Title: Coffenberry Gym Construction


1
Coffenberry Gym Construction
Construction begins March 3rd, 2008
2
Staging
A temporary office trailer, power and sanitary
provisions were brought in. SUSD power pole was
removed and power was transferred to the
contractor. The entire perimeter was fenced.
3
Coffenberry Gym Construction
The first thing that took place was drilling a 21
foot deep shaft for the elevator needed on the
second story. This is completed.
4
Coffenberry Site Work
A Vapor barrier was installed on the area serving
the concrete slab.
5
Underground work
Water lines from the City water were connected
under Spruce Avenue along with the main sewer
connection
Underground plumbing lines were installed
throughout the gym area.
6
Underground work
Wood footing forms were installed for the next
days concrete pour.
Locker room shower drains Installed at west end
of gym.
7
Underground work
Lobby and concession plumbing installed at east
end of building. The red caps (right picture) are
guards for the tops of the rebar sticking up.
8
Concrete Pour
4 truckloads of concrete (30 yards) were poured
in the footings that support the buildings
perimeter on March 18, 2008, 15 days after ground
breaking took place.
9
Water Service- We have water!
Water is being flushed after being connected to
the gym and at the rear of the building for
irrigation on March 18th, 2008.
10
Change Order
  • Gym walls are constructed of concrete block,
    insulated and needing to be regularly sealed. In
    order to bring the price of construction down for
    bidding purposes a product called Dry-Block was
    removed from the project. This product creates a
    water tight block, increases the weight of the
    block and increases the cost of installation.
  • The cost of this change from Regular Block to
    Dry-Block was a 12,000.00 price increase. This
    allows us the advantage of NOT having to
    regularly seal the building at a cost of
    6,000.00-7,000.00 (14,817 square feet X 0.49)
    every three to five years and insures a water
    tight building.

11
Bleachers
Bleachers have been ordered. A total of 400
seats, 200 each side of the gym 48,180.00 total
cost including motor operation, 2 score tables
and railings.
12
Gymnasium Lockers
Lockers will be ordered next week. The two types
we are obtaining are the Junior Varsity and the
Intramural types. Cost of the lockers without
installation is 49,774.00. Our department will
construct bases and install the lockers
13
End