Regional OnBoard Bus Survey Proposal - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Regional OnBoard Bus Survey Proposal

Description:

Would complement the TPB Household Travel Survey currently underway and Spring ... TPB staff with assistance from local agency staff will develop the sampling plan ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 11
Provided by: reg151
Learn more at: https://www.mwcog.org
Category:

less

Transcript and Presenter's Notes

Title: Regional OnBoard Bus Survey Proposal


1
Regional On-Board Bus Survey Proposal
Presentation to the TPB Technical Committee
Robert E. Griffiths Technical Services
Director October 5, 2007

2
Background
  • WMATA has budgeted 750,000 for a Metrobus
    Passenger Survey in 2008
  • TPB Regional Bus Subcommittee requested that
    additional funding be identified for a
    supplemental local bus on-board survey that would
    complement WMATAs effort
  • Supplemental Survey would survey riders on local
    and county agency buses, including systems
    outside the WMATA Compact area

3
Spring 2008 Metrobus Survey
  • Purpose of WMATAs On-Board Survey
  • Subsidy allocation for WMATAs Regional Bus
    Routes
  • Collection of origin-destination trip patterns
    for bus route planning and travel demand model
    validation
  • Profile of current bus riders

4
TPBs Interest in a Supplemental On-Board Bus
Survey
  • With data from the 2008 Metrobus Survey,
    supplemental survey would provide complete
    picture of bus transit usage in the region
  • Would provide information on bus only transit
    ridership in the suburbs, not easily obtained by
    other means
  • Would complement the TPB Household Travel Survey
    currently underway and Spring 2007 Metrorail
    Passenger Survey
  • An unique opportunity in terms of survey timing

5
Bus Survey Issues
  • Survey data collected on WMATA Regional Bus Route
    needs to be accurate and of very high quality for
    subsidy allocation purposes
  • Planners and modelers would like to have very
    detailed information about bus riders and their
    trip patterns
  • Long, complicated survey forms asking sensitive
    questions, like household income, can diminish
    survey response and data quality

6
TPB Staff Recommendations
  • Amend the FY 2008 UPWP to add 2008 Metrobus
    Survey and Supplemental On-Board Bus Survey
  • WMATA would transfer 750,000 in funding from
    their FY 2008 budget to TPBs 2008 UPWP Budget
  • Reprogram 375,000 in FY 2008 UPWP funds
    currently budgeted for the Household Travel
    Survey and WMATA Technical Assistance for
    Supplemental On-Board Survey
  • Conduct WMATAs 2008 Metrobus Survey and the
    Supplemental On-Board Survey as a single contract
    procurement managed by TPB staff
  • Evaluate impact of questionnaire length and
    content on survey response and data quality in a
    survey pre-test

7
On-Board Bus Survey Planning Assumptions
(Metrobus)
  • TPB staff with assistance from WMATA will develop
    the sampling plan for the survey
  • WMATA regional and non-regional weekday bus
    routes will be surveyed by contractor hired by
    TPB staff
  • Survey will be designed to provide WMATA staff
    with the high quality data needed for subsidy
    allocation
  • An income question will be included on the long
    version questionnaire in the survey pre-test
  • WMATA staff will approve the survey design and
    final questionnaire used on regional and
    non-regional Metrobus routes

8
On-Board Bus Survey Planning Assumptions (Local
Bus Systems)
  • Weekday bus routes on the following systems will
    be surveyed
  • Prince Georges County (The Bus)
  • Montgomery County (Ride On)
  • Frederick County (TransIT)
  • The City of Alexandria (Dash)
  • Arlington County (Art)
  • The City of Fairfax (Cue)
  • Fairfax County (Connector)
  • Prince William County (PRTC OmniRide, OmniLink)
  • Loudoun County (LC Transit)
  • Survey data collected in WMATA and supplemental
    local bus on-board surveys will be shared with
    MTA and data collected in MTA commuter surveys
    will be incorporated into TPBs regional transit
    database

9
On-Board Bus Survey Planning Assumptions (Local
Bus Systems)
(cont)
  • TPB staff with assistance from local agency staff
    will develop the sampling plan and questionnaire
    for each local bus system
  • Survey questionnaire will include same core
    questions that are on 2008 WMATA Metrobus survey
  • Local agency staff will approve the survey design
    and final questionnaire used on their bus system
  • Survey contractor hired by TPB staff or
    contractors already under contract to local
    transit will conduct on-board survey

10
Proposed Schedule
  • Review of UPWP Amendment by TPB Technical
    Committee Nov 2rd
  • TPB Action on UPWP Amendment Nov 14th
  • Issue RFP Nov 15th
  • Select Contractor Dec 19th
  • Start Contract January, 2008
  • Survey Pre-Test Early March, 2008
  • Conduct Survey April May, 2008
  • Data Delivery June, 2008