Title: Offshore Transmission Regulatory Regime
1Offshore TransmissionRegulatory Regime
- DECC / Ofgem External Communications Workshop
- 8 December 2008
2IntroductionDuarte Figueira
- Director, Renewables Deployment Team
- DECC
3Welcome and Aims of the dayOffshore
Transmission overview of proposed regulatory
regime
- Provide further clarity on
- Offshore Transmission project status
- EU Third package
- Design of the regime (as set out in the November
08 joint DECC/Ofgem consultation document) - Implementation issues
- The key stages, next steps and dates in the
implementation process - Encourage discussion
- Questions
4Agenda
- Arrival / Coffee
- Welcome and aims of the day Duarte Figueira
(DECC) - Offshore Transmission overview and context view
from DECC Duarte Figueira - Overview of EU Third Package of Legislative
measures for the Gas and Electricity Markets
Sue Harrison (DECC) - Questions
- Overview of regulatory regime and latest
consultation Robert Hull (Ofgem) - Questions
- Implementation of Regime key changes Bridget
Morgan (Ofgem) John Greasley (National Grid) - Questions
- Next Steps Duarte Figueira (DECC)
- Close
5Offshore Transmission overview and context view
from DECC
- Duarte Figueira
- Director, Renewables Deployment Team
- DECC
6New Offshore Transmission Regime
- Provision of offshore grid connection to offshore
wind farms key to delivery of our targets. - Developers need a grid connection they can afford
on time. - Up to 15 billion of new offshore grid needed to
connect Rounds 1, 2 3 offshore wind.
7Offshore Wind - Background
- Major contributor to UKs 2020 renewables target
- UK already no. 1 in offshore wind 598 MW
installed - Ambitious plans for up to 33 GW of offshore wind.
8SEA Round 3 timeline
- Offshore Energy SEA launched December 07
- SEA scoping Spring 08
- Crown Estate launch of Round 3 June 08
- SEA workshops September/October 08
- Crown Estate Invitation to Negotiate issued late
Sept 08 - SEA Environmental Report published Jan 09
- Environmental Report Consultation January-April
09 - Crown Estate ITN closes 3 March 2009
- Government Decision on SEA Spring 2009
- Crown Estate finalises zones, awards complete by
end 2009 - Earliest projects construction could begin 2014
onwards
9Regulating Offshore Transmission
- First R1 projects and some R2 projects grid
connections built by developers - But scale of offshore wind planned means we
need a regulatory regime in place to support
offshore wind development ensure secure
supplies - Govt therefore took powers in Energy Act 2004 to
regulate offshore transmission.
10New Offshore Transmission Regime - benefits
- Will provide offshore grid companies OFTOs
with a secure income stream for 20 years. - Means developers will not have to fund cost of
cables upfront. - NG will co-ordinate onshore and offshore grid.
- Competition will lower cost of assets and allow
new players to bring new solutions funding. - Amended grid codes will provide secure supplies.
11Current Consultation
- Now consulting on implementation of high level
policy decisions - Refinement of policy positions
- Further update on changes to codes and licences
- OFTO of last resort result of EU Unbundling
requirements.
