Capital Projects - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Capital Projects

Description:

Capital outlay projects include new construction, alterations, and additions of ... State and non-state projects submitted annually on the 5-year Capital ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 27
Provided by: karen98
Category:
Tags: capital | projects

less

Transcript and Presenter's Notes

Title: Capital Projects


1
Capital Projects
  • Building an Understanding

2
Capital Projects
  • What is a capital project?
  • Capital projects classifications.
  • What drives campus development?
  • What is the process for getting a project
    approved and underway?
  • How long does it take?
  • What to remember.

3
What is a Capital Project?
  • Capital outlay projects include new construction,
    alterations, and additions of existing structures
    or infrastructures.
  • Governed by state laws and CSU Policies
  • Public works policies and practices apply,
    including the requirement to pay prevailing
    wages.
  • Facilities Planning under the VP AFD has
    responsibility for administering all campus major
    capital outlay projects on behalf of the Trustees
    and the State of California.

4
Capital Projects Classifications
  • State Funded capital projects
  • Non-State Funded capital projects
  • Hybrid projects
  • Include both state and non-state funding
    components

5
Capital Projects ClassificationsState Funded
Capital Projects
  • Funded by appropriations of state tax revenues or
    other special legislative appropriations
  • Categorized as capacity and non-capacity space
  • Capacity space generates FTES capacity
  • Non-capacity space is utilized for offices, lab
    prep, etc. and does not generate FTES capacity

6
Capital Projects Classifications Non-State
Funded Capital Projects
  • Projects funded from donations, state enterprise
    funds, e.g. housing, parking, etc., and auxiliary
    funds (Foundation)
  • Do not generate FTES capacity
  • Do not generate facility operating funds, e.g.
    utilities, maintenance, etc.

7
Capital Projects Classifications Hybrid capital
projects
  • Project design may include capacity and
    non-capacity state space AND utilizes non-state
    funding for space types not funded by the state
    or enhancements to state funded space, such as
    research space, larger lab than formula allows,
    more administrative space, etc.

8
What Drives Campus Development?
  • Campus Master Plan
  • Links the physical requirements of academic
    programs and auxiliary activities both State and
    Non-state.
  • Shows existing and anticipated facilities
    necessary to accommodate a specified enrollment
    at an estimated target date.
  • Website
  • http//www.facilities.calpoly.edu/masterplan/maste
    rplan.htm

9
What Drives Campus DevelopmentCampus Master Plan
  • Approved in March 2001
  • Set the course for construction over the next 20
    years.
  • Developed long range enrollment predictions and
    assigned enrollment growth to each college.
  • Established the priorities for state funded
    capacity and non-capacity space.

10
What Drives Campus Development Physical Master
Plan
  • Describes the general location of each project on
    campus.
  • State and non-state projects submitted annually
    on the 5-year Capital Improvement Program to the
    CSU must be included on the physical master plan.
  • If a project is not included in the Master Plan,
    Facilities Planning must submit a Master Plan
    amendment for approval.
  • Campus Master Plan Committee
  • Campus Planning Committee
  • CSU Board of Trustees

11
The ProcessState Capital Projects
  • Requests are based on enrollment, capacity,
    utilization data, and on the requirements of each
    academic or support program.
  • Campus submits a complete project program for the
    building including room types, configurations,
    square footage and cost estimates.
  • Time period between legislative approval of
    project and funding is approximately 18 mos.

12
The Process State Capital Projects
  • CSU system total capital outlay budget is
    approximately 350 million per year. Many
    projects are approved through the process but are
    not funded due to lack of budget availability.
  • Cal Poly competes with the other CSU campuses for
    a share of the budget.
  • Non-state sources can have some influence on the
    timing of state funding relative to other CSU
    projects.

13
The Process State Capital Projects
  • Constraints
  • State projects must conform to State University
    Administrative Manual (SUAM) space guidelines,
    e.g. faculty office size, lecture room space,
    etc.
  • Limited state funding.
  • Time lag between planning estimates,
    appropriation of funds, and bids.
  • Budget Act establishes time periods in which
    project funding must be encumbered and expended.
  • Unexpended funds revert to the State of
    California.
  • Voter approval of a bond issue.

