Title: Implementing a BRT Project: The Final Steps


1
Implementing a BRT Project The Final Steps
1010 1130 a.m. Michael A. Sanders Chair,
Connecticut Department of Transportation (Moderat
or)
2
Session Presentations
  • ITS Enhanced Bus Rapid Transit, Matt Hardy
  • HOV and BRT A Great Combination, David
    Schumaker
  • A New Beginning Transforming Bus Operations at
    MBTA through Bus Rapid Transit, Steven Epps

3
  • Steven Epps
  • 26 year employee of the Massachusetts Bay
    Transportation Authority (MBTA)
  • Director of Bus Operations
  • Has held the positions of Bus Driver, Inspector,
    Instructor, Facility Superintendent and Chief
    Transportation Officer

4
A New Beginning Transforming Bus Operations at
the MBTA through Bus Rapid Transit (BRT)
Steve Epps, Director - Bus Operations, MBTA
5
MBTA Bus Operations
  • 2,300 employees
  • Over 1,000 vehicles
  • 10 Maintenance Facilities
  • 90,000 daily fleet miles
  • Over 200 bus routes 9,200 bus stations stops

Southampton Street Maintenance Facility
Construction
6
MBTA Ridership 2004
Total Daily Ridership 1.2 Million passengers
(unlinked)
4 out of 10 MBTA customers are bus riders for all
or a portion of their trip (linked)
7
MBTA Bus Operations (1980)
  • 8 maintenance facilities
  • Over 950 diesel high floor vehicles
  • Average Vehicle age 7 years old
  • Average MF age 39 years old
  • Most recently built facility Cabot Yard (1979)

8
MBTA Priorities (1980s) Subway Systemwide
Investment
  • 1.5 Billion investment
  • Subway systemwide improvements
  • Subway station modernization
  • Platform extensions
  • Power and signal system upgrades
  • Major track replacement program
  • Subway expansion
  • Northwest Corridor (Red Line)
  • Southwest Corridor (Orange Line)
  • Acquisition of technology advanced vehicles
  • Advanced Technology Operations Control Center
    (OCC)
  • Increased train consists from 4 to 6

9
MBTA Priorities (1990s) Systemwide Improvements
  • 2.0 billion investment
  • Commuter rail expansion
  • Worcester Commuter Rail Extension
  • Old Colony Railroad Extension
  • Newburyport/Rockport Extension
  • Commuter Rail vehicle procurement (214 coaches,
    25 locomotives)
  • 20M modernization of OCC
  • Build out of major intermodal facilities
  • New commuter information systems
  • 98 new communities served
  • Doubled commuter rail ridership

10
MBTA Bus Operations (Aug. 2003)
  • No new bus maintenance facilities built
  • 978 diesel, high floor vehicles
  • 25 low floor, CNG vehicles
  • Average Vehicle age 14 years old
  • Average MF age 64 years old
  • Youngest maintenance facility Cabot Yard (23
    years old)

11
MBTA Bus Operations (Nov. 2004)
Arborway Maintenance Facility
  • 2 new maintenance facilities in operation
  • Southampton Street Arborway Yard Maintenance
    Facilities
  • Strategically located in industrial areas
  • High end technological equipment
  • Modern Maintenance Control Reporting Software
    System
  • A third maintenance facility in design
  • Upgrades and improvements at Cabot Yard and the
    Everett Backshop and Heavy Repair Facility

Cabot Yard CNG Retrofit (Underway)
12
MBTA Bus Operations (Nov 2004)
  • 578 new low floor, clean fuel, advanced
    technology vehicles (compressed natural gas,
    ultra low sulfur diesel dual mode vehicles)
  • Average vehicle age 4 years old
  • Customer friendly bus stops (shelters
    schedules)
  • Bus fleet equipped with Global Positioning
    Systems (GPS), automatic vehicle announcements
    and variable message signage

13
New Workforce Standards
  • Basic aptitude recruiting skill set required
    for
  • Mechanics
  • Engineers
  • Electricians
  • Emphasis on diversity and maximizing talents of
    workforce potential
  • Top down accountability
  • Information and resources to bring a standard of
    excellence

14
Bostons 5th Rapid Transit Line The Silver Line
  • Rapid transit without rails
  • The flexibility of bus service combined with
    attributes normally associated with rail service
  • A major investment
  • A highly effective choice to improved the public
    transportation options and boost ridership

15
Building the Silver Line Project-by-Project
Worcester Square
  • Washington Street Service - Dudley Square to New
    England Medical Center
  • South Boston Piers Transitway South Station to
    Logan Airport
  • Silver Line Tunnel New England Medical Center
    to South Station

16
Silver Line Phase I July 2002
Phase I Washington Street Replacement Service
  • 2 Miles
  • 16 Stations
  • 17 New Vehicles
  • Ph. I Cost 50M

Worcester Square
17
Silver Line Phase I project elements include...
  • Complete street reconstruction, building edge to
    building edge.
  • A reserved lane for BRT service.
  • New lighting, landscaping, information kiosks and
    street furniture.
  • A design that does not preclude light rail in the
    future.

18
Silver Line Phase I Ridership Impact Daily Riders
19
Silver Line Phase I Ridership Impact Trip Time
Reduction
20
Silver Line Phase II Fall 2004
Phase II South Boston Transitway
Logan Airport
BMIP
BCEC
Worcester Square
  • 4.1 Miles
  • 3 Stations
  • 32 New Vehicles
  • Ph. II Cost 601M

21
Silver Line Phase II elements includes...
  • 1 mile tunnel from South Station to the South
    Boston Waterfront.
  • 3 new stations
  • South Station
  • Courthouse Station
  • World Trade Center Station
  • A new maintenance facility on Southampton Street.

Russia Wharf (NATM Method)
South Station
Courthouse Station
22
Silver Line Vehicles
  • Phase I Vehicle
  • 60-foot articulated vehicles
  • CNG powered
  • Low floor
  • Smart Bus Technology
  • Phase II Vehicle
  • 60-foot articulated vehicles
  • Dual mode
  • Low floor
  • Smart Bus Technology

23
Silver Line Phase III December 2010
Phase III Silver Line Tunnel
  • 1 Mile
  • 3 Stations
  • Ph. III Cost 760M
  • Total Silver Line Cost 1.4B

Worcester Square
24
Silver Line Phase III New Starts Status
  • Silver Line Phase III is among 27 projects in the
    preliminary engineering phase for consideration
    in FTAs New Starts process
  • Silver Line Phase III is the MBTAs priority
    project for consideration in FTAs New Starts
    process
  • Projects are rated based on seven New Starts
    criteria
  • Mobility improvements
  • Environmental benefits
  • Operating efficiencies
  • Cost effectiveness
  • Transit-supportive land use
  • Local financial commitment
  • Other factors

25
(No Transcript)
26
(No Transcript)
27
The Silver Line A catalyst for economic
development
Area D-4 Police Station (5M)
South End Community Health Center (30M)
Laconia Lofts (18M)
Joseph Moakley Courthouse (200M)
28
(No Transcript)
29
Why BRT for the Silver Line?
  • Flexibility
  • Capacity
  • Convenience
  • Allows for incremental growth
  • Cost effective investment
  • Triggers economic development

30
Silver Line Benefits An Investment in Transit
Community
  • Improves mobility reduces travel times
    connects/extends the MBTAs transportation
    network
  • Enhances economic opportunity provides
    accessibility to jobs
  • Revitalizes and expands business districts and
    activity centers creates and sustains jobs
  • Supports transportation policies on environment,
    energy conservation, providing health, safety and
    security for our citizen, expanding multimodal
    transportations systems