12Overview of EU Third Package of Legislative
Measures for the Gas and Electricity Markets
13Third package unbundling requirements - Context
- Third package is the latest step towards the
creation of a single EU energy market - Aim is to deliver choice for consumers and more
cross-border trade so as to achieve efficiency
gains, competitive prices and higher standards of
service, and to contribute to security of supply
and sustainability - Key plank is effective unbundling, ie separation
of transmission networks from generation and
supply without this, there is an inherent risk
of discrimination not only in the operation of
the network but also in the incentives for
vertically integrated companies to invest
adequately in their networks
14Third package unbundling requirements - Process
- Ministerial agreement on third package was
achieved on 10 October 2008 - Package must now be agreed with the European
Parliament. Wording of some provisions will
inevitably change, but the unbundling
requirements are unlikely to change
significantly. - Third package is expected to enter into force in
mid-2009 - Third package must be implemented in Member
States at the latest 18 months after that date,
ie around end-2010 - However, Member States have one extra year to
implement the unbundling requirements, ie by
around end-2011
15Third package unbundling requirements in text
agreed by Ministers in October 2008
- Member States can choose any of the following
three options - - Ownership unbundling, where the same
person must not exercise control over a
transmission system and over a generation or
supply business - Or, where the transmission system belongs to
a vertically integrated undertaking (VIU) on the
entry into force of the package - - Independent system operator, where the
system operator is in separate ownership from the
rest of the VIU and the VIU retains ownership of
the transmission network but performs none of the
functions of the transmission system operator or
16Third package unbundling requirements in text
agreed by Ministers in October 2008
- - Independent transmission operator, where
the system operator remains part of the VIU but
in a separate legal entity. There are very
detailed and strict requirements on both the ITO
and the parent VIU to ensure effective
independence of transmission system operation, eg
supervisory body, compliance programme, close
regulatory oversight to ensure compliance, rules
on investment, rules on transfer of staff - - By way of derogation, arrangements which
guarantee more effective independence of the
transmission system operator than the third
option may be certified as compliant by the
regulator and the Commission
17Questions
18Overview of the Regulatory Regime and latest
consultation
- Robert Hull
- Head of Offshore Transmission Policy Incentives
- External communications Session
- 8th December 2008
19Update on the Proposed Offshore Transmission
Regime
20Introduction
- Update on the Regulatory regime
- Offshore transmission background
- Key regulatory proposals, including key
developments in the November consultation - Update on the Tender process
- Projects that are likely to be tendered in the
transitional regime - Key features of the tender process
- Next steps
21Offshore Transmission
- Government expects that up to 33GW of offshore
renewables will be developed, within the entire
offshore area for the UK - It will cover offshore projects, including wind
and future tide based generation - There will be a regulatory regime for offshore
transmission connections - As for onshore generator pays transmission
charges - Risks and costs shared with consumers
- The first two rounds alone (South East North
West) cover up to 8 GW and this is likely to
require more than 2.5bn of transmission assets
22From Principles to practice
23Key Regulatory Proposals (1)
- The offshore generator connection requirements
will set the scope and trigger the selection of
an Offshore Transmission Owner (OFTO) - The OFTO to undertake this investment will be
appointed by competitive tender with the winner
awarded a transmission licence. - Tender will offer opportunities for innovation in
delivering fit for purpose, value for money
assets - Open-ended licences with 20 year initial
regulated revenue period - The tender process will be run by Ofgem,
resulting in selection of a preferred bidder and
approval of a long term regulated revenue stream. - Tenders will be run to in early years to select
OFTOs for transmission assets that are in
service or being constructed by the offshore
developer (transitional regime)
24Key Regulatory Proposals (2)
- The OFTOs annual income received from the GB
System Operator (GBSO) is based on asset
availability not utilisation - Availability incentive
- Aim incentivise rectification of short- and
long-term outages - Proposal includes a banking mechanism coupled
to the 10 penalty - OFTO accrues credits if availability gt target,
debits if lt target - Credits earned for good performance offset
penalties payable - Aim to incentivise consistent high performance,
while maintaining viability of OFTO proposal
25Key Regulatory Proposals (3)
- Post construction revenue adjustments
- Incremental capacity increases up to 20 by
existing OFTO - Further tender exercise for major capacity
increases - Adjustment mechanisms to address unexpected or
uncertain cost changes - End of the revenue stream
- If there is an ongoing generator demand for the
asset - Extension of revenue stream Where limited
additional investment is required (up to 20). - Retender Where ongoing use of the asset requires
significant new investment (over 20). - Performance bond towards the end of the period to
maintain incentive properties over the asset life - If there is no ongoing demand the licence would
be revoked
26Key Recent Policy DevelopmentsNovember Joint
Consultation
- Implementation proposals
- updated change proposals for standard framework
documents - change proposals for special conditions of NGETs
transmission licence - propose for changes to licences and industry
codes to be designated by Secretary of State and
become part of the standard framework - EU unbundling requirements
- OFTO of last resort consulting on revised
position developed in light of unbundling
announcement - NGET business separation requirements
- Published proposed text for NGET to support
business separation of the GBSO from OFTO arms - Performance incentives
- Published proposals for an OFTO operational
availability incentive framework
27Update on the tender process
28Overview of offshore projects likely to be
tendered in the transitional regime
29Tender Process
- A generator meeting certain pre-conditions will
trigger a notice inviting expressions of interest
from prospective OFTOs - Means that the tender is based on high level
generator requirements - Pre-conditions include the developer holding a
connection agreement with NGET and entering into
lease arrangements with The Crown Estate - The tender process will be co-ordinated through
annual competition windows this will be kept
under review - A four stage tender process is proposed i.e.
