Title: Capital Budgeting Further Considerations
1Capital Budgeting Further Considerations
2Lecture Outline
- Introduction
- The input for evaluating projects relevant cash
flows - Inflation real vs. nominal analysis
- Taxes CCA detailed calculations
- Summary and conclusions
3Introduction
- Up to this point we have examined the methods or
techniques for capital budgeting NPV, IRR, PI,
Payback, AAR. - All, except AAR, use cash flows for the analysis.
AAR is not accepted as a good technique of
analysis. - Now we turn to cash-flow analysis. From where do
we get the cash flows? We need to determine which
cash flows should be included in the analysis and
how to include them properly. Here we bring in
the concepts of relevant cash flows, inflation,
and taxes.
4Relevant cash flows
- The main principles behind which cash flows to
include in capital budgeting analysis are as
follows - Only include cash flows that change as a result
of the project being analyzed. Include all cash
flows that are impacted by the project. This is
often called an incremental analysis looking at
how cash flows change between not doing the
project vs. doing the project.
5Relevant cash flows
- Use projections of cash flows, not accounting
income. - Accounting income ? cash. Accounting income
cannot be spent, a firm can be losing cash but
have positive accounting income, so accounting
income is not necessarily representative of cash.
Cash is what really generates value cash can be
spent! - Depending on arbitrary accounting policies,
income can easily be manipulated, so, by itself,
it is not a reliable input for capital budgeting
analysis.
6Which cash flows are relevant to the project
analysis, which are not?
7Working Capital Changes Required by the Project
the cash flow effects
- Working capital (WC) items do not show up as
costs or revenues, however changes to the WC
items either require or free-up cash. - Increases in current assets required for the
project imply that cash is used so a cash outflow
occurs. - To increase inventories requires cash.
- To increase the cash-register float also requires
cash. - An increase in accounts receivable (AR) means
that the cash you may have recognized, through
revenue, hasnt been received yet. In effect, if
your project requires you to increase credit for
your customers (an AR increase), then this uses
up cash that you would otherwise have.
8More on working capital changes
- Increases in current liabilities, on the other
hand, free-up cash, so a cash inflow occurs. - Increasing accounts payable (AP) means that a
cost cash flow you may have recognized elsewhere
has not yet been paid, therefore the increase in
AP is a cash saving or inflow. - For other payables, the analysis is the same.
- Salaries payable, utilities payable, etc.
- Overall, changes in net working capital (NWC)
represent cash flows.
9Working Capital Example
- With the Project (that ends in 2006)
10NWC Solution
- No project, change in NWC CFs are as follows
- With the project, change in NWC CFs are as
follows - Change in NWC results in the following
incremental cash flows that should be included in
the project analysis
11Salvage Values and Clean-up Costs Self Study
- The change in salvage value or clean-up costs
represent cash flows related to a project. - Example consider a project to build an ice-cream
stand on some leased land that is currently used
for a parking lot. At the end of the lease, in 5
years, the land must be returned to a natural
state.
12Salvage/Clean-up Analysis Self Study
- Without the Ice-Cream Stand Project
- Year 0 cash flow 0. Nothing needs to be done,
the parking lot can continue for 5 years. - Year 5 cash flows -20,000 to clean up the
parking lot material. Sell the parking lot gate
for scrap for 200.
- With the Ice-Cream Stand Project
- Year 0 cash flows -14,000 to partially clean
up the parking lot material now. Sell parking lot
gate for 1,500. - Year 5 cash flows -16,000 to clean up the
remaining parking lot material and remove ice
cream stand. Sell ice cream stand for scrap for
1,000.
Do the incremental analysis
13Salvage/Clean-up Solution Self Study
14Inflation
- Sometimes a projected cash flow is given as a
nominal amount (the expected actual amount of
cash to be received or paid). - Sometimes a projected cash flow is given as a
real amount (the current or date 0 purchasing
power of the cash flow. - Note, the real cash flow is not the PV.
15Nominal/Real Cash Flow Examples
- Freds contract with his employer states that he
will be paid 100,000 three years from now. - This is a nominal cash flow. Fred expects to
actually be paid 100,000 in three years. - Currently, the basket of goods used to measure
the consumers price index costs 125. Sue
expects to receive a cash flow in four years that
will allow her to purchase 100 of these baskets. - This can be represented by a real cash flow.
- The real cash flow amount would be 12,500.
- If there is inflation between now and four years
from now, then the nominal (actual) cash flow Sue
expects must be more than 12,500. She will
expect a nominal cash flow that will buy the same
100 baskets. In terms of year 0 purchasing
power, the real cash flow is 12,500.
16Are real cash flows the same as present values?
- No!
- Which would you prefer to receive, 1,250 today
(which can buy 10 baskets of goods) or a dollar
amount in 5 year that will buy 10 baskets of
goods then? - The 1,250 today is preferred even though, in
terms of purchasing power, both payments give the
same purchasing power. - Since the 1,250 today is preferred, the two cash
flows cannot have the same present value.
17How do we discount real cash flows?
