Title: Boiler Safety
1 2Safety Appurtenances In Boiler
- Pressure gauge Test connection
- Safety Valves (Drum Super-heater)
-
- Blow down valve
- Drum Level Water Gauge Glasses
- Stop Valve in Steam line
- Stop Check Valves in Feed Line
3Necessity of Safety valve
- It prevents the boiler pressure from going
above a safe pre-determined pressure, by opening,
to allow the excess steam to escape into the
atmosphere when the set point is reached. This
guards against a possible explosion from
excessive pressure. - Each Boiler must have one S.V, the minimum
size being a ½ inch valve for miniature boilers
a ¾ inch valve for others. A Boiler with more
than 500 Sq.ft of heating surface an electric
boiler with a power input of over 500 KW should
have two or more Safety valves.
4Capacity of Safety valve
- In any case , SV capacity must be such as to
discharge all the steam the boiler can generate
without allowing pressure to rise more than 6
above the highest pressure at which any valve is
set in no case more than 6 above the maximum
allowable working pressure. -
- All the Safety valves used on Steam boilers
must be of Direct Spring Loaded type.
5Definition of Safety Relief valve
- It is an automatic pressure-relieving device
actuated by the pressure upstream of the valve
which opens by pop action, with further increase
in lift of the valve, when pressure increases
over popping pressure. - It thus combines the feature of pop action
further lift with pressure increase.
6Terminology of Safety Relief valves
- Blow down
- It is the difference between the opening
closing pressure of - the Safety valve.Ex- A safety valve that pops
at 200psi seats - at 195 psi has a blow down of 5 psi.
- Code rule for determining SV relieving capacity
- SV capacity on a boiler must be such that the
SV or valves will - discharge all the steam that can be generated
by the boiler - (this is assumed to be the max. firing rate)
without allowing the - pressure to rise more than 6 above the
highest pressure at which any - valve is set in no case more than 6 above
the max allowable - pressure.
7ASME markings required on High Pressure Safety
Valves
- Name or identifying trade mark of manufacturer
- Manufacturers design or type number
- Size in inches, Seat Diameter in inches( i.e the
pipe size of - valve inlet )
- Pressure in lbs/ sq.ft or Kg / sq.cm (Steam
pressure at - which it is to blow)
- Blow down in Kgs or lbs ( BD is the difference
between the - opening closing pressure )
- Capacity in lbs / hr or kg / hr
- Capacity lift in inches. It is the distance the
valve disc rises - under the action of steam when the valve is
blowing under a - pressure of 3 above the set pressure.
8Number of Safety Valves requirement
- Each Boiler requires at least one SV, but if the
heating surface exceeds 500 Sq.ft, the boiler
must have two or more Safety relief valves. - When not more than two valves of different sizes
are mounted singly on the boiler, the smaller
valve must not be les than 50 in relieving
capacity of the larger valve. - Every super-heater attached to a boiler with no
intervening valves between the super-heater
boiler requires one or more safety valves on the
super-heater outlet header.With no intervening
stop valves between the super-heater boiler,
the capacity of the safety valves on the
super-heater may be included in the total
required for the boiler, provided the safety
valve capacity in the boiler is at least 75 of
the aggregate SV capacity required for the
Boiler. - Ex- If a boilers steaming capacity is 100
tons, a minimum of two valves are required - on Boiler with a total relieving
capacity of 75 of (100 Tons) I.e 75 tons. The - super-heater would then require a SV
with a capacity of (100 75) tons - i.e 25 Tons.
9Important Points
- Heating Surface
- That side of the boiler surface exposed to
the products of combustion, exclusive of
super-heating surface.The areas to be considered
for this purpose are tubes, fire-boxes, shells,
tube sheets the projected area of the headers. - Sequence of Safety valves Blowing
- The super-heater safety valves should always
be set at a lower pressure than the drum safety
valve ,so as to ensure steam flow through the
super-heater at all times. If the drum safety
valve blows first, the super-heater could be
starved of cooling steam, leading to possible
super-heater tube overheating rupture.
10Important Points
- Re-heater Safety valves
- The capacity of re-heater safety valves can
not be included in the total safety valve
capacity required for the boiler
super-heater.The relieving capacity of re-heater
safety valve must not be less than 15 of the
required total on the header. The total capacity
on the re-heater must be at least equal to the
maximum steam flow for which the re-heater is
designed . One SV must be on the re-heater
outlet. - Installation of Safety valves
- Every safety valve shall be connected so as
to stand in an up-right - position with spindle vertical.