Pre-Qualification, Invitation to Tender, Best and
Final Offer, and Preferred Bidder - Bidders will be required to comply with industry
codes, technical standards, and licences - Ofgem will grant a licence to the winning bidder
- Seeking value for money, fit for purpose bids
- Licence sets out obligations and entitlements
- Ofgem will recover tender costs from bidders and
generators
30Tender process Transitional Arrangements
- Transitional arrangements will apply where
transmission assets have been or will be
constructed by the offshore developer - Ofgem will determine efficient asset values in
advance - OFTO will adopt assets post construction
- Phased projects will be adopted as phases are
completed - Arrangements will apply where the developer meets
certain pre-conditions ahead of Go Active or Go
Live - Pre-conditions include that the offshore
developer has completed the construction or has
secured financing to construct the assets - Bidders will be able to bid for more than one
project in a tender round - Ofgems evaluation strategy will be to seek the
most economically advantageous bid for each
project - The key factor will be the long-term revenue
stream, subject to evidence of suitable technical
and managerial capability
31OFTO Qualification Criteria
- Evidence of a suitable ownership structure for
the OFTO - evidence of a suitable approach for financing the
OFTO, demonstrating adequate financial standing
and an understanding of the investment economics
- evidence of suitable management capability for
operating the OFTO and - evidence of relevant technical and specialist
capability for OFTO operation, including but not
limited to - Evidence of an understanding of the key Health
Safety requirements (including policies and
experience) and - Evidence of an understanding of key environmental
requirements.
32Key Features of the Tender Process
- Certainty for OFTOs and Generators over
Technical, Licence and Regulatory Requirements - Stable regulated income for project lifetime
- Pre-agreement on risk allocation
- Transparent bidding process
- Greater flexibility on choice of design,
procurement, operational management, insurance,
financial structure, etc. - OFTO bids a 20 year revenue stream based on its
view of costs, returns, scope for future
developments. - We will develop our process in the light of
responses received to the October tender
consultation
33Who Can Participate?
- The tenders will be open to all interested
parties, including consortiums of companies,
banks, investment groups, manufacturers as well
as existing network companies - EU rules on unbundling will apply to the regime
and interested parties will need to be compliant
34Risk Allocation
35Summary of Regime Key Benefits
- For Generators
- Deliver cheaper and more timely offshore grid
connections - Be more focused on generators requirements
- Flexibility for future offshore generation needs
- For OFTOs
- Encourage innovation through competition and
enable new entrants to compete in the market - Long term regulatory certainty and lighthanded
regulation - Low risk - OFTO protected against generator
failure and credit risk
36Summary of Regime Key Benefits
- For Generators
- Deliver cheaper and more timely offshore grid
connections - Be more focused on generators requirements
- Flexibility for future offshore generation needs
- For OFTOs
- Encourage innovation through competition and
enable new entrants to compete in the market - Long term regulatory certainty and lighthanded
regulation - Low risk - OFTO protected against generator
failure and credit risk
37Next Steps
- Ongoing consultations on regime details
- Industry codes and technical standards
- Transmission licence conditions
- Further consultations expected early in the New
Year on - Tender regulations
- Tender documentation
- Final joint consultation
- Preparation for first tender round (transitional
projects) - Go-Active June 09 (with tenders expected to
start during Summer) - Go-Live June 10 (Prohibition extend offshore
and applies to offshore developments at 132kV and
above)
38(No Transcript)
39Questions
40Implementation Proposals
- Bridget Morgan
- Head of Standard Framework Development Offshore
Transmission - 8 December 2008
41Introduction
- Summary of legal framework change proposals
- Ongoing development of change proposals
- Next steps
- Impact on the role of the GBSO
42Why are Changes Being Made?
- To extend the existing frameworks offshore
(majority of changes). - To implement different arrangements offshore (in
limited circumstances where justified). - To maintain consistency within the regulatory and
contractual frameworks.
43What Changes have been Proposed?
