CALICEUK: The Big Squeeze - PowerPoint PPT Presentation

About This Presentation
Title:

CALICEUK: The Big Squeeze

Description:

These stand some chance of being funded from new proposals in the future ... Currently under test; was put in beam the week before Xmas ... – PowerPoint PPT presentation

Number of Views:90
Avg rating:3.0/5.0
Slides: 12
Provided by: paulda6
Category:
Tags: caliceuk | squeeze | xmas

less

Transcript and Presenter's Notes

Title: CALICEUK: The Big Squeeze


1
CALICE-UK The Big Squeeze
  • Paul Dauncey

2
The minimal programme
  • Some parts of the programme are generic
  • Can be applied to more than just the ILC. These
    stand some chance of being funded from new
    proposals in the future
  • Hence for now we want to keep them going at a
    lower level than originally hoped until they can
    be revived.
  • Some parts are close to some major breakpoint
  • E.g. some publishable results coming within the
    next year.
  • These should be reduced to the minimum but still
    at a level that publications could be produced
    so we reap the benefit of the UK investment.
  • Some parts have UK responsibilities which
    effectively cannot be handed off
  • Would seriously damage the UK reputation (further
    than already done) as an international partner
  • We have assumed that Rolling Grant (RG) staff,
    who have mainly small fractions of FTEs on
    CALICE-UK, will continue to work as expected.
  • There are five workpackages which will be
    discussed in turn
  • We budget travel centrally this would be needed
    in addition to the following

3
Workpackage 1 Beam tests
  • Detailed comparison of simulation models with
    data
  • Take large data samples in physics prototype
    calorimeters
  • Highly generic relevant to any calorimeter system
  • Longest running, biggest programme within CALICE
  • UK joined this in 2002, providing the DAQ system
  • Also provide real-time monitoring during
    data-taking
  • Have a dataset of several 100M events
  • First significant run was at DESY in May 2006
  • Took data at CERN during 2006 and 2007
  • Moving to FNAL for 2008/9

4
WP1 minimal programme
  • First publication of beam test data expected in
    2008
  • UK people have contributed significant effort to
    the analysis and lead several areas
  • Both the Physics and Analysis Coordinators are
    from the UK
  • Ridiculous to stop this before publications are
    produced
  • Need to keep some RA activity in this area
  • Would normally be very active in future
    data-taking at FNAL in 2008
  • If really reducing to minimal contribution then
    must cut back here
  • Cannot stop working on DAQ this would stop the
    whole CALICE beam test
  • Cannot hand off DAQ responsibilities expertise
    is completely within the UK
  • For DAQ itself, can avoid using RA effort for
    real-time monitoring, then need some low level of
    RA effort
  • We are assuming analysis would be mainly after
    FY08/09 so we cannot take part
  • Must be sure we can analyse FNAL data if funding
    becomes available later
  • We will not have funds to travel to do shifts if
    really reduced to minimal
  • Have to negotiate with CALICE that the above
    contributions are sufficient

5
Workpackage 2 DAQ
  • Construction of DAQ systems using commercially
    available components wherever possible
  • No custom VME cards and crates
  • UK clearly leading ILC effort in this area
  • Again highly generic relevant to any detector,
    not even just calorimeters, e.g. LHC upgrades
  • Contributing to EUDET collaboration
  • Building technical prototype calorimeters
  • UK responsibility to provide DAQ system
  • EU funding legally requires matching funds
  • Testing of EUDET systems scheduled to start after
    FY08/09
  • Must keep this going through the next year
  • Again, withdrawal of UK could cause project to
    collapse

6
WP2 minimal programme
  • Most of electronics design uses RG effort
  • We hope this should be able to continue as is
  • Could need to hand some responsibilities off to
    EUDET colleagues movement of items on the
    interfaces and/or firmware/software most likely
    but needs to be negotiated
  • Equipment spend is relatively low but is needed
    in FY08/09
  • Some RA effort clearly also needed for testing
  • Development of DAQ software needs RAs
  • Essential to allow this to roll on some
    significant level of RA effort needed here
  • EUDET provides some level of funding
  • It would just about be possible to complete the
    EUDET responsibilities in FY09/10 without STFC
    funding (if academic effort is sufficient to
    count as matching funds)
  • However, possibly would not have enough to get
    results from the prototypes as well
  • Assume a generic RD proposal will need to be
    submitted to start in FY09/10
  • Otherwise no matching funds for EUDET
    continuation, EUDET

