Title: 3rd Market Dress Rehearsal Brief


1
3rd Market Dress Rehearsal Brief
  • 2 May 2002

2
Countdown
Jarrow Count Down To Go Live as at 2nd May
2002 Just 11 Total Days 7 JSE Business Days
Remaining
3
A Special Note of Thanks
  • The JSE would like to thank all users for the
    effort and time taken to participate in both the
    First and Second Dress Rehearsal
  • Overall the 2nd Dress Rehearsal went extremely
    well and the participation and adequate
    preparation by all Users was an important
    contributor to this success
  • The Dress Rehearsal met the objectives in
    relation to allowing for
  • Practice
  • Highlighting key issues
  • Identifying readiness for Go Live
  • The purpose of these Dress Rehearsals is to build
    user confidence in their ability to participate
    effectively in the new environment after Go Live
  • It is in the interest of both the market and the
    users to participate in the remaining Dress
    Rehearsal in order to achieve market readiness
    and build market confidence to Go Live

4
Project Timeline
2001
2002
June
Aug
Oct
Sept
Feb
Jan
Dec
Nov
July
Mar
April
May
4/6/01
3/8/01
JSE Design
19/10/01
6/8/01
JSE Development
4/6/01
19/10/01
JSE Build and Test of
Technical
Infrastructure
22/10/01
JSE/LSE Prepare and Execute
Integration Test

18/01/02
4/6/01
3/8/01
9/11/01
Prepare and Execute Business Operations Proving
12/4/02
21/1/02
Design of JSE Front End Solution
Build and Test of JSE

Front End Solution
2/03/02
LCON
16/03/02
Design, Build and Test of Data Vendor / Member


Front End Solution
LCON
27/6/01
18/01/02
30/03/02
LCON
13/4/02

1st DR
27/04//02

2nd DR
31/03/02
18/7/01
27/6/01
4/6/01
JSE / LSE Draft Spec
JSE / LSE Final Spec
Prepare and Execute Customer Test
26/11/01

4/05/02
3rd DR
Go-live
We are here!
5
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

6
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

7
Objectives
How were the previous Dress Rehearsal Objectives
met?
8
Objectives
How were the previous Dress Rehearsal Objectives
met?
9
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

10
Principles
How were the previous key Dress Rehearsal
Principles met?
11
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

12
Deployment Timeline
April
May
March
3 Apr
DR 1 Brief (JHB)
2 May
3rd DR Brief
LCON 1
4 Apr
DR 1 Brief (CT)
Sat2 Mar
Dress Rehearsal 3
Sat/ Sun4-5 May
JSE LSE Internal Dress Rehearsal
Sat6 Apr
Final Cut-Over Brief (JHB)
8 May
LCON 2
Sat16 Mar
Sat/ Sun13-14 Apr
Dress Rehearsal 1
Go-live
13 May
17 Apr
DR 2 Brief (JHB)
JSE LSE ASR Test
17 May
President Mbeki launch
Sat23 Mar
18 Apr
DR 2 Brief (CT)
Commemorative insert in Star and Beeld
20 May
Dress Rehearsal 2
Sat/ Sun27-28 Apr
LEGEND LCON Live Connectivity Testing DR Dress
Rehearsal CONT Contingency ASR Alternate Site
Recovery (LSE) Internal External
Tests completed
LCON 3
Sat30 Mar
JHB Brief
CT Brief
JSESETS Launch
13
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

14
Lessons Learnt
Technical Key Areas of concern -
15
Lessons Learnt
Technical Key Areas of concern (continued)-
16
Lessons Learnt
Other key issues-
  • Lack of testing by ALL Users in test environment
    post conformance LCON
  • Lack of user understanding of principal / agency
    rules and how to apply these to the various trade
    types e.g. OP principal trade
  • Not all users attended and clearly understood
    conceptual trading model training Users should
    undertake refresher training on their own using
    the conceptual training tool on the JSE website.
    CDs available in toolkits
  • Lack of accurate problem reporting to Customer
    Support, users to provide detailed information
  • Incorrect user contact details supplied to JSE
    to improve communications JSE requires correct
    contact details
  • Users should have print-outs of all configuration
    files to assist with problem resolution

17
Lessons Learnt
  • Level of invalid data was extremely high. Trader
    reports were sent with results, please confirm
    these. ALL RST trader IDs not used during dress
    rehearsals will be deleted on 10th May and users
    will need to re-write the JSE exams to gain RST
    status. This remains the brokers responsibility
  • Invalid trader IDs submitted on orders and trade
    reports. ONLY JSE assigned RST codes are valid
    5 numeric digits (as per existing JET logon)
  • Invalid BDA client accounts submitted on ALL
    orders and trade reports. These should be padded
    with leading zeros. e.g. if BDA client account is
    23570, then 0023570 to be submitted. Failure to
    do this results in excessive back office
    administration on BDA to correct re-allocations
  • Incorrect use of trade types on reported trades.
    Trade types apply across all segments, members
    must ensure they submit valid trade types per
    market. E.g OP only valid in segments ZA01,
    ZA02, ZA03
  • Orders carried forward to next day - some members
    complained that their orders were not carried
    forward to the next day. Most orders were hit,
    users should test this in CDS

