System Testing by Flight Operators the Rosetta Experience - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

System Testing by Flight Operators the Rosetta Experience

Description:

System Testing by Flight Operators the Rosetta Experience ... Data Management Subsystem: fully representative with exception of PROMs replaced by EEPROM ... – PowerPoint PPT presentation

Number of Views:189
Avg rating:3.0/5.0
Slides: 18
Provided by: elsamon
Category:

less

Transcript and Presenter's Notes

Title: System Testing by Flight Operators the Rosetta Experience


1
System Testing by Flight Operators the Rosetta
Experience
European Space Operations Center
  • E. Montagnon, P. Ferri, L. ORourke, A.
    Accomazzo, I. Tanco,
  • J. Morales, M. Sweeney
  • Spaceops 2004, Montréal, Canada, 17-21 May 2004

ESOC (TOS-OPR)
May 18, 2004
2
The Rosetta Mission
  • Cornerstone mission of ESA scientific program
  • Objective orbit and land on a comet nucleus
  • Originally due for launch in January 2003 to
    comet Wirtanen
  • Launch delayed by one year due to Ariane 5
    accident mid-December 2002
  • Mission redesigned to a new comet target
    Churyumov-Gerasimenko launch in February 2004

3
The Rosetta Mission Profile
  • Launch in February 2004 with Ariane 5
  • Planetary Swing-bys to Earth (3) and Mars
  • Rendezvous with comet Churyumov-Gerasimenko in
    2014
  • Delivery of a Lander to the comet surface in
    November 2014
  • Main scientific mission at the comet until end of
    2015

4
(No Transcript)
5
Rosetta AIV Approach
  • Initial Structural Model later refurbished as
    Engineering Model (EQM)
  • EQM Test campaign objective validate the
    electrical interfaces / software before final
    test campaign on Proto-flight Model (PFM)
  • Due to delays in hardware and software delivery,
    sequential EQM / PFM testing approach had to be
    abandoned and a new approach adopted in 2002
  • Hardware integration and testing performed on PFM
    with a frozen software version
  • EQM used in parallel to validate on-board
    software and investigate Non-Conformances
  • Validated on-board software installed on PFM
    shortly before launch campaign start
  • PFM Software verification by a reduced set of
    system tests
  • EQM was to be delivered to ESOC after January
    2003 launch

6
EQM Characteristics
  • Full-scale Model
  • Data Management Subsystem fully representative
    with exception of PROMs replaced by EEPROM
  • Attitude and Orbit Control Subsystem at least
    one fully representative physical unit for all
    sensors and actuators
  • Power Subsystem solar arrays not mounted
  • Thermal Subsystem no thermal hardware
  • Telecommunications Subsystem one fully
    representative transponder out of 2, Antennas not
    mounted
  • Payload electronic box with operational SW for
    most of the instruments

7
EQM Test Campaign in 2003
  • After launch postponement, EQM delivered to ESOC
    in March 2003
  • New on-board software (OBSW) was under
    development for uplink in flight in June 2003
  • OBSW delivered in May 2003
  • OBSW system testing and validation performed
    under Industry and ESOC joined responsibility
    using EQM
  • Test schedule driven by deadline for burning new
    OBSW in PROM mid-August 2003

8
Test Campaign Activities
  • New On-board Software test campaign included
    following activities
  • Non-conformances (NCR) re-testing and close-out
  • Validation of new SW functions
  • Mission sequence tests with new SW
  • Activities split between Industry and ESOC based
    on following criteria
  • NCR close-out remains under Industry
    responsibility
  • Testing of new functions by ESOC
  • Mission sequence tests split between Industry and
    ESOC based on availability or not of test
    sequences in Industrys checkout system

9
ESOC Test Campaign Contents
  • Major SW functions validation
  • File Transfer (prior to initial launch)
  • Mission Timeline (prior to initial launch)
  • Back-up Mission Timeline
  • Operational Context Saving
  • Mission Sequence Tests
  • Launch and Early Orbit Phase (Nominal and
    Contingency case)
  • Asteroid Flyby
  • Near Sun Hibernation Entry / Exit
  • Deep Space Hibernation Entry / Exit
  • Back-up Modes Tests (Safe and Survival Mode)
  • Long Duration Test Commissioning simulation over
    5 continuous days with Payload operations in
    real-time and off-line

