Lecture for November 22, 2006

1 / 62
About This Presentation
Title:

Lecture for November 22, 2006

Description:

PGI, Module 9, Pavement Evaluation. PGI, Module 10, ... On November 20, the three topics were presented that relate to pavement ... The extra credit problem is: ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 63
Provided by: ceWash

less

Transcript and Presenter's Notes

Title: Lecture for November 22, 2006


1
Lecture for November 22, 2006
  • Pavement RehabilitationPart 2

2
Pavement Rehabilitation
  • PGI, Module 9, Pavement Evaluation
  • PGI, Module 10, Maintenance and Rehabilitation
  • PG, Volume 2, Section 7
  • PG, Volume 3

3
November 22, 2006
  • On November 20, the three topics were presented
    that relate to pavement rehabilitation (pavement
    evaluation, rehabilitation, maintenance, repair)
  • C-130 pavement issue
  • Whitetopping HMA pavement
  • Rapid runway repair in Iraq

4
November 22, 2006
  • Today, November 22, the following topics will be
    covered
  • Life cycle cost analyses (refer to Nov 20 notes)
  • Begin discussion on HMA overlay design

5
User ManualAvailable Online
6
RealCost Overview
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
Minimum Inputs/Requests for RealCost 2.2
  • Project Details
  • Analysis Options
  • Alternative 1
  • Alternative 2
  • Results

11
LCCA
  • Life cycle cost analysis for Stevens Waya few
    items to consider
  • Construction Costs Roadway Excavation New
    Pavement
  • New Pavement
  • Flexible HMA CSBC
  • Rigid PCC Pavement Base (either HMA or CSBC)

12
LCCA
  • The extra credit problem is
  • Use RealCost 2.2 to compare the agency costs of
    the flexible and rigid options for Stevens Way.
    Use your own designs.
  • To use the RealCost software
  • Download the software from the link provided.
  • Compare only the agency costsnot user costs.
  • The Agency Construction Cost is the item
    calculated in Total Project Cost in the
    preceding image.
  • Select a reasonable discount rate and analysis
    period. Justify your selections.

13
LCCA
  • Miscellaneous material costs
  • Roadway Excavation 15/yd3
  • Crushed Surfacing 20/ton
  • HMA 120/ton
  • PCC Pavement 250/yd3
  • Steel reinforcing bar 1.25/lb
  • Epoxy coated steel dowel bars 5.00/each

14
LCCA
  • Other costs (these percentages vary)
  • Traffic control Add 25 to the Construction
    Costs (varies widely)
  • Mobilization Add 5
  • Taxes Add 8
  • Preliminary Engineering Add 10
  • Project Engineering Office and Contingencies Add
    15

15
LCCA
  • Total Project Cost
  • (Construction Costs)(1Traffic Control)(1Mobiliza
    tion)(1Taxes)
  • (1Engineering)(1Project Engineering Office and
    Contingencies)
  • Agency Construction Cost for RealCost 2.2

16
RealCost 2.2Project Level Inputs
17
(No Transcript)
18
Analysis Options
19
Analysis Options
20
RealCost 2.2Alternative-Level Inputs
21
RealCost 2.2Alternative-Level Inputs
  • Alternative 1 Make this one the flexible option
  • Initial Construction
  • Input Agency Construction Cost and Activity
    Service Life. If wearing course must be replaced
    after 15 years of service, then input 15 years
    into the ASL. This requires Rehabilitation at the
    15 year point.
  • Rehabilitation 1, 2, etc
  • Generally these will be HMA overlaysmill and
    replace about 2 inches.
  • Alternative 2 Make this one the rigid option
  • Initial Construction
  • Rehabilitation 1, 2, etc
  • Will your PCC design require rehabilitation
    during its design life?

22
Alternative 1Initial Construction
23
Alternative 1Rehabilitation 1
24
RealCost 2.2Simulation and Outputs
  • Select Deterministic Results
  • Go to Worksheet and print this. This must be
    turned in with your solution.