18
Lessons Learnt
  • InfoWiz Key Issues-
  • User applications can and should automatically
    re-request missed messages intra day. No need to
    notify Customer Support of this.
  • User Applications should send one request for a
    range of missed messages i.e. if messages 2,3,4
    and 6 are missing this should result in 2
    requests not 4
  • Users applications should be built so that
    re-request data is satisfied by either the IRI
    connection or via the broadcast interface
  • General-
  • CDS reference data re-synchronisation. Reference
    data, SENS messages and Index data are all
    updated. Period rules in progress
  • Unfacilitated playtime on TALX at the JSE may be
    booked through the JSE online booking tool.
    Playtime is available from Mon 06 May Fri 10
    May from 13h00 16h00 pm

19
Dress Rehearsal Improvements
  • Users were better prepared for this test
  • Extranet message usage was effective
  • Account manager concept was well received
  • Effective use of email groups
  • JSE Infrastructure stable
  • Access for all JSE staff to logging tool helped
    resolve issues timeously

20
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

21

3rd Dress Rehearsal Participation
  • MANDATORY Participation is required during the
    next Saturday live trading day simulation from -
    (except for users who have passed 2 tests)
  • All JSE and NSX Equities traders 100
    participation in all scheduled DR tests
  • All relevant user IT support staff.
    (e.g.networks, applications, PC support etc)
  • All information Users who will be
    subscribing to InfoWiz
  • All basket trading and client order entry
    applications
  • All other user applications interfacing with
    their front-end applications
  • The test starts at 10h30 and ends at 18h00
  • The traders must participate from 12h00
    15h30
  • All primary and backup(on site) terminals
    must be tested
  • NOTE From go live, members accept full
    responsibility for all order and trades submitted
    by their traders. Dress Rehearsals facilitate
    testing in a live-like environment.

Checklists must be in Saturday evening after
Dress Rehearsal. Fax (011) 520 8432 / 8022.
These will be accepted electronically via Email.
22
Responsibility
USERS are responsible for ensuring
  • They participate throughout the test between
    10h30 18h00 on all the test days
  • Full participation from all traders (12h00
    15h30)
  • Full participation from all relevant User IT
    support staff (e.g Networks, applications, PC
    support etc)
  • Full support from relevant software providers
  • Identifying the responsible person per User to be
    used by the JSE as the key contact person. Users
    must provide the contact details to the JSE
    helpdesk by Thursday (2 May) by close of business
    today (011) 520-7309
  • All Users follow the test plan and schedule -
    PLEASE READ TEST PLAN/SCHEDULE!!!!
  • ONLY realistic prices and order details are used
    for all orders failure to do so, will result in
    unnecessary disruptions and potential delays to
    the test schedule. The JSE will be monitoring
    all test data and this behaviour will result in a
    User Dress Rehearsal FAIL!!!!!
  • Staff are aware of problem escalation procedures
    to ensure problems logged with the correct
    helpdesk. E.g Front-end queries are logged with
    software providers not the JSE
  • All problems are reported and logged with the JSE
    Customer Support (011) 520 7777

23
Responsibility
USERS are responsible for ensuring (cont..)
  • All user test data is removed from their
    production environments after the Dress
    Rehearsals
  • All traders have attended conceptual training
    prior to the Dress Rehearsals
  • All traders have attended front-end training
    prior to the Dress Rehearsals
  • All JSE test scripts and procedures are
    downloaded from the JSE web prior to the test
  • That all Users are informed this is NOT a stress
    test and that attention should be given to
    functionality and data integrity. Users are
    responsible for ensuring data accuracy
  • Members make use of the JET testing on Sunday to
    ensure they can continue with trading the Monday
    after each test
  • Ensuring Users keep track of all actions in the
    event of a problem to assist with problem
    determination
  • Relevant monitoring of their infrastructure and
    related applications is performed during the
    dress rehearsals

24
Responsibility
JSE is responsible for ensuring
  • Support will be through the JSE Customer Support
    helpdesk
  • All queries are allocated a reference number
  • Ensure all queries are addressed and resolved
  • First line support for all TALX related queries
  • Monitoring of all test data and Users to ensure
    compliance with the test schedule and scripts
    (including errors generated by Users)
  • Monitoring errors generated by users
  • Test schedule execution and adjustments as
    required watch the market messages for
    adjustments
  • Evaluate Dress Rehearsal participation and
    success and GO LIVE readiness
  • Contact Number during test
  • JSE Customer Support (011) 520-7777

