Title: College of Public HealthUAMS


1
College of Public Health-UAMS
  • High Performance Design Case Study
  • 2006 Legislative Task Force

2
(No Transcript)
3
COPH-UAMS
  • Integrated Design Team
  • Sustainable Building Program
  • LEED 2.0 Criteria
  • Energy Efficiency
  • Local Materials
  • Healthy Environment

4
Promote Healthy Activity
  • Communicating Stair
  • Fitness Center
  • Outdoor Space-Every Level
  • Health Food

5
Lighting / Natural Light
6
COPH-UAMS
  • Local Materials
  • Brick
  • Concrete
  • Recycled Steel
  • Building Reuse -Bottom 2 Floors
  • High Efficiency Glazing
  • Energy Conserving Features
  • Energy Star Roof
  • No Irrigation-Indigenous Plants
  • No Exterior Light Pollution-Full Cutoffs

7
Energy Conserving Features
  • Energy Procurement
  • Exhaust Air Energy Recovery
  • Building Pressure Control
  • Variable Air Volume
  • Demand Controlled Ventilation
  • Occupancy Sensors
  • Variable Volume Heating Water
  • Variable Volume Chilled Water
  • Central Energy Plant Capacity Charge Structure
  • Night Set-Back/Set-Up
  • Variable Volume Domestic Hot Water Recirculation
  • Efficient Lighting/Daylighting

8
Energy Procurement
  • Rate Analysis
  • Natural Gas Combined Billing
  • Power Factor Correction
  • Electrical Master Metering
  • Natural Gas Transportation
  • Natural Gas Purchasing Group
  • Interruptible Natural Gas Supply

9
Power Factor Correction
  • Ratio of Actual Demand to Peak Demand
  • Low Power Factor Caused by Inductive Motors
  • Utility Offers Rate Incentives to Improve Power
    Factor
  • Power Factor Increased to 99 by Installing
    Capacitors at Electrical Services

10
Electricity Master Metering
  • Single Master Meter For Entire Campus
  • Reduces Electricity Unit Costs
  • Eliminates Multiple Customer Charges
  • Time of Use Rate Structure
  • Reduces Peak Demands Due to Diversity

11
Natural Gas Transportation
  • Unbundled Arrangement
  • CEA Provides Distribution and Balancing Only
  • Separate Contracts for Commodity and Pipeline
    Transportation
  • Physical and Financial Hedging
  • Existing Combined Billed Arrangement

12
Natural Gas Purchasing Group
  • Group Includes Industrial, Higher Education, and
    Hospital Facilities
  • Competitively Bid Commodity Contract
  • Competively Bid Pipeline Contract
  • 3rd Party Manager

13
Interruptible Gas Supply
  • Standby Fuel Oil System
  • Contract Demand less than Maximum Daily Quantity
  • Reduces CEA Distribution Charges and Pipeline
    Charges

14
Total Energy Wheel (TEW)
Assumes 75 Latent and Sensible Effectiveness
15
Chilled Water System
  • High Efficiency Water Chillers
  • Variable Speed CHW Pumps
  • Chilled Water Supply Temperature Reset
  • Optimal Equipment Dispatch
  • Hydronic Free Cooling
  • Low Flow/High DT CHW

16
Tower Water System
  • High Efficiency Cooling Towers
  • Variable Speed Cooling Tower Fans
  • Condenser Water Supply Temperature Reset
  • Variable Water Volume

17
Lighting Modifications
  • Electronic Ballasts
  • Compact Fluorescent Lamps
  • Daylighting
  • Photocell Controls
  • T8 Fluorescent Lamps
  • Occupancy Sensors