Title: Comal County Chip Sealing
1Comal County Chip Sealing
June 26, 2007
2 3(No Transcript)
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17Chip sealing is the application of a bituminous
binder immediately followed by the application of
an aggregate. The aggregate is then rolled to
embed it into the binder.
Binder Application
Aggregate Application
Rolled
18Advantages of Chip Sealing
- Improved Skid Resistance
- Cost Effective Treatments
- Good Durability (Typically 5-7 Years)
- Ease of Construction
- Chip Seal 1 Mile/Day
- Asphalt 1 Mile/Week
19Disadvantages of Chip Sealing
- Flying Chips Broken windshields and vehicle
damage - Noise Considerations Chip seals can be noisy
to travel on - Weather Considerations Must be constructed
during warm, dry weather during daytime only - Pedestrian Not good for roller-blading
skateboarding
20Materials
Binders must provide good adhesion, or stickiness
- Aggregates must have following characteristics
- Single-sized, if possible
- Clean
- Angular (not rounded)
- Aggregates must be damp for emulsion use
21Construction Process
Surface Preparation
- Crack Sealing or Filling of Cracks
- Patching Deteriorated Areas
- Cleaning or Brooming Any Loose Material
- Removing Pavement Markers and Delineators
22Construction Process
Binder Application
- Uniformly Apply the Binder Over the Surface at a
Designed Rate - Pavement Surface Temperature Should be 55ºF and
Rising - Humidity Should be 50 or Lower
- Most Important Step in Process
23(No Transcript)
24Construction Process
Aggregate Application
- Should Follow the Binder Application by no more
than 90 Seconds - Should be no more than 100 Feet Behind
Distributor Truck
25Construction Process
Aggregate Application
- Should Follow the Binder Application by no more
than 90 Seconds - Should be no more than 100 Feet Behind
Distributor Truck
26Construction Process
Rolling
- Initial Rolling by Pneumatic Roller or Steel
Rollers - Compaction by Traffic Finishes the Process
- Should be Done During Hotter Weather
- Should Follow Aggregate Spreading by no more
than 500 Feet - Minimum of Two Rollers Should be Used to Cover
the Full Width of the Chip Spreader
27(No Transcript)
28Construction Process
Brooming
- After Chip Seal, Excess Aggregate Must be
Broomed Off - Within 2 to 4 Hours after Sealing
29(No Transcript)
30Possible Problems
- Bleeding Too much binder leading to leaking
of emulsion - Traffic Control Ensure that vehicles do not
drive on binder application - Shelling Aggregate not applied in a timely
manner. Binder sets. Aggregate does not stay
in place.
31(No Transcript)
32Comal County Canyon Lake Spillway Canyon
June 26, 2007
33Storm Total for 1998
1998 Storm Totals
34Storm Total for 2002
35Structural Flood Control Measures in Comal County
Canyon Reservoir
36Structural Flood Control Measures in Comal County
Emergency Spillway
37Structural Flood Control Measures in Comal County
x
38(No Transcript)