Title: California Environmental Quality Act CEQA
1California Environmental Quality Act(CEQA)
2Introduction
- CEQA is Californias most important environmental
laws - A cherished institution, but also one of the most
controversial
3A Little History
- CEQA was adopted by the California Legislature,
and signed into law by then Governor Ronald
Reagan in 1970. - Loosely based on the National Environmental
Policy Act (NEPA), which had been signed into law
by President Nixon several months earlier on Jan
1, 1970.
4What is CEQA?
- Really simple in concept CEQA requires
government agencies to consider the environmental
consequences of their actions before approving
plans and policies or committing to a course of
action on a project. - CEQA requires public agencies to deny approval
for a project if it poses significant adverse
environmental effects when feasible alternatives
or mitigation measures can substantially lessen
the effect.
5Legislatures explanation for enacting CEQA
- Inform government decision makers and the public
about the potential environmental effects of
proposed activities - Identify the ways that environmental damage can
be avoided or significantly reduced - Prevent significant, avoidable environmental
damage by requiring changes in projects, either
by the adoption of alternatives or imposition of
mitigation measures and - Disclose to the public why a project was approved
if that project would have significant
environmental effects. (pub. Res. Code 21000,
21001)
6Seems innocuous enough, doesnt it?
- CEQA does not directly limit development (as does
the California Coastal Act) - CEQA does not mandate environmental clean-up (as
do the Federal Clean Air and Water Acts) - Time tested procedures for complying with CEQA
7Then whats the hub-bub?
- CEQA does require that a development proposal be
accompanied by an analysis listing its
environmental impacts and that, where feasible,
those impacts be mitigated. - Questions of as to the definitions terms such as
Project, Significant Effect, Approval
8The Heart of CEQA
- CEQA requires that public agencies prepare an
Environmental Impact Report whenever the approval
of a proposed project may cause significant
adverse effects or impacts on the environment - A "public agency" is any California state agency,
board, or commission, or any county, local or
regional agency, but not including any state
court or any agency or arm of the United States
government - "project" is any activity undertaken by any
public agency, supported in whole or in part by a
public agency, or requiring approval by a public
agency - A "significant effect on the environment" means a
substantial, or potentially substantial, adverse
change in any of the physical conditions within
the area of the project, including land, air,
water, minerals, flora, fauna, noise, or any
objects of historic or aesthetic significance.
9CEQA is fundamentally a law about process
- At the heart of the process is the requirement
that governmental agencies conduct environmental
reviews especially Environmental Impact Reports
(EIRs)--before approving or disapproving
projects - "project" is any activity undertaken by any
public agency, supported in whole or in part by a
public agency, or requiring approval by a public
agency. - A "public agency" is any California state agency,
board, or commission, or any county, local or
regional agency, but not including any state
court or any agency or arm of the United States
government
10If CEQA is a law about process, how does the
process begin?
- The CEQA process begins with a preliminary review
of the proposal to determine whether CEQA applies
to the agency action, or whether the action is
instead exempt. (California Code of Regulations,
title 14, section 15000 et. seq. (Guidelines))
11- If the agency determines that the activity is not
subject to CEQA, it files a notice of exemption,
and not further action is necessary for CEQA
compliance. - If the agency determines that the activity is a
project subject to CEQA, the agency must prepare
either an EIR, a Negative Declaration or a
Mitigated Negative Declaration.
12Determining if the Activity is Exempt from CEQA
- If it can be said with certainty that a project
will not have a significant effect on the
environment, it is exempt from CEQA review. - Can you think of a project that will not have a
significant effect on the environment?
13Statutory and Categorical Exemptions from CEQA
- CEQA sets out statutory exemptions that limits
CEQAs application to certain types of projects - Example No specific compliance with CEQA is
required for a residential development (of any
size) if the project is consistent with an
earlier zoning, community plan, or general plan
for which an EIR was prepared unless (1) the new
project will have significant effects not
addressed in the earlier EIR (2) substantial new
information shows those effects will be more
significant than those described in the prior
EIR or (3) there are significant impacts
peculiar to the parcel or the project.
14Statutory and Categorical Exemptions from CEQA
- The Guidelines also contain categorical
exemptions that the Secretary of Resources has
found not to have a significant effect on the
environment - Big example approvals which are ministerial in
nature rather than discretionary. Presumptively
ministerial projects include the issuance of
building permits, the issuance of business
licenses, the approval of final subdivision maps,
and the approval of individual utility service
connections and disconnections - The operation, repair, maintenance, or minor
alteration of an existing facility is exempt. - replacement or reconstruction of an existing
facility is exempt - The new construction or conversion of a small
structure is exempt, g.g., construction of an
apartment house with fewer than four units or
construction of a commercial store with an
occupancy load of fewer than thirty persons.
