1
MICE Tracker Electronics Update
  • Progress towards a tracker test at KEK

2
Status VLPC System
  • The VLPC system is complete and operating to spec
  • Can easily control to the 9K spec.
  • With heaters off T5.3K
  • Uses a Sumitomo SRDK-415D Cryo-cooler.
  • This is the unit we plan to use throughout MICE

3
Status Cryo System
  • Full Commissioning done Performance To Spec!!!

4
Cryo Gas System
5
Status Cryo System
  • However, we did have problems with the thermal
    links in the cryostat as you know.
  • Thermal contact was unreliable
  • Gaps lead to vacuum space and, of course,
    provided VERY GOOD insulation
  • This was corrected with the addition of In wire
    compressed between the Invar box and the clamps

6
Status Cryo System
  • We have updated the design (Russ Rucinski and
    Michael Sarychev
  • Provides positive clamping!

7
Status Cryo System
8
Status Cryo System
  • So our plan is to do a full interation of the
    cryostat design and be ready for production of
    the second system late Fall
  • Thermal clamp redesign
  • Address top-plate flatness
  • Top plate was not quite as flat as we would like.
    VLPC cassette seal leaked slightly and
    non-standard gaskets had to be used. Sealed
    well, but not overly elegant
  • Simplify G-10 backing plates
  • Increase can diameter by 2 cm

9
StatusElectronics
  • The system will use 4 AFE II boards from D0.
    These are now working
  • 512 ch
  • ADC
  • Discrim.
  • TDC in next
  • version

10
Status Electronics
  • 6 AFE II boards have now been fully tested and
    are available to MICE
  • All Channels tested
  • Temperature and bias control operation
  • LVDS readout functional
  • Still need to run the boards through the
    temperature and bias control calibration test
    stands

11
Things still to do
  • Test readout of 4 boards through VSLB to VME
  • Calibrate the two VLPC cassettes with LED pulser
  • Noise
  • Gain
  • Dead channel count
  • Implement replacement board for sequencer control
    (readout controller)
  • This will allow for much more efficient
    asynchronous triggering
  • Test trigger
  • Cosmic ray test with tracker at Fermilab
  • THE TRACKER HAS ARRIVED AT FERMILAB!

12
Timescale
  • Next two weeks
  • Get 4 board readout working
  • Get sequencer controller replacement working
  • July 18-22
  • Calibrate VLPC Cassettes
  • July 25-29
  • Cosmic Ray Test
  • August 1
  • Pack and Ship to KEK
  • August 8-12
  • Preliminary setup and shakeout at KEK
  • At least operate VLPC cryo
  • ???