ECJ case law on remedies - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

ECJ case law on remedies

Description:

A joint initiative of the OECD and the European Union, ... C-26/03, Stadt Halle OECD ... C-26/03, Stadt Halle. Broad meaning of the concept of decision' ... – PowerPoint PPT presentation

Number of Views:89
Avg rating:3.0/5.0
Slides: 21
Provided by: droui
Category:
Tags: ecj | case | law | remedies | stadt

less

Transcript and Presenter's Notes

Title: ECJ case law on remedies


1
ECJ case law on remedies
  • Leading up to the new Directives

2
Issues
  • Timelines (especially standstill period)
  • Direct awards
  • Remedies outside the scope of the Directives

3
Overview
  • C-111/97, EvoBus
  • C-81/98, Alcatel
  • C-470/99, Universale Bau
  • C-327/00, Santex
  • C-249/01, Hackermüller
  • C-230/02, Grossmann Air Services
  • C-26/03, Stadt Halle

4
C-111/97, EvoBus Austria
  • Facts
  • Austria failed to implement Directive 92/50/EEC.
  • Therefore the competence (jurisdiction) to hear
    disputes regarding service contracts was not
    attributed to any court.

5
C-111/97, EvoBus Austria
  • ECJ The Court referred to C-54/96, Dorsch and
    held that it is for the legal system of each
    Member State to determine which court or tribunal
    has jurisdiction to hear disputes involving
    individual rights derived from Community law.

6
C-81/98, Alcatel
  • Facts
  • Austrian procurement law does not provide for a
    specific obligation for a contracting authority
    to make the award decision itself known to
    bidders.
  • Contracts are concluded when the successful
    bidder receives a notice of acceptance by the
    contracting authority.
  • The Federal Procurement Office is empowered to
    set aside unlawful decisions only before and
    until the contract is concluded.
  • In practice, tenderers had no knowledge about
    award decisions.
  • Other tenderers learned about contract in press
    and made applications for review 5-15 days later.

7
C-81/98, Alcatel
  • ECJ
  • Article 2 (1) (b) Power to set aside
    decisions taken unlawfully, including to be
    defined widely the provision does not lay down
    any restrictions with regard to the nature and
    content of those decisions
  • Article 2 (6) effects of powers on a contract
    concluded subsequent to its award, after the
    conclusion of a contract following its award
  • The decision to award the contract must in all
    cases be open to review procedures prior to the
    conclusion of the contract.
  • Confirmed in C-212/02, Commission v Austria

8
C-212/02, Commission v Austria
  • ECJ
  • All tenderers must be informed of the contract
    award decision prior to the conclusion of the
    contract, so that there is a genuine possibility
    of bringing an action.
  • A reasonable period must elapse between the time
    when the award decision is communicated to
    unsuccessful tenderers and the conclusion of the
    contract, in order to make is possible for
    unsuccessful tenderers to have sufficient time to
    examine the validity of the award decision and in
    particular to apply for interim measures.

9
After the Austrian cases open questions
  • How long should the standstill period be?
  • What are the consequences for the contracting
    authorities of not respecting the standstill
    period?
  • Are there any exceptions to the standstill period?

10
Standstill periods in days
  • Austria 7 /14 Bulgaria 10
  • Czech 15 Denmark 7-10
  • Estonia 14 Finland 21/28
  • France 10 Germany 14
  • Hungary 8 Ireland 14
  • Italy 30 Lithuania 10
  • Luxembourg 15 Malta 10
  • Netherlands 15 Poland 7
  • Portugal 10 Romania 15
  • Slovakia 14 Slovenia 20
  • Sweden 10.

11
C-470/99, Universale Bau
  • Facts
  • (State of) Vienna procurement rules foresaw
    limitation periods within which certain allegedly
    unlawful decisions could no longer be challenged.
  • After the limitation period had passed, such
    decisions could no longer be challenged.
  • Remedies Directive does not provide for any
    limitation periods.

12
C-470/99, Universale Bau
  • ECJ
  • In absence of Community rules, Member States are
    free to provide procedural rules if coherent with
    fundamental principles of the EC Treaty.
  • 2 week limitation period in principle consistent
    with principle of effectiveness and equivalence
    (C-231/96), time limits need to be appropriate.

13
C-327/00, Santex
  • Facts
  • Italian law provides that an invitation to tender
    or clauses thereof must be challenged within the
    limitation period of 60 days. When that period
    has expired a challenge is no longer possible.
  • Bidder did not contend specific (potentially
    discriminatory) clause because contracting
    authority led him to believe that disputed clause
    would be interpreted in a non-discriminatory
    manner.
  • After time limitation period had passed,
    contracting authority excluded bidder from tender
    procedure on the basis of the potentially
    discriminatory clause.

14
C-327/00, Santex
  • ECJ
  • (Citing Universale Bau), found 60 days period to
    be reasonable but held that the changing conduct
    of the contracting authority had rendered the
    exercise of the rights conferred on tenderer
    excessively difficult.
  • National court must interpret domestic law, as
    far as possible, in a way which accords with
    the requirements of EC law or must even, if
    necessary, refrain from applying the
    limitation-period.

15
C-249/01, Hackermüller
  • Facts/problem
  • May a bidder who has not been eliminated by the
    contracting authority, be excluded from the
    review procedure by a decision of the review
    body?

16
C-249/01, Hackermüller
  • ECJ
  • Elimination of the bid before making the
    selection is a decision against which it must be
    possible to seek review.
  • Review body must afford tenderer right to
    challenge the validity of the exclusion in the
    review procedure, at the end of which, however,
    the review body may reach the conclusion that the
    bid should have been eliminated at the outset and
    that his application is therefore dismissed, as
    he neither has been nor risks being harmed by the
    alleged infringement.

17
C-230/02, Grossmann Air Services
  • Facts
  • G submitted a tender for the provision of
    non-scheduled air transport services for the
    Austrian government.
  • Government annulled first invitation to tender,
    since only one offer remained after the
    examination of bids.
  • In the second tender G did not submit an offer
    but challenged the award decision on the ground
    that the tender documents had been tailored from
    the outset to the then successful tenderer Lauda
    Air.

18
C-230/02, Grossmann Air Services
  • ECJ
  • It must be possible for an undertaking to seek
    review of discriminatory specifications before
    submitting a bid and without waiting for the
    contract award procedure to be terminated.

19
C-26/03, Stadt Halle
  • Facts/problems
  • Is the remedies Directive applicable to decisions
    taken outside the formal award procedure and
    prior to a formal call for tenders?
  • Decision to award contract outside the formal
    procedure.
  • Decision not to initiate award procedure.

20
C-26/03, Stadt Halle
  • Broad meaning of the concept of decision
  • Any act of a contracting authority adopted in
    relation to public contract capable of producing
    legal effects regardless of whether that act is
    adopted outside or as part of a formal procedure.
  • Not subject to review are acts which constitute a
    preliminary study of the market or which are
    purely preparatory.
Write a Comment
User Comments (0)
About PowerShow.com