Title: Simple Performance Tests for HotMix Asphalt Concrete


1
Simple Performance TestsforHot-Mix Asphalt
Concrete
  • Ramon Bonaquist, P.E.
  • Chief Operating Officer
  • Advanced Asphalt Technologies, LLC

Simple Performance Test
2
What Is It?
  • Test That Indicates How Mix Will Perform
  • Rutting
  • Cracking

1. Identify Inferior Mixes 2. QC/QA
Operations 3. Structural Design
3
Lots of Possibilities
  • Gyratory Compactor
  • Rut Testers
  • Asphalt Pavement Analyzer
  • Hamburg
  • Fundamental Tests
  • Uniaxial/Triaxial
  • Shear
  • Indirect Tensile
  • Many Show Promising Correlation With Pavement
    Performance Using Limited Data Sets

4
NCHRP/FHWA Research
  • To Recommend a Fundamental Based but Simple
    Performance Test(s) to Support of the Superpave
    Volumetric Mix Design Procedure
  • Started 1997 FHWA Leadership
  • Moved to NCHRP in Late 1998
  • Continue Through Early 2003

5
Simple Performance Test Requirements
  • Absolute Requirements of Test
  • Compliment Superpave Volumetric Design
  • Use Gyratory Compacted Specimens
  • High Correlation to Rutting/Fracture
  • Identify Inferior Mixes
  • Preferred Requirements of Test
  • Tied to Structural Design
  • Adaptable to QC/QA

6
Two Major Projects
  • NCHRP Project 9-19
  • Recommend Test(s)
  • Develop Protocol(s)
  • Develop Criteria
  • Validate Criteria
  • NCHRP Project 9-29
  • Equipment Specs
  • Procure First Articles
  • Evaluate First Articles
  • Revise Specs

7
Recommend Tests
  • Identify Existing Test Methods
  • Correlation Study
  • Relate Test Parameters to Observed Performance
  • Well Documented Experimental Sections

8
Sites for Correlation Study
MnRoad
WesTrack
FHWA-ALF
9
(No Transcript)
10
Recommend Tests
  • Identify Existing Test Methods
  • Correlation Study
  • Relate Test Parameters to Observed Performance
  • Well Documented Experimental Sections
  • Select Candidate Tests

11
Candidate Tests
  • Dynamic Modulus
  • Rutting
  • Cracking
  • Creep Test
  • Rutting
  • Repeated Load Test
  • Rutting

12
Dynamic Modulus Test
  • Rutting
  • Min E at High Temp
  • Fatigue Cracking
  • Max E at Intermediate Temp

13
Creep Flow Time Test
  • Rutting
  • Min FT at High Temp

14
Repeated Load Permanent Deformation Test
  • Rutting
  • Min FN at High Temp

15
Advantages
  • Dynamic Modulus
  • Used For Structural Design in 2002 Design Guide
  • Addresses Rutting and Cracking
  • Optimization
  • Creep
  • Simple Test Equipment
  • Minimal Training
  • Repeated Load
  • Potentially Best Simulation of Actual Loading

16
Disadvantage
  • Specimen Size
  • 100 mm Diameter by 150 mm High
  • Smooth Parallel Ends (Sawed)
  • Sawed and Cored From Over-Height Gyratory
    Specimens
  • Some SGC Can Not Produce Tall Specimens
  • Needed to Ensure Fundamental Properties

17
Project 9-19 Criteria Development
  • Use Models Proposed in Project 1-37A for the 2002
    AASHTO Design Guide
  • Account for
  • Climate
  • Traffic Level
  • Structure
  • Test at Effective Pavement Temperature
  • Minimum or Maximum Values
  • Traffic Level
  • Pavement Structure
  • Completed in Fall 2002

18
Project 9-19 Validation
  • Criteria Will Be Validated
  • Not the tests
  • In-Service Pavement Data
  • 50 LTPP and Other Test Sections
  • Completed by the End of 2002

Fatigue Cracking
Rutting
19
Equipment Specifications
  • Automated Specimen Fabrication Equipment
  • Creep / Flow Time Test
  • Repeated Load / Flow Number Test
  • Dynamic Modulus Test

20
Specification Development
Draft Equipment Specs Cost Estimate
21
First Article Simple Performance Test System
  • EnduraTec
  • Instron
  • Interlaken
  • Shedworks

22
Project 9-29 First Article Simple Performance
Test Systems
  • Tests
  • Flow Time
  • Flow Number
  • Dynamic Modulus
  • Temperature Range
  • 20 to 60 C
  • Confining Pressure Range
  • 0 to 210 kPa

23
Project 9-29 First Article Simple Performance
Test Systems
INTERLAKEN
SHEDWORKS
24
Project 9-29 First Article Simple Performance
Test Systems
25
Shedworks
26
Shedworks
27
Shedworks
28
Shedworks
29
Interlaken
30
Interlaken
31
Project 9-29 First Article Specimen Fabrication
System
  • Pine
  • Shedworks

32
Project 9-29 First Article Specimen Fabrication
Equipment
BLADES
CHUCK
CORE BARREL
33
Summary- Simple Performance Test Work Completed
  • Three Candidate Tests
  • Dynamic Modulus
  • Flow Number
  • Flow Time
  • Detailed Draft Protocols
  • Detailed Equipment Specifications
  • First Article Devices
  • Simple Performance Test System (25 k to 45 k)
  • Automated Specimen Fabrication System (12 k)

34
Summary - Simple Performance Test Work in Progress
  • Criteria Development
  • November, 2002
  • Criteria Validation
  • End of 2002
  • First Article Evaluation
  • Early 2003

35
Questions ?