Title: Work Controls Manager Workshop
1Work Controls Manager Workshop
- Chris Johnson, Al Boerner Steve Coleman
- April 15, 2008
2Workshop Overview
- Bldg 555 Mercury Cleanup Lessons Learned
- Work Coordination / Work Complexity Update
- Web Requisition Update
- Work Planning and Control (WPC) Training Course
Update - Integrated Safety Management (ISM) Performance
Measures - WPC Effectiveness Review August 2008
- Feedback/Open Discussion on WPC Issues and
Concerns
3Bldg 555 Mercury Cleanup Lessons Learned
- If a procedure exists Reference the SOP on the
Work Permit review the steps in the pre-job
briefing (Note any deviations from procedure due
to job situations/conditions.) - Workers can have different PPE, but must always
meet minimum prescribed (however it does allow
the auditor to raise the issue and open it up for
discussion). - Auditors can sometimes get in the way of safe
work practices. On the job it was noted that the
auditor was distracting the worker during job
performance.
4Work Coordination / Complexity
- DOE ISM Inspection Team believed the graded
approach document used for categorizing work into
low, moderate or high levels was exceptional.
However, there was no guidance on work complexity
and coordination. - Proposed changes to the graded approach document
was forwarded to several Work Control Managers
and Coordinators for review and comment - After several iterations April 1st minor
revisions to the subject area went active - Work Control Managers must flowdown revised
guidance to Work Control Coordinators
5(No Transcript)
6Web Requisition Changes
- Defined Manual/Hand Delivery and separated it
from Installation - Placed Warranty Work as a separate type of
on-site work and it doesnt need review from the
WCC to pin Requisition - Added Construction as a separate type of
on-site work and if selected, process the
requisition differently from other types of
on-site work (includes associated controls). - Reworded the Plant Engineering question to
include only Hoisting and Rigging services - Expanded Radio Frequency (Rf) wireless device
question - Added question on deliverable goods outside US
7Work Planning Control Training
- Jim Nemeth from the Training Qualification
Office is working on the WPC Web based course.
The revised course will include - Scenario based activities
- Integration of the various JTA course information
- Hazard analysis Control techniques
- Pre-job briefings, Change control, etc
- The final draft will be forwarded to Work Control
Managers for review and comment 4th quarter of
FY 2008
8ISM Performance Measures
- In the FY08 BSA/BNL Contract As part of BNLs
annual declaration, a set of performance measures
(due 3/31/2008) was required to be developed for
ISM Effectiveness determination (Performance
Evaluation Measurement Plan PEMP Target
5.2.1.5). - The 4 Process and outcome measures
- Work Planning Breakdown establish a baseline to
identify the percent of worker planned,
prescribed and permit planned work. Analyze to
determine if consistent with risk levels (through
assessments, RARs, ORPS, NTS, etc) - Evaluate unsafe behaviors (observations) to
determine correlation to ISM core functions
(leading indicator) - Evaluate the ratio of work planning and control
problems identified to the total number ORPS,
NTS, RARs, Injury Illness (lagging indicator) - Work planning problems that causes facility
downtime (e.g., inadvertent shutdown of systems
or processes) - report from maintenance
management (lagging indicator)
9WPC Effectiveness Review
- A number of existing actions in the ISM/Safety
Improvement Project Plan address WPC findings
identified in the 2005 ISM Readiness Review
those actions include - Creating a culture all work is planned and
develop supporting procedures methodologies
recently implemented worker planned, prescribed
and permit planned work - Integrate human performance factors and
principles into the WPC Management System - During the week of August 11th, 2008
effectiveness review team (DOE-BHSO, BNL IO
Office PNNL IO Office) will consider the
following criteria - Appropriateness of corrective actions
- Implementation effectiveness
- Performance Improvement
- Follow-up/Assurance
10Summary/Questions/Comments
- Work Control Manager Actions
- Flowdown work complexity and coordination
guidance to WCCs and forward an email to Chris
Johnson and/or Steve Coleman stating so. - Flowdown Web Requisition changes to WCCs
- Identify the of worker planned, prescribed and
permit planned work in respective
Departments/Divisions (for example 60 worker
planned, 35 prescribed and 5 permit planned)
and forward to Chris Johnson and Steve Coleman. - WPC Issues and Concerns?
