Title: DAFNE Status Report
1DAFNE Status Report
Scientific Committee Nov-2005
2OUTLINE
-
- Milestones from last SC
- Status of the Kloe run
- Plan and schedule for the off-energy Kloe run
- Schedule and plans for the Finuda Roll-in
- Conclusions
3The road toward Lgt1.5e32
now 1.4e32 Ldaygt10pb-1
now 8.6pb-1 Lmonthgt
200pb-1 now 170pb-1
Further re-activation of the pumps across the RF
cavity (5 gain), more pumps and cooling Faster
switch of the transfer lines (5 gain) Emittance
reduction (10 gain, requires a 1day MD) IP
Coupling reoptimization (10 gain, requires a
1day MD) Tunes closer to the integer or just
above the half integer (10 gain, requires 2days
MDs) The last four tests will be done
sequentially in the next month in our reserved
days (one each week).
Slide shown at the May-2005 SC
4DAFNE DELIVERED L IN YEAR 2004-5 for KLOE
109-111 bunches I-peak 2.05 A Ipeak 1.39
A Lpeak 1.53e32 cm-2s-1 Lday peak 9.4
pb-1 Lmonth gt 215 pb-1 L2004-5 gt 2000 pb-1
5DAFNE Peak rate on a 2hrs interval
Lhour peak 431nb-1/hr Corresponding to
a potential of 10.4pb-1 in 24hrs of
continuos Operations Lbest shift 3.26pb-1
6- Delivered gt215pb-1 logged 204pb-1 in 30 days!!!!!
7Peak currents
- Electron current reached record value of 2.1Amps
- Routinely exceeded 1.85Amps in collision
Positron current reached record value of
1.39Amps Routinely exceeded 1.3Amps in collision
Routinely run with 109 bunches and 111 at times
8Tune shift in Oct 2005Light Xs show the
effective tune shift once the correction for the
finite bunch lenght is appliedBlow-up from
beam-beam about 15Blow-up from other
high-current effects of the order of 10
9- Run History from May to November
- Steady run with few MDs (mainly for fbcks
improvements). - Long down time due to Criogenic problems,
succesfully identified in a faulty turbine and
fixed. - Overall down due to criogenics about 5 weeks
(2weeks simply due to cleaning of the system
after some minor hardware failure) - Additional loss of uptime due to time-sharing
with other users (BTF and Synchrotron light
dedicated runs) - Main improvement in peak and integrated
luminosity due to fbck, faster switch and
adiabatic tuning.
10Peak luminosity evolution in 2004-5
Down due to Criogenic problems
Down and lower Integrated luminosity due to
scheduled BTF runs
Other smaller holes due to minor hardware
failures and dedicated Synchrotron Light runs
11Plans and schedule for the Kloe Run
- Our web figures for the integrated
luminosity for Kloe have been inflated by about
5 since the very beginning (1999!). - We have reset our counter on the Kloe logged
luminosity from their presenter, currently
about 1970pb-1. - When we reach 2000pb-1 (in a few days) we will
start the energy scan that should be completed by
the end of the year (about 40pb-1 needed). - The off-energy run that requires about 200pb-1
should take place from January to March and will
start immediately after the recovery from the
Xmas shutdown - It is not yet decided what to do if we are
lucky and we deliver the required luminosity
earlier than March,31 - Finuda roll-in needs about 3.5 months
12Summary performance for the Kloe run
- Reached 75 of our target peak luminosity
1.531032 instead of 2.01032 - Reached 94 of our target daily luminosity
- 9.4pb-1 instead of 10pb-1 (Dafne Units).
- Reached 110 of our target monthly luminosity
- 221pb-1 instead of 200pb-1 (Dafne Units)
- Reached our target delivered luminosity
(2000pb-1 Dafne Units) with 2 months more w.r.t.
our planned schedule of 16months, 85 average
luminosity delivered w.r.t. our target
13- Dafne Upgrades for the Finuda and Dear
runs. - Finuda Roll-in April-July 2006
- Upgrades for the Finuda run aimed to exceed
2.51032 - Kloe Roll-out and installation of a standard
beam pipe with a triplet of small quads gt - - Optics very similar to what we have now
with Kloe - - smaller crossing angle, more parasitic
beam-beam, smaller piwinsky angle - - less coupling at the IP (just two
D-quads to adjust), smaller y-sizes - specific luminosity like in Kloe (already
true for the 2003-4 run)
14- 2) Remove all the broken Ion-Clearing-Electrodes
- Shield the ICE in the Wigglers with a
metal-sheet gt - - Smaller e-ring impedance, 30 reduction in
bunch lenght 20-30 reduction of vertical
emittance at high current, - - Smaller longitudinal and transverse
instabilities in general - Possibly 20-30 increase in luminosity
- 3) Install the fast stripline injection-kickers
and new tapered chambers between bends and
kickers and kickers and septa gt - - Better injection efficiency (from 50 to
gt90) - - Virtually no background during the
injection - - Faster injection
- - Higher positron current gt10
- - Smaller rings impedence (10-20)
- Possibly 10-20 increase in peak luminosity
and 20-30 in integrated
15- 3) Apply a NEG or a Ti coating in the p-ring
wigglers chambers - - Increase of the p-electron cloud
instability up to a factor 2 - Possibly 40-60 increase in p-current and
luminosity - 4) Insert a shield in the vacuum chamber across
the compensators to reduce the number of
parasitic beam-beam - - Higher currents in collision gt10
- Possibly 10 increase in luminosity
- 5) Insert 2 horizontal wires in the IP area or
in the splitters area to compenaste for the
parasitic beam-beam - - Higher currents in collision gt30
- Possibly 30 increase in luminosity
16- 6) Modify the wiggler poles to eliminate the
wiggler non-linearities - - Increase the ring energy acceptance by a
factor 2, the toushek lifetime by a factor 4 - Possibly 10-20 increase in integrated
luminosity - Background decrease by a factor 2-4
- 7) Transverse feedbacks upgrade with the new SLAC
modules and possibly new pick-ups - - Higher currents and more stable beams
-
- 8) More ideas
17- Overall possible luminosity gain way in
excess of a factor 2, 50-60 gain seems
reasonable gt 2.51032 - Several upgrades synergic with other
activities and top-of-the-line worldwide kickers
(ILC), wigglers (ILC), Ti-coating (ILC,LHC) - All the upgrades synergic with the DAFNE
upgrade - Further upgrades for the DEAR run to reach
41032 - - New Interaction region with low
chromaticity, earlier beam-separation Possibly
30-50 more luminosity - - Two crab cavities (one per ring) Possibly
20-50 more luminosity (20 simply from the
geometric factor) - - More ideas to come
18Conclusions
Dafne has overall reached 85 of the target for
the 2004-5 Kloe run (averaging peak, monthly and
total integrated luminosity) Based on the
acquired know-how we have a clear and easy way
to further improve the machine performances for
the Finuda run and the Dear run. Moreover a lot
of the work that we will do for the Finuda and
Dear runs will great benefit the understanding of
the critical parameters for the Dafne Upgrade
(and b.t.w. will deliver more data to the
users) Many thanks to the Acceleration Division
for the great work done!!!!