- Consider the basket of goods that costs 125
today. Suppose inflation is expected to be 5
each year for the next 5 years. - How much, in real dollars, do we need to be able
to purchase 10 baskets in 5 years? - Let this be our real cash flow
- How much, in nominal dollars do we need to be
able to purchase the same 10 baskets in 5 years? - This must be the equivalent nominal cash flow
- What is the relation between the real and nominal
cash flow? (be exact formula?)
18Discounting real vs. nominal cash flows
(continued)
- If the relevant discount rate for the nominal
cash flow is 12, then what is its PV today? - What discount rate applied to the real cash flow
would get the same PV today? - What is the relation between the real discount
rate and the nominal discount rate? (be exact
formula?)
19Conclusions on real and nominal cash flows
- It is possible to express any cash flow as either
a real amount or a nominal amount. - Since the real and nominal amounts are
equivalent, the PVs must be equivalent, so
remember the rule
20Use of real cash flows
- If a projects cash flows are expected to grow
with inflation, then it may be more convenient to
express the cash flows as real amounts rather
than trying to predict inflation and the nominal
cash flows.
21Taxes the basics
- Unfortunately, in most civilized countries both
corporations and individuals must pay tax on
income and profits. - Tax is a cash outflow. So we must include taxes
in our capital budgeting analysis.
22Calculating tax effects from non-financing
components of the income statement.
- Recall the income statement you learned about in
accounting - Whatever affects the income statement amounts
will also affect the taxes paid. - Assume depreciation here is what is recognized
for tax purposes. In Canada, this is called
capital cost allowance, CCA.
23Tax consequences and after tax cash flows (assume
a tax rate, Tc, of 40)
24Yearly cash flows after tax
- Normally we project yearly cash flows for a
project and convert them into after-tax amounts. - CCA deductions are due to an asset purchase for a
project. CCA is calculated as a of the
Undepreciated Capital Cost (UCC). Since a
amount is deducted each year, the UCC will never
reach zero so CCA deductions can actually
continue even after the project has ended (and
thus shelter future income from taxes). All
CCA-caused tax savings should be recognized as
cash inflows for the project that caused them.
25Detailed CCA Calculations
- Example DuoCity Taxi is considering expanding
its fleet. - The cost of the new taxis is 1,000,000 now.
- Taxis fall under CCA Class 16 and are allowed a
CCA rate of 40. - DuoCitys tax rate is 45 and the relevant
opportunity cost of capital is 15. - The project will generate revenues in excess of
expenditures of 450,000 per year for 5 years. - The project will also require an immediate
working capital increase of 50,000, no
intermediate changes, and a reversion to normal
working capital requirements at the end of 5
years. - Assume the taxis relevant to this project will be
sold at the beginning of the 6th year for
100,000.
26Analysis using the Tax-Shield Approach keep CCA
tax shield effects separate in the analysis
- NPV of above cash flows
- PV of CCA tax shields
- NPV of the project
27PV CCA Tax Shields
- C cost of asset
- d CCA rate
- Tc Corporate tax rate
- k Discount rate for CCA tax shields
- Sn Salvage value of asset sold in period n with
lost CCA deductions beginning in period n1 - Note In this course, assume no Capital Gains on
disposal of the asset. Also, assume Asset Pool
is not terminated upon disposal of the projects
asset.
28Summary of Capital Budgeting Items and Tax Effects
- The following formula may help summarize the
projects NPV calculation. - NPV -initial asset cost1
- PVSalvage Value or Expected Asset Sale
Amount1 - PV incremental cash flows caused by the
project2 - PV incremental working capital cash flows
caused by the project1 - PVCCA Tax Shields
- Footnotes
- 1.These items usually have the same before-tax
amounts and after-tax amounts. I.e., there is no
tax effect. For asset purchases/sales the tax
effect is done through CCA effects. - 2.These items usually have the after-tax cash
flow equal to the before tax cash flow multiplied
by (1-Tc).
29Competitive Advantage and Positive NPV
- Only if there are sources of competitive
advantage, should a positive NPV result. - The qualitative analysis of competitive advantage
and the quantitative NPV analysis therefore act
to complement each other. Combined, they lead to
better decisions. - The stock market recognizes such good decisions
by rewarding new projects that utilize or enhance
competitive advantages and generate positive
NPVs. - Stock prices typically rise on the announcement
of a previously unanticipated project that
enhances the corporations strategy and generates
positive NPV.
30Summary and Conclusions
- A careful NPV (or IRR or PI) analysis will show
which projects will add wealth to the firm. This
should be confirmed with an equally careful
analysis of the corporate strategy to ensure that
the positive NPV result can be shown to be the
result of some form of competitive advantage. - All relevant cash flows for a project must be
included in the capital budgeting analysis for a
project. - Relevant cash flows are those that change as a
result of accepting the project. - We exclude things that dont change. We also
exclude interest charges or financing expenses
because these are accounted for in the discount
rate. - Tax effects must also be included. CCA is a
special case to consider because the tax savings
may continue beyond the end of the project. - Once we have all after-tax cash flow effects
projected, we can conduct our analysis of a
project using our preferred methods NPV, IRR, or
PI Payback may also be used but its
oversimplification should be recognized.