14
The Process Non-State Capital Projects
  • Though Non-State capital projects have fewer
    constraints than state projects, funding of these
    projects adds a level of complexity.

15
The Process Funding a Non-State Project
  • Funding constraints
  • University cannot borrow funds
  • University may not use Support appropriations,
    i.e. the General Fund for capital outlay
  • Only borrowing vehicle available is the SRB
    program applicable to revenue-generating
    projects.
  • Auxiliary may loan or provide guarantees of
    funding but their capacity to do so is limited.

16
The Process Non-State Project Development
Step 1
  • Initial planning process by AFD with client
  • Establish expectations.
  • Develop a project description and scope.
  • Recommend a project delivery method.
  • Develop a project timeline and critical path.
  • Prepare a funding plan that meets critical path.
  • Check for consistency with mission, campus master
    plan and refer to campus committees as needed.

17
The Process Non-State Project Development
Step 2
  • Develop a preliminary project budget
  • Identify initial design funding
  • Preliminary Design Effort
  • Building Programming
  • Conceptual Design
  • Schematic Design
  • CEQA
  • Reconcile budget to cost estimates at each design
    phase

18
The Process Non-State Project Development-Step
2 (cont.)
  • All project funding must be in place to proceed
    through campus CSU approvals.
  • SRB financing packages will be developed by
    Assoc. VP of Finance for approval by the CSU.
    SRB financing packages must be submitted to the
    Chancellors Office a minimum of 8 weeks prior to
    the BOT meeting.

19
The Process Non-State Project Development
Step 3
  • Schematic CEQA approvals
  • Master Plan Committee
  • Campus advisory committees as necessary
  • President
  • Campus Planning Committee
  • Chancellors Office staff
  • Board of Trustees

20
The Process Non-State Project Development
Step 4
  • Final Design Documents
  • Complete Working Drawings
  • Reconcile cost estimates at 50 and 100 complete
    drawings to budget
  • Adjust funding plan, as needed
  • Bid Project (if Design/Bid/Build delivery)
  • Adjust funding plan, as needed
  • BOT approval of SRB financing, if applicable

21
The Process Non-State Funded Projects
  • Non-state funded projects have more flexibility
    in space configurations if non-scheduled space.
  • Non-state projects require that adequate funds
    are available to address cost increases, market
    conditions or other unknowns.
  • Project schedule cannot be maintained without
    adequate funding.
  • No BOT approvals without funding

22
The Process Funding a Hybrid Project
  • Non-State funding component must be in place at
    the time the state appropriates its share of the
    project funds.
  • Ensures project can be completed within the
    States prescribed timeframe.

23
Capital Projects How long does all this take?
  • Typical non-state projects require 3-5 years from
    the Initial Planning Meeting to project
    completion.
  • Each project varies due to the complexity of the
    building program.
  • State projects have the added uncertainty of
    state funding availability and the passing of
    bond measures.

24
What to remember
  • Administration Finance facilitates campus
    physical development and is always the first
    point of contact for any project idea.
  • Building can be exciting but requires a
    commitment of resources
  • Time is money

25
What to remember
  • Construction is not a science and costs fluctuate
    in response to market conditions.
  • For state projects this means adjustments to
    project scope.
  • For non-state project this means adjustment to
    scope or additional funding.
  • Be prepared to be flexible and compromise.
  • Non-state projects do not generate state funding
    to cover operating costs.

26
Questions? Contact
  • Bob Kitamura, Director
  • Facilities Planning and Capital Projects
  • Email bkitamur_at_calpoly.edu
  • Phone 756-2581
  • Karen Webb, Asst. Vice President
  • Administration and Finance
  • Email kwebb_at_calpoly.edu
  • Phone 756-2661
Write a Comment
User Comments (0)
About PowerShow.com