15Limitation on the Categorical Exemptions
- A categorical exemption will not apply if
- There is a reasonable possibility of a
significant effect on the environment due to
unusual circumstances - Significant cumulative impacts from projects of
the same type will result or - Projects will have an impact on a uniquely
sensitive environment.
16Procedures for making an exemption determination
under CEQA or the Guidelines
- There are none! City of Pasadena v. State, 14
Cal. App 4th 810, 819-820 (1993) Assn for
protection of Envtl. Values v. City of Ukiah, 2
Cal. App. 4th 720, 731-732 (1991).
17What can an Agency Do?
- An agency may elect to file a notice of
exemption. Guidelines 15062(a) - If an agency files the notice, it triggers a 35
day statute of limitations for challenging the
project approval on any ground under CEQA. Pub.
Res. Code 21167(d) - If no notice is filed, challenge period runs 180
days following agencys approval.
18So the project doesnt fit into a statutory or
categorical exclusion, now what?
- Prepare an initial Study.
- What is it? A preliminary analysis prepared by
the lead agency (usually the city or county
having primary jurisdiction over the project) to
determine whether an EIR must be prepared, or
whether a negative, or mitigated negative
declaration will be sufficient. Talk about who
really prepares, and what is contained in an
initial study
19Conclusions of Initial Study
- If I.S. concludes that there will not be a
significant effect on the environment, agency can
issue a neg dec. Done with CEQA! - Negative declaration is a written statement from
the agency that an EIR is not required because a
project will not have a significant adverse
impact on the environment.
20Conclusions of Initial Study
- An agency can also issue a mitigated neg. dec.
- A mitigated neg. dec. states that revisions to
the project made or agreed to by the applicant
would avoid potentially significant adverse
impacts, and that there is no substantial
evidence that the project, as revised, will have
a significant effect on the environment.
21Conclusions of Initial Study
- Upon issuance of neg. dec. or mitigated neg.
dec., agency must notify the public that it is
available for review. - The dec. must also be filed with State Clearing
house for review by relevant public agencies
prior to approval. - Agency then may receive and consider comments,
may make changes to mitigation measures depending
on comments. - The agency will then likely file a notice of
determination (starts clock on judicial
challenges to decision)
22Conclusions of Initial Study
- As a general rule, an agency cannot adopt a neg.
dec. or mitigated neg dec., and must prepare an
EIR if it can be argued on the basis of
substantial evidence that the project may have a
significant effect on the environment. - Substantial evidence means enough relevant
information and reasonable inferences from the
available information that a fair argument can be
made to support a conclusion, even though other
conclusions may be reached.
23Preparation of EIR
- Step 1 The Scoping process.
- Agency consults with applicant, other agencies
and the public to determine the scope of the EIR.
24Preparation of Draft EIR
- Following the scoping process, either agency
themselves prepare and draft EIR, or the
applicants consultant prepares an EIR - If the consultant prepares the EIR, the agency
independently reviews, evaluates and exercises
judgment over the document, and issues it raises
or addresses. - Final responsibility to provide an adequate EIR
resides with the lead agency.
25Circulation of Draft EIR
- Upon the completion of a draft EIR, it is
circulated to the public and to public agencies
for review and comment. - After receiving comments, the public agency must
prepare responses to significant issues raised by
the reviewers, and in many instances, will revise
the EIR.
26Final EIR
- Final EIR consists of
- The Draft EIR
- Comments and recommendations received on the
Draft EIR - The responses of the lead agency to the
significant environmental points raised in the
review and consultation process - A list of persons and agencies commenting on the
draft EIR and - Anything else the agency wants to add.
27Final EIR
- The lead agency actually has no duty to make the
final EIR a public document, but usually make it
a point to do so. Note, however, if the Final
EIR contains significant new info is added prior
to certification of the Final EIR, changes, it
must be recirculated. - At least 10 days before certifying a final EIR,
the lead agency must provide any other public
agency that commented on the EIR a written
response to that agencys comments.
28So whats in an EIR anyway?