- There are detailed change proposals within our
current consultation for - Transmission Licence (Annex 1)
- Balancing and Settlement Code - BSC (Annex 2)
- Connection and Use of System Code - CUSC (Annex
3) - Distribution Connection and Use of System
Agreement - DCUSA (Annex 4) - Distribution Code (Annex 5)
- Grid Code (Annex 6)
- System Operator Transmission Owner Code - STC
(Annex 7) - GB Security Quality of Supply Standard - GBSQSS
(Annex 8) - NGET Special Conditions (Annex 9)
44Why are Changes Being Made?
- To extend the existing frameworks offshore
(majority of changes). - To implement different arrangements offshore (in
limited circumstances where justified). - To maintain consistency within the regulatory and
contractual frameworks.
45Existing Contractual Arrangements Required for
Generator Connection to GB Transmission System
In Scotland
Transmission Owner
Generator
NGET
STC
CUSC
Grid Code
This is how it works now
46Proposed Contractual Arrangements required for
Offshore Generator Connection to GB Transmission
System
Same structure of arrangements with new type of
transmission licensee (OFTO)
47Proposed Contractual Arrangements required for
Offshore Generator Connection to GB Transmission
System
Offshore connecting to transmission system in
Scotland
Offshore Generator
Offshore Transmission Owner
NGET
CUSC
STC
Grid Code
Transmission Owner
NGET may need to seek transmission services from
more than one transmission licensee
48Proposed Contractual Arrangements required for
Offshore Generator Connection to GB Transmission
System
Offshore connecting via onshore distribution
system
STC
Offshore Transmission Owner
Offshore Generator
NGET
CUSC
DCUSA
Grid Code
Distribution licensee
NGET may seek services from a distribution
licensee
49What has changed since June 2008?
- We have identified policy proposals whose
implementation would require changes to a number
of the relevant documents in our current
consultation. - We have provided further detail about
implementation proposals for - Connection application process
- 20 limit on development of offshore transmission
system without further competitive tender - Standard transmission access products for
offshore generators - 132kV connected licence exempt offshore generators
50What has changed since June 2008? 2
- Changes across all documents to
- Take account of responses to our June document.
- Improve drafting of change proposals (eg
correction of consistency issues and
typographical errors). - Remove any parts of previous change proposals not
considered appropriate for the offshore
transmission regime. - Reflect changes implemented under normal
governance arrangements (updated baseline) - Specific changes to each relevant document
- Highlighted in chapter 4 and the introduction to
each Annex
51Current Consultation Standard Framework
Development
- Areas where we would particularly welcome input
from industry participants - Commercial treatment of OFTO provided reactive
power services. - GBSQSS security criteria for offshore transformer
equipment, offshore cable circuits and busbars
forming part of an offshore transmission system. - Development of NGET Seven Year Statement (SYS).
- Revised OFTO of last resort proposals.
- Proposed NGET business separation obligations.
52Ongoing Development Work
- Drafting review to check change proposals are
- Consistent
- Appropriate for revised OFTO of last resort
proposals - Correctly aligned with proposed change to
Schedule 1 of NGETs transmission licence - Further consideration of
- Commercial treatment of OFTO provided reactive
power capability - Proposed offshore transmission security criteria
- Changes implemented under normal governance
- Review of consultation responses
53Next steps
- Second consultation on tender regulations planned
for New Year 2009. - Further consultation on tender process planned
for February 2009. - Final consultation on licence and code change
proposals planned for spring 2009. - Go-Active planned for June 2009.
- Go-Live planned for June 2010.
