Title: First Parish in Needham Unitarian Universalist
1First Parish in Needham Unitarian
Universalist Renovations and Additions
Building Committee Status Report January 2008
2First Parish in Needham Unitarian
Universalist Renovations and Additions
AGENDA
- Construction Status
- Schedule
- Budget
- Accessibility issues
- Colors Finishes
Building Committee Status Report January 2008
3August 2007
4Demolition
5Roof Demolition
6Interior Demolition
7Excavation/Underpinning
8Foundations/underpinning
9Foundations
10Structural Reinforcement
11Structural Reinforcement
12Parish Hall Addition
13Parish Hall Addition
14Parish Hall Addition
15Parish Hall Addition
16Parish Hall Addition
17New Entrance
18New Entrance
19New Entrance
20New Entrance
21Parish Hall Interior
22Unforeseen Conditions
Rubble Foundations
23Rubble Foundations
24Foundation Replacement
25Foundation Replacement
26Sub-standard Structure
27Sub-standard Structure
28Drainage/Waterproofing
29Drainage/Waterproofing
30First Parish in Needham Unitarian
Universalist Renovations and Additions
AGENDA
- Construction Status
- Schedule
- Budget
- Accessibility issues
Building Committee Status Report January 2008
31ACCESSIBILITY ISSUES
Accommodations
- Parking
- Main Entrance at Lincoln Street
- Elevator to Upper Lower Levels
- Ramp to Office Wing
- Chair Lift at Playground/Parking Entrance
- Mens, Womens and Unisex Toilet Rooms
- All Interior Doors and Hardware
- Sinks and Cabinetry in Classrooms and Kitchen
- Sound System in Sanctuary
32ACCESSIBILITY ISSUES
Variances
- Chancel
- Choir loft
- Historic Front Entrance
- Stove vs. Cooktop
- Countertop Height for Dishwasher
33First Parish in Needham Unitarian
Universalist Renovations and Additions
AGENDA
- Construction Status
- Schedule
- Budget
- Accessibility issues
- Colors Finishes
Building Committee Status Report January 2008
34First Parish in Needham Unitarian
Universalist Renovations and Additions
Building Committee Status Report January 2008