecard diagrams that you prepare for
other aspects of the business. Could you outline
a set of measures that could be developed into a
balanced scorecard for managing the whole
process of working with subcontractors? Please
also provide a brief explanation for each
measure. - Secondly, advise the company regarding processes
and controls that we could adopt to manage the
whole process of the collaboration wit
6Question No 4 he Group Finance Director has left
you the following memo MEMORANDUM To Senior
Management Accountant From Felicity Bunyan,
Group Finance Director Subject Debt covenant As
you know, we have significant bank borrowings.
The bank has put a number of 'debt covenants' in
place. These are conditions that must be met if
we are to be allowed to carry on with the loan.
If we breach any of those conditions, the bank
has the right to demand immediate repayment of
their loan and to take possession of the assets
that we have pledged as security in the event
that we cannot afford to repay. One of those
conditions is that our gearing ratio cannot
exceed 37 when we measure debt as a percentage
of total long term finance. Our gearing ratios
were as follows over the past few years 2012
32 2013 34 2014 33 We have a problem on the
horizon. As you are aware, in order to maintain
flexibility, Bild has used operating leases to
finance the majority of its construction
equipment. Most of these leases are over three or
five years. Proposed changes to the rules
relating to the accounting treatment of leases
mean that we may have to recognise additional
long term liabilities before the loans are due
for repayment. Doing so will put us in technical
default with respect to our debt covenant,
pushing our gearing to around 40. Please draft a
paper for me that
7- Analyses our gearing position with respect to the
nature of our business and its overall position. - Suggests an approach that might be taken to
negotiating a change to the loan conditions with
the bank so that our technical default might be
overlooked. - Question No 5
- The following memo was on your desk when you
arrived at work this morning MEMORANDUM - To Senior Management Accountant
- From Felicity Bunyan, Group Finance Director
Subject public-private partnership proposal - The Central subsidiary of Bild Civil Engineering
has received a very interesting proposal to
tender for a major government contract. The
intention is that we will build a new hospital
for the City Health Board, which is funded by the
government and is responsible for the management
of health care. City Health Board is keen for us
to tender for the running of the hospital
infrastructure once the construction work is
complete. It is that aspect that I need you to
consider. - I have copied the City Health Boards summary of
its requirements for you. I need you to write me
a report covering two issues - What are the planning and control issues,
including financial controls, associated with
our undertaking to run this hospital on the basis
outlined by City Health Board? - What factors should Bild take into account in
deciding whether to bid for this proposal?
Please justify the inclusion of each factor that
you identify. - The summary of City Health Board's requirements
can be found by clicking the Reference Materials
button. - http//www.exams4sure.com/CIMA/G1-practice-exam-du
mps.html
8- Buy Complete Questions Answers File from
- PDF Version Test Engine Software Version
- 90 Days Free Updates Service
- Valid for All Countries
http//www.exams4sure.com/CIMA/G1-practice-exam-du
mps.html