54(No Transcript)
55Implementation of regime impact on the role of
NGET
56National Grids Role in GB Electricity
Transmission
- National Grids System Operator obligations under
its current licence terms are to - Operate the GB Transmission System
- Ensure GB Transmission frameworks are in place
- CUSC users rights and obligations with respect
to the transmission system - Bilateral Connection Agreement Site specific
agreement between User and NGET - Grid Code technical and operational
requirements for users - GBSQSS security and quality of supply standard
joint obligations with the Scottish TOs - BSC Balancing and Settlement Code
- STC requirements between NGET and TOs - joint
obligation with the Scottish TOs - Co-ordinate and produce the Seven Year Statement
- Offer terms for connection to and use of the
transmission system - Have charging methodologies in place
- Comply with distribution codes
57Operating the GB Transmission Networks
- Under current arrangements the TOs in Scotland
provide a transmission service in accordance with
the STC, which means - Making their transmission systems available
- Providing National Grid with a means to direct
configuration of the Scottish networks - Providing real-time information to National Grid
- Configuring their networks to National Grids
direction in accordance with agreed procedures - National Grid is in turn obliged to
- Ensure networks are operated within licence
standards - Ensure networks are operated within specified
limits - Operational limits are set out in the TOs
Services Capability Specification
58Relationship between TO and SO
Current Arrangements
Transmission Owner
System Operator
Scottish Hydro
Scottish Power
System Design Project Management Engineering
and Maintenance
System Planning System Operation Market
Facilitation Contractual interface with Users
National Grid
National Grid
59Ensure GB Transmission Frameworks are in place
Code change proposals to extend the current
framework to accommodate offshore transmission
are currently being consulted on
60Co-ordinate and produce the Seven Year Statement
- The Seven Year Statement (SYS) provides
information from which prospective transmission
users can evaluate connection opportunities - Published annually by National Grid (plus a
quarterly update) - Covers the GB Transmission System
- By default will extend to cover offshore area
- We also publish other information, for example
the Transmission Networks Quarterly Connections
update - What information would be useful to an offshore
developer?
61Offer terms for connection to and use of the
transmission system
- NGET is the contractual counterparty for all
users of the GB Transmission system - Two-stage process proposed for offshore
transmission regime - Initial connection offer at three months
- Tender process
- Agreement to Vary
- NGET manages the relationship with other TOs
(Scotland and Offshore) via the STC
62Overall Connection Application Process
Tender
Preferred
Process continues to licence award
Window
Bidder
Starts
Identified
Tender Process
Offshore network
Preferred
Connection
Connection
design options
Bidder
(including distribution
Offer
Offer
accedes to
options)
Connection
Connection
Agreement
Information
Information
STC
Application
Offer
Assessment of
to Vary
onshore impact
Acceptance
Acceptance
Connection Process
Connection Process
Connection
Connection
Construction,
Terms
Commissioning and
Offer
varied to
Accession proceed
Onshore
under STC
include
Works and
Governance
Final
Assumed
offshore
Offshore
works
Works
Stage 1
Stage 2
63Have Charging Methodologies in place
- NGET puts in place Charging Methodologies in
accordance with Transmission Licence Obligations - Facilitate competition
- Cost reflectivity
- Take account of developments in TOs transmission
businesses - All users of the GB Transmission System pay
Connection Charges and/or Use of System Charges
to NGET - NGET pays TOs in accordance with their own
Charging Methodologies
64Offshore charging proposals
- Offshore charging consultation closed on 24
November - Eight responses received
- Mixed views
- Report to be provided to Ofgem in December
- Deadline for veto will be prior to 1 April 2009
- NGET intends to publish further information
relating to indicative charges based on its
recommendations
65Comply with Distribution Codes
- Offshore transmission can connect to DNO onshore
- Will only arise if offshore generator requests
such an option - Will be reflected in the input data to the tender
process - NGET will investigate options for DNO connection
after the initial connection offer - This will involve applying to the relevant DNO
- Terms of DNO offer will be reflected through to
the User
66Transition - impact on NGET
- Transitional projects may already have
agreements with - NGET and/or
- A DNO
- These agreements will need to change
- Impacts will be considered on a case by case
basis - Ultimately these agreements will transit to
Bilateral Connection Agreements with NGET - Exact timing of the process is yet to be
finalised - We also need information from yourselves for
operational purposes
67Getting Connected Workshop
- Workshop held on 1 December 2008
- Good level of attendance/engagement on the day
- Issues considered
- Information useful to prospective developers
(SYS) - Walking through the Connection Application
Workshop - NGET will document and publish output from the day
68Where is more information available?
- Your Customer Account Manager
- For general queries please contact
- gbso.offshore_at_uk.ngrid.com
- NGET website for offshore transmission
- http//www.nationalgrid.com/uk/Electricity/offsho
reProject/
69 Questions
70Next Steps
- Current Consultation Closes January 9 2009
- Further Final Consultation
- Go-Active June 2009
- First Tenders Summer 2009 Transitional
Projects - Go-Live June 2010