Title: Evaluating Investment Projects
1Chapter 8
- Evaluating Investment Projects
Shapiro and Balbirer Modern Corporate Finance
A Multidisciplinary Approach to Value
Creation Graphics by Peeradej Supmonchai
2Learning Objectives
- Describe capital budgeting as a management
process and its integration into a companys
strategic plans. - List ways in which projects can be categorized.
- Calculate a projects NPV and IRR and use these
measures to make investment decisions. - Explain the similarities and differences between
the net present value (NPV) and internal rate of
return (IRR) method, and discuss why NPV is the
preferred criterion for making investment
decisions.
3Learning Objectives (Cont.)
- Indicate the problems in using non-discounted
cash flow techniques such as payback and
accounting rate of return to make capital
budgeting decisions. - Describe the use of capital budgeting techniques
in practice and explain why managers use other
methods than NPV to make investment decisions. - Indicate how the equivalent annual cost method
can be used to evaluate projects with different
economic lives.
4Capital Budgeting as a Management Process
- Development of a strategic plan
- Generation of potential investment opportunities
- Estimation of a projects cash flows
- Acceptance or rejection
- Project post-audit
5Classification of Investment Projects
- Size
- Type of Benefit Expected
- By Degree of Dependence
6Classification by Benefit Type
- Cost Reduction
- Expansion Project
- New Product Introduction
- Mandated Projects
7Classification by Degree of Dependence
- Independent Projects
- Mutually Exclusive Projects
- Contingent Projects
8Net Present Value (NPV) Decision Criterion
- Calculate the present value of the expected cash
flows from an investment using an appropriate
discount rate. Subtract from this the present
value of the initial net cash outlay for the
project to get the NPV. If the NPV is positive,
accept the project. If it is negative, reject it.
If two projects are mutually exclusive, choose
the one with the highest NPV.
9Mathematical Representation of NPV
- Where
- St the cash flow in time period t
- I0 the initial investment outlay in time
zero - k the required rate of return on the
project - N the projects economic life in periods
10Calculating A Projects IRR-An Example
- Quickie Enterprises is considering the
construction of a microprocessor plant costing
400 million. Cash flows will increase by 10
million a year from 100 million in the first
year to 140 million in five years. At the end
of 5 years, the plant will be obsolete and have
no value. Whats the plants NPV if Quickies
required rate of return is 12 ?
11Calculating A Projects NPV- An Example
- Quickie Enterprises Microprocessor Plant
- Cash Flows in million
- Year Cash Flow PVIF_at_12 Present Value
- 0 -400 1.0000 -400.00
- 1 100 0.8929 89.29
- 2 110 0.7972 87.69
- 3 120 0.7118 85.41
- 4 130 0.6355 82.62
- 5 140 0.5674 79.44
- NPV 24.45
12Internal Rate of Return (IRR) Decision Criterion
- The IRR is the discount (or interest) rate that
equates the present value of the cash flows with
the initial investment. If a projects IRR
exceeds the required rate of return accept it
otherwise reject it. If two projects are mutually
exclusive, choose the investment with the highest
IRR.
13Mathematical Representation of IRR
- Where
- St the cash flow in time period t
- I0 the initial investment outlay in time
zero - N the projects economic life in periods
-
14Calculating A Projects IRR- An Example
- Quickie Enterprises Microprocessor Plant
- Cash Flows in million
- 100 110 120
130 140 - 400
- (1IRR) (1IRR)2 (1IRR )3 (1IRR )4
(1IRR )5 - IRR 14.30
15Similarities between NPV and IRR
- Both are DCF techniques that focus on the amount
and timing of a projects cash flows. - Both can accommodate differences in risk by
adjusting the projects required rate of return. - Both give the same accept-reject decision for
independent projects.
16Differences between NPV and IRR
- NPV is an absolute measure of project worth IRR
measures the return per dollar invested. - NPV assumes the cash flows are reinvested at the
required rate of return IRR assumes the cash
flows are reinvested at the IRR. - The NPV is unique for a given required rate of
return with an unconventional cash flow pattern,
there may be multiple IRRs.
17NPV Profile
- The NPV profile is the relationship between the
NPV of a project and the discount rate used to
calculate that NPV. Since the IRR is the discount
rate that makes a projects NPV zero, the NPV
profile also identifies a projects IRR.
18Graphical Illustration of the NPV Profile
19Payback Period
- Length of time it take a projects cash flows to
recover its initial investment. - Projects whose paybacks are shorter than some
maximum cutoff period are accepted those with
longer paybacks are rejected. - Under the payback method, projects with shorter
payback periods are preferred to longer ones.
20Limitations of the Payback Method
- Ignores the time value of money.
- Does not consider cash flows beyond the payback
period. - No connection between the maximum acceptable
payback period and shareholder required rates of
return.
21Accounting Rate of Return (ARR)
- The accounting rate of return (ARR) is the ratio
of the average after-tax profits to the average
book value of the investment.
22Limitations of the ARR
- Ignores the time value of money
- Based on accounting profits, not cash flow
- Difficult to establish target rates of return
23Capital Budgeting in Practice
- Most large firms use either IRR and/or NPV for
making decisions - IRR appears to be more popular than NPV
- Payback is used heavily as a secondary method