Title: Introduction to Surveying BPD LEVELLING PROCEDURES
1Introduction to Surveying (BPD)LEVELLING
PROCEDURES
- Dr Philip Collier
- Department of Geomatics
- The University of Melbourne
- p.collier_at_unimelb.edu.au
- Room D316
2Review of levelling
- In this lecture we will cover
- Equipment and procedures
- Purposes of levelling
- Some definitions
- Reading a staff
- Collimation error
- Two-peg test
- Booking and reduction
- Adjustment
- Errors
- Applications
3Equipment
- Level
- Tripod
- Staff
- Change plate
- Staff bubble
- 50 m tape measure (sometimes)
4What is levelling?
- A measurement process whereby the difference in
height between two or more points can be
determined
5When do we level?
- Typical examples include
- To establish new vertical control (BM or TBM)
- To determine the heights of discrete points
- To provide spot heights or contours on a plan
- To provide data for road cross-sections or
volumes of earthworks - To provide a level or inclined plane in the
setting out of construction works
6Definitions
- Level surface
- A surface over which water will not flow
- The direction of gravity is always normal to a
level surface - Horizontal surface
- A horizontal surface will be tangent to a level
surface - Over short distances (lt100 m) the horizontal
surface and the level surface will coincide
7Definitions (cont.)
8Reading an E-face staff
0.339
0.33
0.3
9Collimation error
- Occurs when the line of sight (as defined by the
cross-hairs) is not horizontal - Leads to an incorrect staff reading
line of sight
error
horizontal line
10Two-peg test
- Identifies whether the level has a collimation
error - Allows the collimation error to be determined
- See the plane surveying web site for the two-peg
test procedure
11More definitions
- Datum
- A reference surface to which the heights of all
points in a survey or on a site are referred - May be arbitrary or a national height datum
- In Australia we have the Australian Height Datum
(AHD) - The surface which defines the AHD is
(approximately) Mean Sea Level (MSL)
12More definitions
- Reduced Level (RL)
- The height of a point above the datum
- Benchmark (BM)
- A stable reference point of known RL
- Usually used as the starting and finishing point
when levelling - Temporary Bench Mark (TBM)
- A point placed (e.g. peg, nail, spike) to provide
a temporary reference point
13More definitions
- Backsight (BS)
- Always the first reading from a new instrument
station - Foresight (FS)
- Always the last reading from the current
instrument station - Intermediate sight (IS)
- Any sighting that is not a backsight or foresight
14More definitions
- Change point (CP)
- Location of the staff when the level is moved
- Change points should be...
- Stable
- Well defined
- Recoverable
- e.g. sharp rock, nail, change plate, etc...
15Rules for levelling
- Always commence and finish a level run on a
Benchmark (BM or TBM) - Keep foresight and backsight distances as equal
as possible - Keep lines of sight short (normally lt 50m)
- Never read below 0.5m on a staff (refraction)
- Use stable, well defined change points
16Levelling procedures
- The example on the plane surveying web site
shows - Observation procedures
- Booking procedures
- Reduction procedures
17A sample loop
18Booking the observations
CP 3
BM A
1.32
3.98
Kerb
Kerb
CP 1
CP 2
Post
19Booking the observations
CP 3
BM A
2.56
Kerb
1.25
3.65
Kerb
0.67
CP 1
CP 2
Post
20Booking the observations
CP 3
BM A
Kerb
Kerb
3.49
2.58
1.54
CP 1
CP 2
Post
21Booking the observations
CP 3
BM A
Kerb
Kerb
2.64
3.79
CP 1
CP 2
Post
22Reducing levels (Rise and Fall)
23Reducing levels (Rise and Fall)
24Reducing levels (Rise and Fall)
25Reducing levels (Rise and Fall)
26Reducing levels (Rise and Fall)
27Reducing levels (Rise and Fall)
28Reducing levels (Rise and Fall)
29Reducing levels (Rise and Fall)
30Reducing levels (Rise and Fall)
31Reducing levels (Rise and Fall)
32Reducing levels (Rise and Fall)
33Reducing levels (Rise and Fall)
34Reducing levels (Rise and Fall)
35Reducing levels (Rise and Fall)
36Loop misclosure
- Misclosure
- The amount by which the measured height
difference (DHmeas) differs from the known height
difference derived from the RLs of the starting
and finishing benchmarks (DHknown) - Misclosure DHknown - DHmeas
37An acceptable misclose?
- Small misclosures in closed level loops are
expected because of the accumulation of errors - If the misclosure is small, it can be adjusted
- If the misclosure is large, the loop (or part of
it) must be repeated - Misclosures can also result from errors in
published BM levels and from BM instability
38Testing the misclose
- The amount of misclosure we are prepared to
accept depends on the accuracy we are hoping to
achieve - For routine levelling, the third order levelling
standard is adopted - misclosure ? 12?k mm
- where k is the length of the loop in km
39Continuing the example
- The misclosure is 30 mm
- The length of the loop is 0.7 km
- The misclosure limit is
- 12?(0.7) 10 mm
- The misclosure of 30 mm is too big
- The loop must be repeated (or find the error)
40Adjusting the misclose
- Adjustment is carried out to ensure that the
measured and known RLs of the closing benchmark
agree - The misclosure is linearly distributed according
to the number of set-ups - The adjustment per set-up for the previous
example is (0.03/4)...
41Adjusting the misclose
42Adjusting the misclose
1(0.03/4)
43Adjusting the misclose
2(0.03/4)
44Adjusting the misclose
3(0.03/4)
45Adjusting the misclose
4(0.03/4)
46Adjusting the misclose
47Errors in levelling
- Collimation
- Parallax
- Change point instability
- Instrument instability
- Staff instability
- Benchmark instability
- Refraction
48Errors in levelling
- Staff reading and interpolation errors
- Staff verticality
- Instrument shading
- Temperature on staff
- Booking errors (e.g. using just 1 benchmark)
- Earth curvature
- Magnetic field effects on auto level
49Applications of levelling
- Point heights (relative to a datum)
- Height differences (independent of datum)
- Longitudinal sections and cross sections
- Data for volume calculations
- Contouring
- Setting out
50Establishing a new point
51Measuring height differences
52Profiles and cross-sections
53Plotting contours
The RLs for points A, B and C have
been determined by levelling. We are now
required to determine the location of
the contours using a 0.5 m contour interval.
54Plotting contours
55Plotting contours
LINE AC ?HAC 2.905 - 1.100 1.805 DAC 14.14
m For the 1.5 m contour D 14.14(1.5 -
1.1)/1.805 3.13 For the 2.0 m contour D
14.14(2.0 - 1.1)/1.805 7.05 For the 2.5 m
contour D 14.14(2.5 - 1.1)/1.805 10.97
56Plotting contours
LINE BC DHBC 2.905 - 2.510 0.395 DBC 10
m no contours cross this line
57Plotting contours
58Introduction to Surveying (BPD)LEVELLING
PROCEDURES
- Dr Philip Collier
- Department of Geomatics
- The University of Melbourne
- p.collier_at_unimelb.edu.au
- Room D316