11Work Planning Controlfor Work Control
Coordinators
Chris Johnson April, 2008
12Work Planning Control for Work Control
Coordinators
- Whats Changed in Work Planning Control Subject
Area - Three-Tiered Work Planning Format
- When How to Use Each Kind
- Complexity and Work Coordination for Work Permits
applying the Graded Approach
13Work Planning Control Changes
- WCM / WCC Qualification Local, Dept. Decision
- BTMS Training Local Knowledge Requirements /
Hazard Recognition - Planning Levels
- New Guidance / Instructions Exhibits Forms
- Change Control
- ISM Flowdown to Contractors / Vendors
- Visitor Notification
- Work Observations
14Three-Tiered Work Planning Format
- Worker Planned Work
- Prescribed Work
- Permit Planned Work
15Worker Planned Work
- Formerly Skill-of-the-Craft
- Typically Low Hazard Routine Work
- Characteristics of Worker Planned Work
- Employees Current on JTA
- JRAs have been completed for Hazards of Task
- Employee has Approval for Task on Qualification
Matrix - Worker-Qualified from OJT, Other Site Experience,
Degree, Certified License, Etc. - Planning Done Immediately Before Work is
Performed - Worker to Consider
- Hazards, Critical Steps, Failure Scenario, Likely
Errors, OK to Proceed, Change Control
16Prescribed Work
- Pre-Approved Work Plan or Procedure Written by
Others - Task is Important Enough, Done Frequently Enough,
or has a Hazard that Calls for a Specific
Procedure - Could be One-Time Procedure or Done in Advance
- Pre-Planning should Dictate Training, PPE,
Equipment, Tools, Access Requirements, or Special
Instructions
Caution Since this work is pre-planned,
attention must be given to any changed conditions
or new location hazards.
17Permit Planned Work
- Thorough Hazard Analysis Checklist
- Gets the Most People Involved Including Subject
Matter Experts - High Visibility to Workforce
- Planning is Usually done Close in Time to Work
Effort But Duration Could be Long so Changing
Conditions and/or Scope Requires Vigilance (WCC) - Best Buy In by Planners, Supervisors, Experts,
Workers - Has Mechanism to Obtain Feedback
18Permit Planned Work / Graded App
- Environment, Safety, Security, Health Risk
- Low Little chance of negative outcome if
workers do what they are suppose to do. Few, if
any, preventive measures required. - Moderate Risks are present that require
specific action or prevention strategy to ensure
mitigation. - High Without effectively employing hazard
mitigation strategies, a negative outcome is
likely.
Strategies should be employed in the following
order Replace/Eliminate Hazard ? Engineering
Controls ? Administrative Controls ? PPE
19Permit Planned Work / Graded App
- Complexity Level
- Low Task sequence is not significant. Minimal
interactions between personnel required. - Moderate Task sequence is significant.
Frequent interactions among personnel required. - High Continuous interdependency among personnel
required. elements. Plan demands input
discussion from as many experts as can be
utilized. Pay considerable attention to starting
conditions, watch for manage emergence. (Plan
well up front watch for changing conditions.)
20Permit Planned Work / Graded App
- Work Coordination
- Low No more than 3 functional groups within one
Dept/Div. Minimal coordination from support
groups. - Moderate More then 3 functional groups
involved. Work requires close coordination with
support groups. - High - More than 6 functional groups within one
department or combination of Dept/Div. or outside
contractors performing work requireing frequent
support systems to assist in risk mitigation.
Hand off points require particularly in-depth
planning.