11CASE STUDY OF A MAJOR DISASTER IN THERMAL STATION
Explosion in Boiler of Unit No.1 of Bongaigaon
TPS ( 4 x 60 MW) on 23.6.91 Bongaigaon TPS
consists of 4 units of 60 MW each commissioned
during the period 1981-1986. A severe explosion
was reported on the Boiler of Unit No.1 on
23.6.1991 at 5.15AM a voltage dip was observed
at that time and it was learnt that the Unit No.1
had tripped. It was noticed that there was no AC
or DC supply available in the Unit 1 Control
Room. The reserve AC supply did not come
automatically. The Boiler Attendant was
instructed to close the oil supply valves to cut
off the oil supply to the boiler. At the time
of the incidence , one oil gun at CD level and
three at AB level were in operation. The
attendant put closed the AB level oil guns and
while going to close the CD level oil gun the
boiler exploded. The Operator ran under a state
of shock and fell down from 12 metre to 8 metre
level Another Boiler Operator was found
unconscious laden with dust and coal on the 12
metre level near the boiler . DG set was started
manually , in spite of the fact that station AC
supply was available . The 6.6 Kv switchgear was
reported to be under water making it difficult
to approach However all the 6.6 Kv breakers
were manually tripped and the reserve supply was
established.
contd.
12CASE STUDY OF A MAJOR DISASTER IN THERMAL STATION
Observations During the investigation it was
found Explosion residue taken out from the
furnace bottom was very rich in un-burnt
oil and pulverized coal. Furnace wall
from inside had oil sticking to the surface.
Boiler operating floor was full of coal /
ash/ dust and even the local BMS panel
was fully covered with dust. BMS panel
was never used for operating the trip valves
Flame scanners were inoperative for many
years and also the igniters were
Non-functional. Oil used to be ignited
manually by Flame Torch (Mashal ).
Whenever the unit tripped the cause of tripping
was never analyzed.
Contd
13SOME MAJOR DISASTER IN THERMAL STATIONS
Following damages had taken place
i) Boiler furnace corners 1 4 got
completely ripped open above CD elevation up to
the furnace top. ii) Front and
left water walls got bulged outward and the
buck-stays were damaged. iii) Economiser
duct from the boiler bank outlet up to the
economiser opened out and had blown
. Contd
14CASE STUDY OF A MAJOR DISASTER IN THERMAL STATION
Causes of the explosion i) Flame failure
took place prior to boiler trip. ii) Flame
failure was not detected since the flame scanners
were not in operation. iii) Due to sudden
grid fluctuation, the boiler tripped on loss of
air flow protection. iv) The generator
breaker and UAT breaker tripped. v) There
was no AC or DC supply available on the generator
board. The automatic change over to
6.6 Kv reserve supply from station did not take
place. This resulted in failure of
supply in 6.6 Kv 1A bus. Since the battery was
not available, the DC supply had failed
resulting in non-operation of all the
controls. vi) Situation further aggravated
inside the furnace since the draft fans were also
not available. vii) The fuel oil
supply continued to go inside the furnace since
the fuel oil pumps were on station
supply and the oil trip valves could not be
closed manually causing boiler explosion.
15CASE STUDY OF A MAJOR DISASTER IN THERMAL STATION
Suggested remedial measures i) Boiler
local BMS panel should be made fully
operational. ii) Practice of operating the
fuel trip valves by shorting of the contacts
should be dispensed with. iii) All
the boiler auto controls should be made
functional and must be maintained. iv) The
DC battery and other connected system should be
maintained in perfect condition. v) All the
interlocks of auxiliaries like FD fans, ID fans,
etc should be made operative. The flame
scanners and igniters are also to be made
operational.
contd
16CASE STUDY OF A MAJOR DISASTER IN THERMAL STATION
Suggested remedial measures vi) The use of
oil should be discontinued beyond 40 unit load
and stable operation should be achieved
with coal firing after 40 load. vii) A
systematic preventive maintenance procedure for
various equipment should be
evolved. viii) Procedure of Annual inspection
and overhaul of boiler as per Indian Boiler
Regulation should be regularly
followed. ix) OM staff should be augmented
and adequate number of trained personnel should
be posted for operation and maintenance.