- An EIR Must contain the following
- A table of Contents or index
- Summary of the proposed action and its
consequences - A project description
- The environmental setting
- An evaluation of the environmental impacts
- Mitigation efforts for the environmental impacts
- Project Alternatives
29Project Description
- The description should extend to the entire
activity that will ultimately result - Must also include reasonably foreseeable future
activities that are consequences of the action
30Evaluation of Environmental Impacts
- Should be prepared with sufficient analysis to
provide decision makers the ability to review
possible environmental consequences
intelligently. - Disagreement among experts does not, by itself,
make an EIR inadequate. - Courts are not really looking for perfection, but
really looking at a complete, good faith effort
in the completion of an EIR. Nonetheless, it
must be responsive to the concerns raised during
the draft EIR.
31Evaluation of Environmental Impacts
- All phases of the project must be considered when
evaluating its impact on the environment
Planning, acquisition, development, and
operation. - The EIR's discussion of environmental impacts
must include relevant specifics of the area, the
resources involved, physical changes, alterations
to ecological systems, changes induced in
population distribution, changes induced in the
human use of the land (including both commercial
and residential development), health and safety
problems caused by the physical changes, and
other aspects of the resource base, including
water, scenic quality, and public services. - Items that must be included
- Significant environmental effects of the proposed
project - Significant environmental effects, which cannot
be avoided if the proposal is implemented - The growth inducing impacts of the proposed
project - Cumulative impacts of the proposed action
- Effects not found to be significant
- Traffic impacts
- Mitigation measures, i.e., measures proposed to
avoid or minimize the significant impacts. - Alternatives to the proposed action
- Inconsistencies with specific plans, general
plans - Organizations or persons consulted in the
preparation of the EIR
32Cumulative Impacts
- Two or more individual effects, that when
considered together, are considerable or that
compound a particular environmental effect. - Thus, an EIR discussion on cumulative impacts
must discuss past, present and any probable
future projects. - Goal is also to avoid the piecemeal effect of
projects.
33Cumulative Impacts
- Not proper to discount cumulative effects merely
because the project contributes to an already
unacceptable condition - But a cumulative impact can be found to be less
than significant if the effects will essentially
be the same with the project as they would be
than without
34Mitigation Measures
- EIR must describe measures to minimize the
projects significant environmental impacts - EIR must also describe any significant
environmental effects that the mitigation
measures will cause.
35Project Alternatives
- A range of reasonable alternatives must be
considered. - Alternative in size, location are common
alternatives considered. - A no project alternative must be considered.
36Project Approval and Findings
- After Final EIR is complete, the agency
determines whether to approve a project - CEQA contains explicit requirements pertaining to
the approval of a project with significant
impacts. For example, all mitigation measures
necessary to eliminate the significant effects of
the project must be incorporated if they are
within the public agency's authority unless both
of the following result if "specific economic,
social, or other considerations make infeasible
the mitigation measures . . . identified in the
EIR" and if the "benefits of the projects
outweigh the significant effects on the
environment."
37Statement of Overriding Considerations
- An agency can approve a project which damages the
environment. - If social, economic or other conditions make it
infeasible to mitigate significant environmental
effects on the project, the agency must adopt a
Statement of Overriding Considerations
38What is the Statement of Overriding
Considerations?
- Although adverse impacts may result, specific
overriding economic, social, legal,
technological, or other situations outweigh the
damage to the projects significant unmitigated
impacts. - Findings must be supported by substantial
evidence in the record
39Project Approval
- The EIR must be certified as completed in
compliance with CEQA - The EIR was presented to the decision makers
within the lead agency, was considered, prior to
approving the project - The EIR must reflect the independent judgment of
the lead agency.
40Notice of Determination
- Must be filed within 5 working days after project
approval - The filing of the notice of determination starts
the 30 day statute of limitations on court
challenges to the approval under CEQA.
41Other Deadlines (Good Luck!!!)
- Initial study 30 days to determine whether an
EIR or negative declaration is required - Notice of Preparation of EIR Other agencies
have 30 days from NOP to review and comment. - Convening of scope and content meetings 30 days
- Public Review period for draft EIR 30 to 60
days - Notice of Completion of EIR Generally an EIR
for a project must be completed within 1 year
(good luck!) - Approval or disapproval of an EIR based on an EIR
(a private project must be approved or
disapproved within 180 days of the certification
of an EIR) - Notice of Determination Starts 30 day statute
of limitations for filing suits.
42Judicial Challenges to Agency Actions
- 30 day clock starts upon notice of determination
- In certain situations, the statute of limitations
is increased to 180 days for example, if no
posting of notice of determination or if, for
example if subsequent changes to a project were
not discussed in an EIR