10
Test Characteristics
  • Use of flight timeline and procedures
  • Use of operational Flight Dynamics products
  • Simulation of ground station passes
  • Use of on-board Mission Timeline
  • Use of mission control operational tools
  • Simulation of signal travel time
  • Payload Operations

11
Spacecraft Test Configuration
  • Test equipment (SCOE) used only for power-on and
    dynamics simulation start
  • Remaining configuration and operations carried
    out from the Rosetta Control Room using the
    flight Mission Control System
  • Avionics Configuration as for flight
  • Mass memory set-up with all files required for
    flight
  • Telemetry storage enabled, Flight Telemetry
    Modes, Mission Timeline started
  • AOCMS in close loop with Flight Dynamics
    simulation as per simulated mission phase
  • All SW tables and defaults configured as per
    simulated mission phase

12
EQM Operations Set-up
To/From PFM
Power SCOE
AOCS SCOE
TM/TC Front End
NDIU
NCTRS
Mission Control System
Checkout System
NDIU Network Data Interface Unit ground
station simulator NCTRS TM/TC Router RSDB
Rosetta System Database
13
Tools Commonality
  • Network Data Interface Unit presents the same
    interface as the ESA Ground Station, thus
    allowing usage of flight equipment for ground
    testing.
  • Joined testing by Industry and ESOC possible
    thanks to common database used throughout the
    Rosetta Project for Software Generation, AIV and
    Operations
  • Different control systems used for AIV and
    Operations
  • Major drawback systems had conflicting
    requirements on database structure

14
Test Results
  • About 6 weeks of OBSW testing by Flight Operators
  • 30 non-conformances raised, from which 22 on
    spacecraft subsystems
  • All on-board software non-conformances fixed in
    time for PROM burning
  • Consolidation of the flight timelines and
    procedures
  • Problems detected on the Mission Control System
  • Best training ever for the Flight Control Team

15
EQM Activities at ESOC
  • After completion of OBSW test campaign, EQM used
    to investigate Non-Conformances and validate SW
    patches before uplink to the PFM
  • Long Duration Test repeated in December 2003 to
    validate problem fixes on the Mission Control
    System
  • EQM used in December 2003-January 2004 for
    payload commissioning simulations as part of the
    Rosetta Simulations Campaign
  • New OBSW version under development for Uplink in
    flight in June 2004 system testing and
    validation to be carried out by ESOC under
    overall responsibility from Industry

16
Recommendations
  • A hardware representative test bench to be
    provided to the flight operators, especially for
    long-duration missions
  • Main advantage w.r.t. traditional SW-based
    simulator in area of Avionics interface to other
    units and Payloads
  • Such test bench not to be used instead of but
    rather in parallel to the traditional SW-based
    simulator
  • Contingency cases can not be as easily trained
    on HW test bench.
  • Spacecraft AIV programs to include a slot for
    system testing by operators in addition to the
    traditional test slot dedicated to database
    validation
  • It is less effort for operators than for
    industry to design and carry out realistic test
    scenarios thanks to the availability of flight
    tools, documentation and expertise.

17
Conclusion
  • Smooth integration of EQM in Rosetta ground
    segment thanks to tools commonality between AIV
    and Operations
  • System test activities prepared and performed
    very efficiently by Rosetta operators thanks to
    the use of flight equipment and procedures
  • Unique experience gained by operators thanks to
  • EQM-PFM similarities
  • Use of real hardware on EQM
  • Development of realistic test cases based on
    Flight Timelines and Procedures
  • Rosetta EQM still heavily used by ESOC and
    Industry to analyze non-conformances and validate
    procedures / software
  • Experience of Rosetta EQM integrated AIV /
    Operations system testing used to define approach
    for future long-duration missions
Write a Comment
User Comments (0)
About PowerShow.com