ETHIOPIAN ELECTRIC POWER CORPORATION - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

ETHIOPIAN ELECTRIC POWER CORPORATION

Description:

... logging proved that the two high pressure production wells are in good condition ... and the second well (LA-8) is also blocked but still has a good flow rate. ... – PowerPoint PPT presentation

Number of Views:524
Avg rating:3.0/5.0
Slides: 18
Provided by: geoth
Category:

less

Transcript and Presenter's Notes

Title: ETHIOPIAN ELECTRIC POWER CORPORATION


1
ETHIOPIAN ELECTRIC POWER CORPORATION
  • REHABILTATION WORK PROGRESS AND EEPCOS FUTURE
    PLAN IN GEOTHERMAL DEVELOPMENT

Geothermal resource council 2007 Annual meeting
Reno, Nevada , USA September 30- OCT 03, 2007
2
General Description of the Aluto Langano steam
fields
  • The Aluto Langano Geothermal field is located in
    the Main Ethiopian rift valley at Lakes District
    between Lakes Langano and Ziway (Fig1)
  • The proven productive area at Aluto is about 8km2
  • Eight wells drilled in the early 1980s, out of
    which only four wells are successfully for
    production
  • The two Wells drilled along the Wonji fault are
    high pressure wells (LA-3 and LA-6) , where as
    Wells drilled on the outflow zone are medium
    pressure wells (LA-4 LA-8)

3
MAIN ETHIOPIAN RIFT WITH GEOTHERMAL PROSPECTS
4
Aluto Langano Steam Field
5
Power plant design and operation
  • A combined steam and binary cycle unit rated at
    7.28 MW(net) was constructed and began operation
    in May1998.
  • However, due to numerous issues with the power
    plant , gathering system, and production wells
    the plant failed operation in 2002

6
Tendering and Contracting
  • In 2004 a competitive tender was offered to
    evaluate the entire project by the Ethiopian
    Electric Power Company.
  • In June 2005 a contract awarded to the Geothermal
    Development Associates to evaluate the condition
    of the geothermal resource and to refurbish and
    restart the power plant

7
Tests and measurements of the Steam field
  • Refurbishment of the wellhead and side valves
    that are stacked and was none functional
  • By Running caliper logging proved that the two
    high pressure production wells are in good
    condition
  • One of the medium pressure well (LA-4) is largely
    blocked by carbonate, and the second well (LA-8)
    is also blocked but still has a good flow rate.
  • Tests with digital temperature and pressure logs
    proved the older test results of the mechanical
    logs

8
The OEC unit Heat exchanger failure and Analysis
  • The heat exchanger is a 316L stainless steel tube
  • The heat exchanger is a counter-flow design with
    steam on the tube side and liquid on the
    shell-side
  • Tubes failed on the steam discharge end
  • Pitting occurs on the internal diameter of the
    tubing
  • X-ray analysis shows that silica sulphr
    depositions with minor traces of K,Na, Cl Al
  • Brine carryover is suspected to be the cause for
    the failure

9
Chemistry and scale deposition Analysis
  • The PH of the steam field is alkaline at about
    8.5-9.0.
  • However, weak acids form when CO2 and H2s
  • is condensed from the coexisting steam
  • Condensation would be most sever at the discharge
    end of the condenser tubes, where cooling greater
    and thus pitting is most sever.

10
Operating the GCCU unit
  • The GCCU Rotor refurbished and de-rated to lower
    the design steam inlet pressure. This helped to
    overcome the pressure drop of the production
    wells.
  • On June 07,207 the first startup of the GCCU unit
    after a six year silent time.
  • Currently the unit has operating with full
    capacity

11
TENDAHO GEOTHERMAL FIELD
  • Extensive aerial and surface investigations
    carried out 1970 80
  • Three deep (up to 2100m) and three shallow (up to
    500m) wells drilled 1993-98
  • Four wells productive with reservoir
    temperatures up to 270ºC.
  • Through Energy market group Geothermal
    Development Associates has studied resources
    confirmation
  • Follow up geochemical and reservoir engineering
    studies being conducted by GSE

12
EEPCOS future plan in geothermal power
development
  • Development of 30 MW expansion at Aluto Langano
  • Development of 3-5 MW pilot plant at Tendaho
    steam field for EEPCO has submitted letter of
    commitment on the final project proposal to ARGeo
  • Resource assessment and power plant development
    at other prospects (Corbetti, Tulu- Moye, Abaya,
    Gedemsa, Dofan, fantale, etc.)

13
GOVERNMENT RATIONALE FOR GEOTHERMAL EXPLORATION
  • Build infrastructure, improved access to
    electricity for social services
  • Accelerate development of indigenous energy
  • Encourage private investment in IPP mode and
    suppliers credit in electricity generation,
    distribution
  • Increase electricity generation capacity of
    800MW of which 90 is hydro, 10 from other
    sources
  • Balance energy mix, decrease dependence on
    drought-prone hydro
  • Exploit reliable base load character of
    geothermal energy
  • Access resources from the UNEP/GEF ARGeo Regional
    Geothermal Program

14
ELECTRICITY LEGISLATION, LICENSING
  • Electricity Proclamation N0.86/1997 seeks to
    promote domestic, foreign private investment in
    power generation from all sources
  • Independent power producers (IPPs) may generate,
    sell electric power to EEPCo or establish
    independent distribution systems in areas not
    served by grid
  • Generation licenses available for life of project
    up to 40 years
  • Transmission, distribution, power sale licenses
    available up to 50 years
  • Power import, export licenses up to 10 years
  • Projects require authorization of Ethiopia
    Environmental Protection Authority (EPA) before
    implementation

15
Opportunities for Private Sector Participation
  • Tendaho Plant Construction
  • Aluto 30 MW Expansion
  • Training of EEPCO and GSE Personnel

16
EEPCO Geothermal Contact Information
  • Merga Tassew, Geothermal Program Coordinator
  • DEGAULLE SQUARE, P.O. BOX 1233
  • ADDIS ABABA, ETHIOPIA
  • Fax 251-1-52-57-10
  • Tel. 251-1-51-25-52
  • pso.dept_at_telecom.net.et
  • mergatassew_at_yahoo.com

17
THANK YOU FOR ATTENTION
  • AND WISH YOU HAPPY ETHIOPIAN MILLINIUM!!
Write a Comment
User Comments (0)
About PowerShow.com