25
Deterministic Results
26
Go to Worksheet
27
RealCost 2.2Project Level Inputs
  • Assignment submittals
  • Summarize your two designs for Stevens Way. Just
    a simple statement of layer thicknesses and types
    will do.
  • Show all calculations used to determine the
    Agency Construction Costs for both the flexible
    and rigid options.
  • Reference all major assumptions, to include
  • Analysis Period
  • Discount Rate
  • Activity Service Lives
  • Attach Worksheet from Deterministic Results
    from RealCost.
  • Finally, state which option you would
    choseflexible or rigidit should be obvious.

28
End of LCCA Discussion
29
Pavement Evaluation
  • Pavement evaluation processes allow for
  • Establish maintenance priorities.  Condition data
    such as roughness, distress, and deflection are
    used to establish the projects most in need of
    maintenance and rehabilitation.  Once identified,
    the projects in the poorest condition (low
    rating) will be more closely evaluated to
    determine repair strategies.
  • Determine maintenance and rehabilitation
    strategies.  Data from visual distress surveys
    are used to develop an action plan on a
    year-to-year basis i.e., which strategy
    (patching, surface treatments, overlays,
    recycling, etc.) is most appropriate for a given
    pavement condition.
  • Predict pavement performance.  Data, such as
    ride, skid resistance, distress, or a combined
    rating, are projected into the future to assist
    in preparing long-range budgets or to estimate
    the condition of the pavements in a network given
    a fixed budget.

30
Pavement Evaluation
  • Pavement performance is largely defined by
    evaluation in the following categories
  • Roughness (or smoothness or pavement profile)
  • Surface distress
  • Friction or skid resistance
  • Structural evaluation

31
Example of Pavement Evaluation Data in the WSDOT
PMS
32
Roughness
  • Ranges of International Roughness Index (IRI)
  • All types of roads
  • Interstate highways
  • Comparison of states and the US
  • Vehicle operating costs versus IRI

33
Roughness
34
FHWA IRI Thresholds for Interstate Highways
Description PSR Rating IRI NHS Ride Quality
Very Good ?4.0 ?1.0 m/km (?60 in/mi) Acceptable (0-2.7 m/km)
Good 3.5-3.9 1.0-1.5 m/km (60-94 in/mi) Acceptable (0-2.7 m/km)
Fair 3.1-3.4 1.5-1.9 m/km (95-119 in/mi) Acceptable (0-2.7 m/km)
Mediocre 2.6-3.0 1.9-2.7 m/km (120-170 in/mi) Acceptable (0-2.7 m/km)
Poor 2.5 gt2.7 m/km (gt170 in/mi) Less than Acceptable (gt2.7 m/km)
35
IRI for Rural Interstates2001
Source FHWA, Highway Statistics, 2001
36
VOC versus IRI for HMA
2.7
37
2.7
38
Roughness
39
Surface Distress(from PGI, Module 9, Section 7)
40
Surface DistressExampleFatigue Cracking(from
PGI, Module 9, Section 7)
41
Surface Distress
42
Friction or Skid Resistance
43
Friction or Skid Resistance
44
Friction or Skid Resistance
45
Structural EvaluationPavement Deflections
  • A tolerable level of deflection is a function of
    traffic and the pavement structural section.
  • Overlaying a pavement with HMA will reduce its
    deflection. The thickness needed to reduce the
    deflection to a tolerable level can be estimated.
  • The deflections experienced by a pavement varies
    throughout the year due to temperature and
    moisture changes.

46
Primary Types of Deflection Measure Devices Used
in the US
  • Static (Benkelman Beam)
  • Impulse (Falling Weight Deflectometer)

47
Benkelman Beam
48
Falling Weight Deflectometer (FWD)
49
Structural Evaluation with Deflections
  • Maximum deflection (D0)
  • Area Parameter (A)
  • Subgrade Modulus (MR)

50
Area Parameter
51
Area Parameter
52
Subgrade Modulus (quick estimate)(from AASHTO 93
Guide)
53
Typical Values of Subgrade Moduli(from PG,
Volume 2, Section 7.3)
54
Pavement Rehabilitation
  • Introduction
  • Most of PG, Section 7.0 is about HMA overlays
    however, pavement rehabilitation is much more
    than that one rehabilitation technique. HMA
    overlays receive substantial treatment in this
    section since they are by far the most common
    type of flexible pavement rehabilitation
    technique in use in the US and most other
    countries.
  • PGI, Module 10 (Maintenance and Rehabilitation),
    Section 3 (RehabilitationFlexible) and Section 5
    (RehabilitationRigid)
  • Another rehabilitation technique commonly used by
    WSDOT is dowel bar retrofit of PCC slabs. This
    will be described later in this section.

