Survivor Living Through an Oracle 11i Upgrade
  • HR, Payroll, General Ledger, Time Management

Presented by Barbara Freeman Randy
Rudkin 602-684-8154 561-371-3134 barbara.freeman
_at_aris.com randy.rudkin_at_aris.com Aris Corporation
2
Todays Topics
  • Project Background
  • Project Management
  • Technical Upgrade Lessons Learned
  • Customization Upgrade - Phase Plan
  • Upgrade from Functional Perspective
  • User Reeducation
  • Survival Tactics

3
Project Background
  • Domestic Coal-Mining Company
  • Goals
  • Decision to technically upgrade only new
    functionality at later point
  • Reduce of Customizations
  • Maintain/Extend Oracle Support
  • Phases (March-June 2001)
  • Upgrade Database from 7.3.4.5.0 to 8.1.6.1
  • Upgrade HRMS, GL, TAMS from 10.7 to 11.53
  • Upgrade Customizations

4
Project Management
  • Project Steps
  • Vision Database, Conference Room Pilot Plan
  • Development, Training, Information Transfer
  • Detailed Functional Upgrade Analyses (10.7 vs.
    11i)
  • Technical Architecture and Database Changes
  • Test System/Integrated Test Plans
  • Corporate Users
  • Field Users
  • Production-Ready System
  • Production Shutdown Plan
  • Validation Plan
  • Contingency Plans

5
Project Management
  • Resources (FTEs)
  • 2.00 Project Managers (1 Overall, 1
    Customizations)
  • 2.00 Database Administrators
  • .10 System Administrator
  • 5.00 Developers
  • 1.25 HR Functional
  • 2.00 Payroll Functional
  • 1.00 GL Functional
  • 1.25 TAMS Functional

6
Project Management
  • Tools
  • Internal Request Management System
  • Outlook Project Calendar
  • Project News Flash
  • Project Plans MS Project, PowerPoint Graphics
  • Logs - Decisions Made, Issue Resolution
  • Functional, Technical, ESC Meetings
  • Communication

7
Technical Upgrade Lessons Learned
  • Upgrade vs Implementation
  • There is a difference!
  • Concept of Instances no longer applicable
  • Test system never the same as production
  • Each CRP is different
  • Look for print problems
  • Dont count on Oracle Support as your only or
    last answer

8
Customization Upgrade - Phase Plan
9
Upgrade from Functional Perspective
  • Upgrade Analysis Walkthrough
  • Function by function comparison
  • Navigation and User Interface changes
  • Action Items
  • Issues
  • Future Functionality
  • Unit and Integrated Test Plans
  • Detailed test scenarios by product and
    functionality
  • Each CRP
  • Production Validation

10
User Reeducation
  • Self Study Guides
  • Follow up Calls
  • On-site, Centralized training class (combined
    with testing)

11
To Be a Survivor
  • Key Flexfields
  • Descriptive Flexfields
  • Elements
  • Lookup Tables
  • Oracle Seeded Reports
  • Table Structure and Values
  • Assignment Sets
  • Basic Benefits

12
To Be a Survivor
  • HRMS Security
  • Custom Menus
  • Request Groups
  • Custom Reports Security Profile
  • Custom Report Performance
  • Secure Users
  • Formulas
  • ADI
  • Environment Issues

13
To Be a Survivor
  • Data Migration
  • Oracle MetaLink

14
SUMMARY
  • Multiple Migration tests
  • Comprehensive Test scripts
  • Production Cutover

15
(No Transcript)
Write a Comment
User Comments (0)