UK Electronics Status and Issues - PowerPoint PPT Presentation

About This Presentation
Title:

UK Electronics Status and Issues

Description:

Full equipment request, but only for ECAL electronics ... Compact Flash. VME64x. Interface. FPGA. Test Connector. SW. SW. Hot swap cycle. Live extract request ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 12
Provided by: paulda6
Category:

less

Transcript and Presenter's Notes

Title: UK Electronics Status and Issues


1
UK Electronics Status and Issues
  • Paul Dauncey
  • Imperial College London

2
UK approval
  • UK electronics project (finally!) approved in Dec
    2002
  • Full equipment request, but only for ECAL
    electronics
  • Full manpower request for engineering effort from
    Rutherford Laboratory (RAL)
  • New engineer (Adam Baird, RAL) has now joined the
    project
  • RAL will also do layout and some testing
  • Budgeted to use all money and effort by the end
    of Mar 2004
  • RAL people have experience of CMS tracker
  • Significant knowledge of design of Front End
    Driver (FED)
  • Readout board for CMS silicon tracker
  • Architecture close to proposed CALICE board
  • Will now use FED as a starting point for
    CALICE

3
CMS Tracker FED
5V
3.3V
Run/Halt
Config E2PROM
Id E2 Prom
1.5V
5V
3.3V
1.5V
1
0V
3.3V
Compact Flash
1
Test Connector
1
VME
LEDs
4x Prog Delay
1
Dual ADC
12x Opto Rx
1
Power Good
VME64x Interface FPGA
FPGA
Synch Processing
Boundary Scan
System ACE
Buffer Jumper Matrix
-5V
ASIC
12x trim dac
Vref
VME
FE 1
PD Array
3
6
4x Prog Delay
12V
12
Dual ADC
LEDs
Temp Sense
5V
Front End FPGA
3.3V
FPGA
Temp Sense
Clock Control Data
2.5V
1.5V
2.5V
0V
LEDs
2
1.5V
QDR SSRAM
-5.0V
spare
Over temp
LEDs
TTS
TTCrx
TTC
DAQ
Readout Synch Control
ASIC
FLT
LEDs
EMU
FSYNC
Spare
Process
Back End FPGA
LEDs
Transfer
VME
Temp Sense
43
85
22
Readout
Clock Control Data
4x Prog Delay
3.3V
1.5V
Dual ADC
8
Busy
12x Opto Rx
8
LEDs
error
FPGA
halted
Synch Processing
ASIC
12x trim dac
Vref
FE 8
PD Array
24
4x Prog Delay
48
5.0 V
96
E-Fuse Hot swap DC-DC
3.3 V
Front End FPGA
Dual ADC
FPGA
2.5V
Temp Sense
1.5V
-5.0V
extract
Hot swap cycle
SW
Live extract request
SW
4
FED layout
  • Ideally, keep everything to the right, redo
    everything to the left
  • Restricts readout board to same I/O and
    inter-FPGA paths as FED
  • No major problems seen so far

5
Implications of using FED
  • FED more complicated and hence expensive than
    previous design
  • Keep cost within budget by increasing number of
    cables per board
  • Previous design had 6 cables ( 6 VFE-PCBs) per
    board, new design has 16
  • Total number of boards for the ECAL drops from 15
    to 6
  • Cost per board should be around 6k 10k?
  • Save on much of layout and some firmware design
  • VME FPGA should be very close (if not identical)
    would like VME interrupts but not (yet)
    implemented
  • Back end (BE) FPGA can reuse major parts of FED
    firmware
  • Front end (FE) FPGA will need all new firmware
  • BE FPGA much larger than needed
  • Use spare logic for trigger handling no need for
    separate board
  • Trigger I/O and distribution via J0/J2 backplane
    unused pins
  • Requires adding termination resistors for
    incoming LVDS, i.e. changing layout of back of
    board

6
Implications of using FED (cont)
  • Space for cable connectors, line
    drivers/receivers, ADCs, etc. restricted by
    position of FE FPGA
  • Need to minimise the number of components here
  • BE has 2?1MByte memories for event buffering
  • With 16 cables, board event size 16?6?18?2
    3.5kBytes/event
  • 2MBytes stores only around 500 events in each
    beam burst
  • May need larger memories for CALICE i.e. would
    require changing layout of back of board
  • 9U front panel so can fit 16 high-density 68-pin
    SCSI connectors
  • 38 pins needed leaves 30 pins 15 differential
    lines spare
  • Connected directly to FE FPGA for use as LVDS
  • Could use as I/O lines for digital HCAL readout
  • For more details, see
  • http//www.hep.ph.ic.ac.uk/calice/electronics
    /electronics.html

7
ECAL assumed electronics schedule
2003 2004
8
Issues CALICE schedule and plans
  • ECAL prototype test schedule
  • When and where will prototype tests be done?
  • ECAL final system schedule
  • When and where is full readout electronics system
    needed?
  • What sets this date and how firm is it?
  • Will first use be beam, cosmics, calibration
    tests?
  • HCAL schedule
  • When will analogue and digital options be ready?
  • Will either or both options use UK readout?
  • Is a prototype test needed for the analogue?
  • When and where will prototype test be done for
    digital?

9
Issues VFE-PCB interface
  • Voltage levels still have some uncertainties
  • Main problem would be negatively-shifted LVDS
  • Needed for schematics before end February
  • Confirm connector choice
  • Compatibility with cable and connector needed at
    VFE-PCB
  • Needed for schematics before end February
  • Pin allocations within connector
  • In principle, needed for schematics before end
    February
  • If desperate, could wire cables to swap pins
    later before end May
  • Cable specification
  • Some cables required for VFE-PCB tests
  • Need to be manufactured before end May
  • Prototype board testing with semi-final VFE-PCB
  • Needed before redesign before end November

10
Issues beam test details
  • Laboratory requirements cable safety
    specification, etc.
  • Needed for cable manufacture before end May
  • Define number of events needed per beam spill
  • Affects size of onboard memory required
  • Also needs event size estimate per board from
    HCAL if using UK boards
  • Needed for schematics before end February
  • Cable lengths
  • Distance between VME crate and ECAL/HCAL
  • Needed for cable manufacture before end May
  • Trigger logic and distribution
  • Allocation of I/O lines with termination
    resistors
  • Needed for assembly before end May
  • Number of pins to be allocated on backplane for
    trigger fanout
  • Needed for firmware design before end May

11
Issues HCAL plans
  • Analogue is VFE-PCB interface compatible?
  • For signal levels, cables, connectors
  • Needed for schematics before end February
  • Number of boards required for manufacture
    before end February 2004
  • Digital interface specification
  • Sufficient number of spare connector pins?
  • Needed for schematics before end February
  • Digital allocations of pins
  • Have to mount termination resistors on correct
    lines
  • Needed for assembly before end April
  • Digital firmware development for spare pins
  • UK unlikely to have manpower required
  • Needed for digital HCAL tests before end
    November
Write a Comment
User Comments (0)
About PowerShow.com