55
WSDOT Structural Design Policy
56
Pavement Rehabilitation
  • Types of HMA overlay design procedures
  • Engineering judgment
  • Component analysis Widely used in a number of
    applications/design procedures
  • Nondestructive testing with limiting deflection
    Still used with measurement instruments such as
    the Benkelman Beam.
  • Mechanistic-empirical This is the primary HMA
    overlay design method used by WSDOT. This
    approach is gaining acceptance in other states
    and countries.

57
Pavement Rehabilitation
  • Component Analysis
  • The Asphalt Institute (AI) approach is
    illustrated in the PG, Section 7, Paragraph 1.3
    and the PGI, Module 10, Section 3.1.2. A number
    of HMA overlay design procedures use a similar
    approach. In effect, you start by determining
    the effective thickness of the existing
    pavement structure. Then, a new pavement
    structure is designed and the difference in the
    two structures (new effective) amounts to the
    overlay thickness. To use the AI approach, the
    following is required
  • Subgrade analysis
  • Traffic analysis
  • Pavement structure thickness analysis ( determine
    effective thickness of existing and all new
    design for the given subgrade and traffic).

58
Pavement Rehabilitation
  • Limiting pavement surface deflectionsAsphalt
    Institute, PGI, Module 10, Section 3.1.3.
  • Surface deflections can be taken with a variety
    of deflection devices. Typically, this is either
    the Benkelman Beam (BB) or the Falling Weight
    Deflectometer (FWD).
  • Compute the Representative Rebound Deflection
    (RRD). You must consider the time of the year
    during which the deflections are taken.
  • The overlay thickness is a function of ESALs and
    RRD (PG, illustrated by the sketch in Figure 7.3).

59
Pavement Rehabilitation
  • WSDOT Mechanistic-Empirical Approach
  • Used to design HMA overlays
  • Can be used to design all new pavements
  • Computer program is EVERPAVE
  • Failure criteria
  • Ruttingsame as you used in Assignment No. 4
  • Fatigue cracking
  • Nfield (Nlab)(SF)
  • The SF is approximately equal to 10 for HMA
    thicknesses of less than 100 mm, 7 if the HMA is
    100-175 mm thick, and 4 if greater than 175 mm.
    Part of the reason for these shift factors is due
    to environmental deterioration as well as traffic
    effects. Additionally, for HMA layers thicker
    than 175 mm, the fatigue cracks often start at
    the top of the pavementnot at the bottom of the
    layer as traditionally viewed.
  • EVERPAVE Inputsreview information in PG,
    Paragraph 1.6.4
  • EVERPAVE is the primary design procedure used by
    WSDOT

60
Pavement Rehabilitation
  • AASHTO Overlay Design Procedure (1993)
  • Introduction WSDOT Pavement Guide, PG, Paragraph
    1.8.1 Note types of overlays that are possible.
    WSDOT primarily uses the AASHTO procedure as a
    design check for HMA overlays placed on flexible
    pavement.
  • Overlay design considerations
  • Pre-overlay repair including level-up or milling
  • Reflection crack control
  • Traffic (ESALs mostly)
  • Subdrainage
  • Ruttingunderstand cause(s)

61
Pavement Rehabilitation
  • AASHTO Overlay Design Procedure (1993)
  • HMA Overlay of HMA Pavement
  • SNol (aol)(Dol) SNf - SNeff
  • In effect, this is similar to the component
    analysis approach discussed earlier. Further, MR
    and SNeff can be determined from nondestructive
    tests. WSDOT uses the FWD for this purpose.

62
Pavement Rehabilitation
  • Availability of Software
  • WSDOT has placed all software (EVERSTRESS,
    EVERCALC, and EVERPAVE) on the current version of
    the WSDOT Pavement Guide CD. You must obtain the
    DARWin software from AASHTO to run that overlay
    design procedure (or develop your own
    spreadsheet).
Write a Comment
User Comments (0)