ScreeningLevel REZ Analysis Tool: Outstanding Modeling Questions - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

ScreeningLevel REZ Analysis Tool: Outstanding Modeling Questions

Description:

What size/ configuration of lines are used in the model? Inclusion of multiple ... 500 kV AC&DC. 765kV AC. Circuits. Single. Double. Initial Recommendation ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 12
Provided by: west51
Category:

less

Transcript and Presenter's Notes

Title: ScreeningLevel REZ Analysis Tool: Outstanding Modeling Questions


1
Screening-Level REZ Analysis Tool Outstanding
Modeling Questions
  • Lawrence Berkeley National Laboratory
  • Black Veatch
  • Generation Transmission Modeling Work Group

2
Overview of Open Modeling Issues
  • Transmission Component
  • Distance estimation
  • Lumpiness of transmission
  • Not lumpy
  • Lumpy
  • How is cost calculated for underutilized lines?
  • What size/ configuration of lines are used in the
    model?
  • Inclusion of multiple resources on the same line
  • How is cost calculated for complementary
    resources
  • Bus-bar costs
  • Granularity of resource data
  • Market Value Adjustment Factors
  • Adjustments to include in model
  • Load Zones
  • Number and location
  • Non-REZ Resources
  • Storage

3
Transmission Lumpiness
  • Transmission is lumpy, but transmission costs to
    deliver a resource can be modeled with this
    lumpiness excluded or explicitly accounted for in
    the model.
  • Options
  • Not lumpy transmission costs are assumed to be
    based on pro-rata share of a transmission line
    (i.e. /MW-mile).
  • Unit costs and losses can vary depending on
    user-defined line voltages (e.g. 500 kV line
    costs 1,500/ MW-mi and 345 kV line costs
    2,000/MW-mi)
  • User can define an assumption such that the
    amount of transfer capacity is less than the
    nameplate capacity of the resource (e.g. 1 MW of
    wind requires 0.7 MW of transfer capacity)
  • Lumpy transmission costs are explicitly based on
    a discrete line being built for any new resource
  • Sizes of lines to include in model (voltage and
    number of circuits)?
  • How to accommodate resources that are smaller
    than transfer capacity of new line?
  • How to accommodate multiple resources on the same
    line (explicitly in the model)?
  • How to account for improved transmission
    utilization of complementary resources?
  • Initial Recommendation
  • Requires discussion, TBD.

4
Lumpy Transmission Underutilized Lines
  • How to accommodate resources that are smaller
    than transfer capacity of new line?
  • Options
  • Full cost of transmission line is allocated to
    resource. Transmission utilization is very small
    if resource is small (e.g. FEAST and E3 models)
  • Starting point assumption for transmission cost
    is allocated on pro-rata basis (i.e. not lumpy),
    but resources smaller than transmission capacity
    of 500kV are flagged. User can either adjust
    transmission utilization to show underutilized
    line or leave starting point value assuming some
    other resource will be available to use the line
  • Initial Recommendation
  • Starting point assumption is cost allocated
    pro-rata, but flagged for small resources.

5
Transmission Sizes of Lines
  • How many different transmission voltage options
    should be provided? What should be the starting
    point assumption?
  • Need to determine transmission costs and losses
    for each option
  • If transmission is modeled as lumpy, also need to
    determine transfer capacity of each voltage level
  • Options
  • Voltage level
  • 345 kV AC
  • 500 kV ACDC
  • 765kV AC
  • Circuits
  • Single
  • Double
  • Initial Recommendation
  • 500 kV single circuit AC as a starting point
    assumption. The user can select any of the above
    mentioned options.

6
Transmission Multiple Resources
  • Should the model have the capacity to model
    multiple resources on a single lines? Should the
    model be able to calculate the improvement in
    transmission utilization due to combining
    complementary resources?
  • Options
  • Benefits of combining resources are estimated
  • Within the model (See next slide how would this
    be done?)
  • External to the model
  • Not considered
  • Initial Recommendation
  • If transmission is modeled as lumpy, the model
    should allow the user to select a combination of
    resources to fill up the transmission line
  • Additional value of complimentary resources, if
    considered, should be estimated by external
    analysis

7
Transmission Utilization Improvement for Multiple
Resources
  • Transmission utilization (TU)
  • If the transmission capacity is equivalent to the
    name-plate capacity of resources, then the TU is
    equivalent to the capacity factor of resources on
    the line. The transmission utilization can be
    improved, however, by allowing for a small amount
    of curtailment or combining complementary
    resources on the same line.
  • How and where should users estimate the
    improvement in TU due to combining complimentary
    resources and curtailment?
  • Options
  • Within the model by using detailed hourly data
  • The model can account for the benefits through
    user-defined assumptions, but the analysis of
    appropriate assumptions is done external to the
    model
  • TU improvement due to complementary resources is
    not considered Transmission Capacity Nameplate
    capacity of resources
  • Initial Recommendation
  • User defined curtailment treated similar to
    transmission losses
  • If included, the analysis needs to be done
    external to the model
  • Issue needs to be explored further to evaluate
    whether the benefits are significant enough to be
    considered at a screening level analysis

8
Load Zone Selection
  • Geographic Granularity of Load Zones
  • How may load zones do we need to capture the
    heterogeneity in load zones but still keep the
    model simple?
  • Options
  • Major metropolitan areas
  • WECC load zones
  • States
  • Initial Recommendation
  • Major metropolitan areas, but restricted to about
    15 to 20 load zones

9
Other Adjustments
  • Value of seasonal exchange
  • Reliability benefits
  • Can a user reduce the transmission capital cost
    estimate of particular lines to account for any
    user-defined reliability benefits?
  • Inclusion of non-monetary benefits land use,
    emissions, water use

10
Additional Discussion Slides
11
Discussion Slide Transmission Lumpiness
  • Costs (with lumpy transmission) from E3 GHG Model
    for Alberta Wind Resources
  • Comparison to similar costs but with simple
    1,000 MW/mile (with 15 CRF) to model non-lumpy
    transmission
  • Accounting for lumpiness only makes big
    difference in the model for small resource
    quantities
Write a Comment
User Comments (0)
About PowerShow.com