Title: Recoil Proton Detector


1
Recoil Proton Detector
  • Silicon and cryostat review

2
SUMMARY
  • Project control (coordination)
  • Work packages
  • Cryostat mechanical design
  • Schedule
  • Tasks to be done

3
PROJECT CONTROL
  • You must named a project leader to
  • To define a management plan
  • To define work packages
  • To do the WP coordination
  • To do analysis risks
  • To do logical steps and strategy
  • To define cost, resources, and schedule
  • Etc

4
RPD Work packageslikely
  • Identify and named responsible WP task

5
CRYOSTAT MECHANICAL DESIGN TASK
  • Typically for cryostat WP for example
  • Link with silicon detectors
  • mechanical,
  • Thermal
  • Cabling
  • position etc
  • Link with phase separator and internal piping
    (must fixed it vibration)
  • Link with Ring A
  • Outside size
  • Silicon electronics interface
  • Water condensation risk
  • Link with barrel flanges
  • Fixation
  • Deformation
  • Position
  • Link with proximity cryogenic and vacuum
    (external piping)
  • Link with LHT (position, safety tube)
  • Mechanical studies on limits
  • To define size, material,

6
SCHEDULE
  • following tasks must be ready for may08 tests
    beam
  • Silicon detectors and internal cryogenic mid
    march
  • Cryostat beginning of march
  • Barrel and internal structure end of feb
  • Frame and tooling mid of feb
  • Ring (A,B) beginning of march
  • Proximity cryogenics end of march
  • Fluids and cabling end of march
  • LHT mid march
  • Slow control beginning of march

7
TASKS TO BE DONE
  • Each responsible must prepare a Technical Design
    Review of WP
  • Cryostat mid December
  • Cooling of silicon and internal cryogenics mid
    January
  • Proximity cryogenics mid January
  • Barrel and internal structure mid January
  • Ring (A,B) depends of B fabrication time
  • LHT (probably PRR) but discuss with barrel
  • Mounting and dismounting procedure (maintenance)
    mid january
  • Slow control mid january
  • Tooling mid January
  • Frame mid January
  • The project leader do the link and the
    coordination of these WP
  • Quickly identify conflicts (eventual)