25
Problem Reporting
To assist with effective problem resolution,
Users must provide accurate details when
reporting the query/problem to the JSE helpdesk -
  • Is it a JSE SETS or InfoWiz query?
  • USAP Code faster resolution and tracking with
    the LSE
  • Is it your primary/secondary/DRP connection?
  • Which Front-End Software?
  • Which Segment and Instrument the query relates to
  • Provide order code and trade code where possible
  • Time of order entry / trade execution
  • Order details namely, Order type, price, volume
  • Your name and contact number for feedback

This is what will be required when reporting
problems once LIVE.
26
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

27
Dress Rehearsals Schedule
Proposed schedule - under discussion
2
Systems Startup Ref Data Download
Normal Trading Schedule
1
SystemsShutdown
JSE Batch Processing
Saturday
Pre Open
MktClose
11h00
18h00
12h00
15h30 Trader Test end
Checking of Batch Results
2
Sunday
08h00
Software VendorFeedback
Internal JSE/LSE Checkpoint
JSE Prep Session
12h00
08h30
11h00
09h30
SystemsStartup RefData Download
Normal Trading Schedule (partial)
1
NOT AVAILABLE
ContinuousTrading
Pre-Open
06h00
08h30
10h00
Colour Legend
  • Trading Schedule will be condensed to fit into
    shorter window (details on next slide).
  • Batch processing will be done during the 3rd
    Market Dress Rehearsal (4th May).
  • Intraday checkpoints with Users will be indicated
    in the detailed schedule.
  • All times reflected are SA standard time (SAST)

JSE/LSE Internal
Notes
JSE User Participation
JSE User Feedback
JSE/LSE Checkpoint
NOT AVAILABLE
28
Test Period Schedule
ZA01
ZA02
ZA03
ZA11
12h00
12h05
12h30
14h00
14h30
14h40
14h50
15h00
15h15
15h30
16h40
16h50
17h00
18h00
29
Test Schedule Saturday
Certain period names may differ depending on
which segment or sector used in NOTE The early
trading closure will apply to one segment only
30
Test Schedule Saturday
Continuous Trading Phase

Halt Early Close 1 segment
14h00 14h30
15h00 (move to runoff for ZA02)
31
3rd Market Dress Rehearsal Brief
Agenda
  • Objectives
  • Principles
  • Deployment Timeline
  • Lessons Learnt
  • Participation and Responsibility
  • Test Schedule
  • Other
  • Questions

32
JSE Systems NOT Available
On these dates no JSE Applications are available
for NORMAL production activity
33
Mapping of Success Guidelines Communicated
  • User ability to connect and trade
  • 100 interactive participation throughout the
    test period
  • No excessive re-requests for data during tests
  • Adherence to the test schedule and conditions
  • Completed and signed test checklists/results
    returned to the JSE
  • Completed and signed declaration that
    functionality and data integrity was intact
  • Key responsible person identified and
    communicated to JSE prior to test
  • Adherence to realistic order details and prices
  • Adherence to normal trading and volume activity
    (NB!! NOT a stress test)
  • All user participation
  • 100 interactive participation throughout the
    test period
  • Number of traders logged on
  • Order and trade summary of all client
    application trader ids (AOP/AOF)
  • Order and trade data generated per trader
  • Limited system errors generated by Users in
    system logs
  • Error messages generated per user
  • All problems logged with JSE Help Desk before end
    of each test day

Connectivity
Test Preparation and Completion of Test
Execution
Suitability of Data Submitted
Level of Participation
Message Success
Used for Information Purposes Only
34
Data for Dress Rehearsal
  • Test scripts for the next Dress rehearsal
    will have minor amendments
  • applied. These are already published on
    the JSE web
  • As JSE business processes have kicked in,
    JSE reference data will be as at 3 May
  • Users must do a FULL download on all dress
    rehearsals and the morning of go live
  • Instruments (incl. warrants) and ex-markers
    expiring before 13 May 2002 have been
  • excluded
  • On the 3rd Market Dress Rehearsal, the
    following dates will be reset to 4 May 2002
  • - instrument effective date
  • - participant effective date
  • Instruments will be suspended by the LSE as
    at 2 May 2002
  • Closing prices as at Thursday 2 May will be
    used for the test users to ensure
  • these have been loaded to the front-ends
    prior to the test or provided traders with
  • hand-outs. This is only a problem during
    the open auction
  • www.jse.co.za / JSE Initiatives / JSE
    Trading and Information Systems
  • (Will be there Friday 3 May under the
    Market Dress Rehearsal Documentation bullet)

35
Other
  • FTSE will NOT be participating and therefore
  • No Index data will be published
  • No FTSE/JSE index series download will be
    available
  • 3rd Dress Rehearsal Outputs available to users
    from 21h00 on Saturday evening-
  • BDA dissemination will be available as part of
    the Dress Rehearsal
  • JSE EOD dissemination will be available
    (excluding FTSE Fredd Files)

36
Questions