Title: ETHIOPIAN ELECTRIC POWER CORPORATION
1ETHIOPIAN ELECTRIC POWER CORPORATION
- REHABILTATION WORK PROGRESS AND EEPCOS FUTURE
PLAN IN GEOTHERMAL DEVELOPMENT
Geothermal resource council 2007 Annual meeting
Reno, Nevada , USA September 30- OCT 03, 2007
2General Description of the Aluto Langano steam
fields
- The Aluto Langano Geothermal field is located in
the Main Ethiopian rift valley at Lakes District
between Lakes Langano and Ziway (Fig1) - The proven productive area at Aluto is about 8km2
- Eight wells drilled in the early 1980s, out of
which only four wells are successfully for
production - The two Wells drilled along the Wonji fault are
high pressure wells (LA-3 and LA-6) , where as
Wells drilled on the outflow zone are medium
pressure wells (LA-4 LA-8)
3MAIN ETHIOPIAN RIFT WITH GEOTHERMAL PROSPECTS
4Aluto Langano Steam Field
5Power plant design and operation
- A combined steam and binary cycle unit rated at
7.28 MW(net) was constructed and began operation
in May1998. - However, due to numerous issues with the power
plant , gathering system, and production wells
the plant failed operation in 2002
6Tendering and Contracting
- In 2004 a competitive tender was offered to
evaluate the entire project by the Ethiopian
Electric Power Company. - In June 2005 a contract awarded to the Geothermal
Development Associates to evaluate the condition
of the geothermal resource and to refurbish and
restart the power plant
7Tests and measurements of the Steam field
- Refurbishment of the wellhead and side valves
that are stacked and was none functional - By Running caliper logging proved that the two
high pressure production wells are in good
condition - One of the medium pressure well (LA-4) is largely
blocked by carbonate, and the second well (LA-8)
is also blocked but still has a good flow rate. - Tests with digital temperature and pressure logs
proved the older test results of the mechanical
logs
8The OEC unit Heat exchanger failure and Analysis
- The heat exchanger is a 316L stainless steel tube
- The heat exchanger is a counter-flow design with
steam on the tube side and liquid on the
shell-side - Tubes failed on the steam discharge end
- Pitting occurs on the internal diameter of the
tubing - X-ray analysis shows that silica sulphr
depositions with minor traces of K,Na, Cl Al - Brine carryover is suspected to be the cause for
the failure
9Chemistry and scale deposition Analysis
- The PH of the steam field is alkaline at about
8.5-9.0. - However, weak acids form when CO2 and H2s
- is condensed from the coexisting steam
- Condensation would be most sever at the discharge
end of the condenser tubes, where cooling greater
and thus pitting is most sever.
10Operating the GCCU unit
- The GCCU Rotor refurbished and de-rated to lower
the design steam inlet pressure. This helped to
overcome the pressure drop of the production
wells. - On June 07,207 the first startup of the GCCU unit
after a six year silent time. - Currently the unit has operating with full
capacity
11TENDAHO GEOTHERMAL FIELD
- Extensive aerial and surface investigations
carried out 1970 80 - Three deep (up to 2100m) and three shallow (up to
500m) wells drilled 1993-98 - Four wells productive with reservoir
temperatures up to 270ºC. - Through Energy market group Geothermal
Development Associates has studied resources
confirmation - Follow up geochemical and reservoir engineering
studies being conducted by GSE
12 EEPCOS future plan in geothermal power
development
- Development of 30 MW expansion at Aluto Langano
- Development of 3-5 MW pilot plant at Tendaho
steam field for EEPCO has submitted letter of
commitment on the final project proposal to ARGeo - Resource assessment and power plant development
at other prospects (Corbetti, Tulu- Moye, Abaya,
Gedemsa, Dofan, fantale, etc.)
13GOVERNMENT RATIONALE FOR GEOTHERMAL EXPLORATION
- Build infrastructure, improved access to
electricity for social services - Accelerate development of indigenous energy
- Encourage private investment in IPP mode and
suppliers credit in electricity generation,
distribution - Increase electricity generation capacity of
800MW of which 90 is hydro, 10 from other
sources - Balance energy mix, decrease dependence on
drought-prone hydro - Exploit reliable base load character of
geothermal energy - Access resources from the UNEP/GEF ARGeo Regional
Geothermal Program
14ELECTRICITY LEGISLATION, LICENSING
- Electricity Proclamation N0.86/1997 seeks to
promote domestic, foreign private investment in
power generation from all sources - Independent power producers (IPPs) may generate,
sell electric power to EEPCo or establish
independent distribution systems in areas not
served by grid - Generation licenses available for life of project
up to 40 years - Transmission, distribution, power sale licenses
available up to 50 years - Power import, export licenses up to 10 years
- Projects require authorization of Ethiopia
Environmental Protection Authority (EPA) before
implementation
15Opportunities for Private Sector Participation
- Tendaho Plant Construction
- Aluto 30 MW Expansion
- Training of EEPCO and GSE Personnel
16EEPCO Geothermal Contact Information
- Merga Tassew, Geothermal Program Coordinator
- DEGAULLE SQUARE, P.O. BOX 1233
- ADDIS ABABA, ETHIOPIA
- Fax 251-1-52-57-10
- Tel. 251-1-51-25-52
- pso.dept_at_telecom.net.et
- mergatassew_at_yahoo.com
-
17THANK YOU FOR ATTENTION
- AND WISH YOU HAPPY ETHIOPIAN MILLINIUM!!