1
CALTHERM CORPORATION
  • David Langenderfer
  • Fall 2004 Coop Session
  • Department of Mechanical Engineering, IUPUI
  • Intern/Coop Presentations March 24, 2005

2
Introduction
  • Co-op at Caltherm Corporation in Fall 2003,
    Summer 2004 and Fall 2004
  • Engineering Lab Associate Fall 2003
  • Manufacturing Engineer Summer 2004
  • Lab Engineer Fall 2004
  • BSME Senior

3
Description of Caltherm
  • Manufacturing Facility in Columbus, IN opened in
    1979
  • Supply diesel engine thermostats
  • 60,000 sq. ft. over 150 employees
  • Acquired Vernay Labs in 1987
  • Acquired Eaton thermostats in 2003

4
(No Transcript)
5
Description of Duties
  • Design various close and stamp tooling
  • Design multiple leak test fixtures
  • Update documentation
  • Kan Ban implementation
  • Spring vs. Dead weight rack comparison
  • Upgraded life cycle testing procedure
  • Designed and implemented new high pressure test
    stand

6
Tooling Designs
  • Designed prototype close tooling for balanced
    thermostat for CAT
  • Designed new tooling for the V-Stat line
  • Designed prototype close tooling for Pressure
    Relief Valve for Racor.
  • Adjustable die for squeeze push element
  • Plate for life cycle testing
  • Adjustable plate for sensor

7
Various Tooling
Original V-Stat Tooling
Adjustable Die
V-Stat Tooling
V-Stat Tooling
Plate for Life Cycle Tester
Adjustable Sensor
8
Leak Test Fixture
  • Modified existing design to accommodate new seal
  • Designed using Solid Edge, created and assembled
    features to determine the appropriate fit
  • Sent to tool room to be made
  • Created work instruction on how to use the leak
    test fixture

9
Leak Test Fixtures
Modification of Original Fixture
New / Original
10
Update Documentation
  • Create APQP documentation such as PFMEA, control
    plans, flow charts and work instructions
  • Created flow charts for multiple low flow cells
  • Checked and modified documentation on CAT side
    bump

11
Kan Ban Implementation
  • Determine the 25 most common wax mixes
  • Create the Kan Ban board and tags
  • Install the Kan Ban board
  • Explain how to use the Kan Ban to the involved
    employees

12
Spring vs. Dead Weight
  • Create a test procedure for testing the
    difference between a spring and dead weight rack
  • Test the two racks with multiple elements and
    various temperatures
  • Report my findings

13
Life Cycle Test Procedure
  • Increase accuracy
  • Increase repeatability
  • Easier replacement
  • Ability to run 24 hours
  • Refill system

Test Fixture
Preliminary Fill System
Fill Tubes
Final Fill System
14
High Pressure Stand
  • Pressure drop
  • Measure flow
  • Look professional
  • Safety
  • Quick part changes

Electrical Enclosure
Reservoir Motor/Pump
Measurement Area
High Pressure Stand
15
Other Tasks
  • Create safety features
  • Create fluid recovery system
  • Modify wiper seal line
  • Design parts rack
  • Design coolant mister
  • Modify Harley-Davidson tooling

16
Safety Shield on Wax Inject
Light Curtain on Wiper Seal Close Press
Wiper Seal Press
Mister for Squeeze Push
17
Float Control for Fluid Recovery System
Fluid Recovery System Holding Tank
Harley-Davidson Tooling
Parts Rack for Wiper Seal
18