7
Workpackage 3 MAPS
  • Design of monolithic active pixel sensors for a
    binary electromagnetic calorimeter
  • Unique idea no other project on this worldwide
  • Need probability of two MIPs in a pixel to be low
  • Needs extremely fine granularity 100mm
  • Hence, excellent spatial resolution and
    potentially dramatic change for PFAs
  • First test sensor produced in 2007
  • Currently under test was put in beam the week
    before Xmas
  • Developed new deep p-well process for this
    sensor
  • Reduces charge collection in non-sensitive
    circuit elements
  • Wide applications for other detectors and other
    STFC science
  • UK now in very strong position for generic MAPS
    development

8
WP3 minimal programme
  • Have already learned a lot from the first sensor
  • Not ILC-realistic but mainly to test ideas
  • Always planned for larger second round sensor in
    2008
  • Only way to reduce cost is to slow down and
    descope
  • Can do this here as it is a UK-only project
  • Produce second round sensor but without all
    required features
  • Much smaller and produced in shuttle run so
    significantly cheaper
  • Reduction in scope reduces engineering design
    effort required
  • Also must produce later than originally planned
  • Need RA and RAL effort for testing essential to
    keep this
  • Could finish studies with second sensor within
    FY08/09
  • This would be a breakpoint where the project
    could close down...
  • ...but would be a criminal waste of the strong UK
    position
  • Would expect to submit generic proposal for
    FY09/10 and beyond

9
Workpackage 4 Mechanics
  • Work on mechanical aspects of ECAL structure
  • Assembly, cooling, endcaps, etc.
  • Reasonably specific to ILD design
  • But could probably be adapted to other structures
    if using similar techniques
  • Responsibility to contribute to EUDET technical
    prototype construction
  • All equipment spend to be completed in FY08/09
  • Again, cannot allow UK to fail to deliver on
    vital aspect of EUDET
  • Relatively small workpackage all effort is RG
  • Only low level of equipment funds needed
  • Must continue with original plans even in minimal
    funding scenario

10
Workpackage 5 Physics studies
  • What we are really here for the eventual physics
    potential
  • Well known that UK is leading PFA development
  • CALICE-UK people also heavily involved in WW,
    ZHH, etc, studies, with more being started
  • Big issue can we continue these studies in
    minimal scenario?
  • EDRs (and LoIs?) potentially delayed so
    longer-term commitment than just FY08/09
  • If LoIs not delayed, then this could be a
    significant breakpoint, but then would be
    expected to stop afterwards not really what
    Intent means
  • Very hard to claim these studies are generic we
    debated whether they could even be common to ILD
    and SiD
  • I believe these studies are critical to our
    long-term investment in the ILC
  • But I have been told STFC will be highly unlikely
    to fund any effort in this area
  • This is a purely political, not scientific,
    statement
  • If correct, then we will need to continue with
    academic and RG effort only

11
Summary
  • CALICE-UK have produced a minimal programme
  • Weve squeezed ourselves to the limit
  • We are really at rock bottom for quite important
    items
  • We are dropping things where significant UK
    effort has been invested
  • We have to assume there will be some possibility
    of future grants
  • Proposals for generic RD projects need to be
    submitted, and hopefully approved, to support
    this work after FY08/09
  • If these are not available, then things will be
    extremely bad
  • We do NOT consider this as a reasonable outcome
    of the current situation
  • This is the absolute limit of last resort
  • This is not something STFC could claim was an
    acceptable level
  • Pressure must be maintained to have a
    peer-reviewed, scientifically-based outcome to
    the current difficulties
Write a Comment
User Comments (0)
About PowerShow.com