Title: Measurement


1
Measurement Verification Section
  • Part 1 MV Overview
  • MV in the Five Phases
  • Part 2 Risk Assessment
  • Risk Assessment and Allocation
  • Part 3 FEMP M V Methods
  • Methods and Applications
  • Part 4 M V Plan Review
  • Checklist
  • Part 5 M V Case Studies
  • Application of lessons

2
Part 1 MV Overview
  • Purpose of MV
  • MV in the five phases
  • Contractor responsibilities
  • Owner responsibilities

3
Purpose of MV
Purpose of MV
  • Performance Contracting is an arrangement where
    the exact benefits are only known afterwards
  • There is an element of risk related to the
    uncertainty of the delivered benefit
  • MV quantifies the savings
  • MV allocates risk between parties
  • MV supports the guaranteed savings

4
Savings
Purpose of MV
  • ESPC can recognize two types of savings
  • Energy Cost Savings
  • Energy-Related Cost Savings

5
Energy Cost Savings
Purpose of MV
  • Reductions in energy use
  • Reductions in peak demand
  • Reductions in energy rates
  • Shifting time-of-use to lower-cost periods
  • Converting to less expensive fuels
  • Self-generation (and cogeneration / CHP)
  • Reduced water and other utility use

6
Energy-Related Cost Savings
Purpose of MV
  • Energy-related cost savings are primarily due to
    reduced OM expenses
  • Parts labor costs
  • Emergency repair costs
  • Equipment replacement costs
  • Cost savings must come from existing budgets or
    it will be difficult to pay the ESCO!

7
Super ESPC is Guaranteed Savings
Actual saving will fluctuate, but should always
be greater than the guaranteed amount
Actual Estimated Guaranteed
Savings
1 2 3 4 5 6 7 8 9 10 11 12 13
14 Contract Year
8
Why You Need MV
Purpose of MV
  • Savings are guaranteed, but actual savings
    fluctuate every year
  • MV demonstrates guarantee is met
  • MV identifies problems
  • MV verifies continued success of projects
  • What you dont measure, you cant manage (Jack
    Welch, former GE CEO)

9
MV During the Five Phases
10
Phase 1 Planning
  • What are project motivators?
  • Improved comfort, better performance
  • Reduced energy costs
  • Reduced OM costs
  • What does MV need to accomplish?
  • Monitor equipment performance
  • Find additional savings
  • Improve OM
  • Enforce guaranteed savings

11
Owner Responsibilities
  • Define project goals in terms of
  • Necessary performance improvements
  • Energy cost savings
  • Energy-related cost savings
  • Define MV requirements
  • Total energy cost savings
  • Equipment performance
  • Long-term verification
  • These need to be included in the RFP!

12
Phase 2 Project Development
  • Contractor Responsibilities
  • Complete Risk Responsibility Matrix
  • Develop MV Overview in Initial Proposal
  • Explain and justify overview
  • How will risks responsibilities be assigned?
  • How will contractor prove performance?
  • What will be measured?
  • What will not?

13
Responsibility Matrix
  • The Risk Responsibility Matrix describes how
    the contractor will address risk factors that
    affect savings and project economics. These are
    broadly characterized as
  • Financial and Economic
  • Facility Usage and Operations
  • Equipment Performance
  • RR Matrix drives MV Overview

14
MV Overview
  • The MV Overview (a.k.a. Initial MV Plan) is
    submitted as part of Initial Proposal. It is not
    a complete plan, but
  • Describes intended approach
  • Purposely lacks detail
  • The MV Overview allows the Owner and the
    contractor to develop a satisfactory MV Plan
  • The MV Overview drives the Detailed Energy Survey

15
Owner Responsibilities
  • Owner Responsibilities
  • Discuss planned physical or operational site
    changes with contractor
  • Provide energy use and rates to contractor
  • Review RR Matrix, MV Overview and assumptions
  • Provide critical comments and feedback
  • Engage Project Facilitator and third-party support

16
Phase 3 Negotiation and Award
  • Contractor Responsibilities
  • Modify Risk Responsibility Matrix
  • Perform Detailed Energy Survey and document
    baseline information
  • Finalize Site-Specific MV Plan
  • Develop ECM Commissioning Approach

17
Detailed Energy Survey
  • MV Plan drives Detailed Energy Survey (DES)
    activities
  • The Detailed Energy Survey defines the baseline
    of the facility, which consists of
  • Energy use and cost history
  • Equipment list and measured performance
  • Factors that influence energy use
  • Operations and maintenance costs
  • If this information is not documented, it is
    lost. It cannot be determined after
    installation.

18
Site-Specific MV Plan
  • RR Matrix drives MV Plan
  • The Site-Specific MV Plan includes
  • What will be done (and when)
  • How will performance be verified
  • Who will conduct these activities (and when)
  • How will savings be calculated
  • How will baseline be adjusted to account for
    varying conditions
  • OM reporting requirements for Owner

19
Commissioning Approach
  • ECM Commissioning (Cx) approach is not a complete
    plan
  • Describes (generally) how each ECM will be
    commissioned prior to acceptance

20
Owner Responsibilities
  • Review MV Plan and Cx Approach
  • Provide critical comments and feedback
  • Approve Site-Specific MV Plan and Cx Approach
  • Participate in and witness DES activities
  • Review DES baseline information
  • Engage Project Facilitator and third-party
    support

21
Phase 4 Implementation
  • Contractor Responsibilities
  • Submit Commissioning Plan
  • Commission measures
  • Submit Commissioning Report and
    Post-Installation Report

22
Commissioning Plan Report
  • Commissioning (Cx) is the process of ensuring
    that systems are installed, tested, and capable
    of meeting design intent
  • The Commissioning Plan defines start-up
    procedures and functional performance tests for
    each piece of equipment as well overall systems
  • The Commissioning Report documents the
    commissioning activities and any issues that were
    discovered and resolved

23
Post-Installation Report
  • The contractor submits the Post-Installation
    Report after the project has been installed. It
    includes
  • Project description
  • List of installed equipment (as built)
  • Performance measurements
  • Expected savings for the first year

24
Owner Responsibilities
  • Witness MV and commissioning activities. Be
    involved!
  • Approve Commissioning and Post-Installation
    reports
  • Engage Project Facilitator support

25
Phase 5 Performance Close-Out
  • Contractor Responsibilities
  • Provide agreed-upon performance-period services
  • Perform required operations maintenance
  • Submit Annual Reports
  • Take corrective action (if needed)
  • Annual savings reconciliation (if needed)

26
Annual Reports
  • The contractor submits Annual Reports to
    demonstrate that savings have occurred. They
    should include
  • Project description
  • Performance measurements this year
  • Realized savings for the year
  • Comparison to the guaranteed amounts
  • Reports should also contain
  • Problems that need Owner attention
  • Operations maintenance and repair replacement
    activities conducted

27
Owner Responsibilities
  • Contract administration
  • Perform agreed-upon operations maintenance
  • Submit proof of preventive maintenance
  • Witness verification activities
  • Review approve Annual Reports
  • End of contract term

28
Review and Discussion
  • Actual savings from Super ESPC are only known
    after project implementation
  • Savings guarantees are only as good as the MV
    supporting them
  • The Owner sets the MV goals the ESCO implements
    the plan

29
Review Questions
  • Why is MV needed?
  • Who is responsible for MV?
  • How are MV and commissioning different?