FERC Order 890 Transmission Integration of Renewable Energy Projects - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

FERC Order 890 Transmission Integration of Renewable Energy Projects

Description:

Conditional firm holder knows maximum curtailment exposure 100's hours/month. In Conditional Firm's final state, if not told in the preschedule (24 hour ... – PowerPoint PPT presentation

Number of Views:62
Avg rating:3.0/5.0
Slides: 16
Provided by: jhp4
Category:

less

Transcript and Presenter's Notes

Title: FERC Order 890 Transmission Integration of Renewable Energy Projects


1
FERC Order 890 Transmission Integration of
Renewable Energy Projects
  • Geothermal Resources Council
  • John Pease PE, MBA
  • Project Manager
  • Technology Innovation
  • Bonneville Power Administration
  • October 2, 2007

2
(No Transcript)
3
(No Transcript)
4
(No Transcript)
5
FERC Order 890 Be Careful of What You Ask For
  • BPA initiates action with FERC in 2005 to make
    use of transmission that is often oversubscribed
    but under utilized
  • Conditional Firm Proposal Presented by BPA to
    FERC March 16th, 2005 in Portland
  • Conditional firm holder knows maximum curtailment
    exposure 100s hours/month
  • In Conditional Firms final state, if not told in
    the preschedule (24 hour notice) that a
    curtailment may occur, then considered firm.
    Before systems are developed, cuts will be within
    hour.
  • Uses additional Available Transmission Capacity
    (ATC) that currently goes unused most hours of
    the year
  • Bounds transmission availability risk to enable
    project financing!

6
  • Reliability Redispatch Pilot Presented by BPA
    to FERC March 16th, 2005 in Portland (BPA feels
    it can not do an economic redispatch, but other
    transmission providers may be able to)
  • Transmission provider will adjust generation
    within the hour from bidders of Incremental and
    Decremental resources to alleviate a transmission
    event that pushes flows up against the Operating
    Transfer limits (OTC). Does not increasing
    available ATC, but does reduce curtailment of
    schedules.
  • Done for Network (native load) customers only
    historically again, this is only reliability
    redispatch
  • Pay for net costs of generation (or loads) who
    may reduce generation to alleviate constraint
  • Prototype project scheduled for BPA summer, 2007
    for reliability redispatch
  • Problem
  • FERC issues 1200 page document that helps to
    utilize unused transmission
  • Lots of strings attached.

7
890 Goal Nondiscriminatory Open Access
Highlights
  • Open Access Transmission Planning
  • Utilities must submit an Attachment K to describe
    its transmission planning process
  • Must address the following principles
    Coordination, Openness, Transparency, Information
    exchange, Comparability, Dispute Resolution,
    Regional Participation, Congestion Studies and
    Cost allocation.
  • FERC hopes to see greater coordination between
    interconnected systems, state authorities and
    stakeholders

8
Order 890 Highlights
  • Energy Imbalance (EI)
  • Difference between actual scheduled energy
  • Must be based on incremental costs so deviations
    are not punitive
  • Primarily helps wind that cannot accurately
    schedule their energy output
  • Was largely based on BPAs methodology, with some
    new twists
  • BPA will finalize its EI in its next rate case

9
Order 890 Highlights
  • Planning Redispatch to Increase ATC
  • Utilities must study two different types of
    redispatch Planning and Reliability
  • Planning Redispatch
  • Utilities must expand or upgrade its transmission
    service, or if more cost effective, redispatch to
    meet a PTP request if ATC is not available, if
    they can do so reliably
  • Can be used as a bridge until new transmission
    is built
  • Non-binding estimates of cost must be provided
  • Study must be requested by the transmission
    customer
  • Due to non-power constraints (flows for fish,
    etc), BPA is not able to commit to redispatch of
    the Federal Hydro system

10
Order 890 Highlights
  • Redispatch Service
  • Reliability Redispatch
  • Used for redispatch of resources to ease a system
    constraint that would result in curtailment of
    network service or transmission providers loads
  • What is used today
  • If your resource is designated a Network resource
    or not may be critical on how costs for the
    service are allocated.

11
Order 890 Highlights
  • Conditional Firm Service
  • Tutorial
  • Access to transmission determined by Available
    Transfer Capability (ATC) needed for the
    requested POR and POD (based on a Path
    Utilization Factor analysis)
  • Rights can be requested on a Firm or non-Firm
    curtailment priority basis
  • Firm transmission available in all hours when
    all lines are in service (unless there is
    parallel path flow on another system
  • Non-Firm firm rights not used or unallocated
    transmission made available on an hourly basis in
    pre-schedule and real-time (it has a higher
    chance of curtailment than firm.)
  • Conditional firm Firm except when the
    transmission provider uses the Conditional Firm
    Hours (if that option was chosen) or when the
    system conditions defined in the contract are
    occurring (if that option was chosen) choice is
    made by the customer, then non-Firm, but
    curtailed last (non-firm curtailment order)

12
Order 890 Highlights
  • Conditional Firm (CF) Service Two Types
  • Ability to Financially Support New Transmission
  • Offered as a bridge until new transmission is
    placed in service
  • Planning redispatch study is offered as well (not
    tied to CF, in no way guarantees an offer)
  • Pricing of LTF CF is at the LTF PTP rate.
    Pricing (of upgrade) is either the higher of
    actual incremental costs or imbedded rate of the
    transmission provider
  • May be able to negotiate a fixed rate, capped at
    the total fixed and variable costs of the
    generation resources providing the resource
  • If a customer doesnt elect a fixed rate, then
    transmission provider can calculate costs on a
    monthly basis

13
Order 890 Highlights
  • Do Not Support the Building of New Transmission
  • Planning Redispatch and Conditional Firm subject
    to limitations
  • Term of conditions is locked for two years, then
    will be reassessed to see if transmission
    provider can continue to provide the service
    reliability and if any change in the number of CF
    hours or the system conditions are needed
  • Pricing is either the higher of actual
    incremental costs or imbedded rate of the
    transmission provider (BPA pricing of CF is at
    the LTF PTP rate)
  • Limiting the hours of curtailment (original
    proposal) is replaced by potentially ending
    transmission service altogether if system
    conditions change! However, TP must be able to
    demonstrate that they can no longer provide the
    service

14
Order 890 Area of Concern
  • A Network resource is typically served by the
    respective transmission provider
  • If a Network resource wants to sell to a third
    party (not a required load in a control area),
    that resource may lose preferential transmission
    access. (BPA - actual requirement is for
    undesignation of the network resource to sell to
    a third party, but can do so temporarily and not
    lose TX access. BPA is currently considering
    removing this requirement in the OATT that will
    be filed)
  • May then have to compete for what transmission is
    still available concern that resources will be
    captured by the control area. (BPA - the
    undesignation can be done temporarily and then
    the transmission beyond that period is still
    reserved for that partys use in serving its
    load. BPA is considering trying to remove this
    requirement altogether)

15
Conclusion
  • BPA is non-FERC jurisdictional, but chooses to
    comply
  • BPA is currently holding public discussions with
    its customers to determine what portions of the
    new pro forma OATT it will modify in its Order
    890 tariff filing
  • BPA (or respective control area) website to stay
    up to date http//www.transmission.bpa.gov/Busine
    ss/Rates_and_Tariff/order890.cfm
  • BPA account executives will help get your energy
    to load
Write a Comment
User Comments (0)
About PowerShow.com