Resource Allocation - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Resource Allocation

Description:

Choose activity that has lowest crash cost per day. May need to consider other dependencies ... Consider holidays, vacations. Compare with workload required ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 29
Provided by: drscott5
Category:

less

Transcript and Presenter's Notes

Title: Resource Allocation


1
Resource Allocation
  • Dr. Dale Masel
  • ISE 536
  • February 14, 2004

2
Resource Allocation
  • Projects Compete for Resources
  • Resources that are consumed
  • Resources that are not consumed
  • Goal Optimize use of Limited Resources
  • Requires trade-offs

3
Expediting a Task
  • Complete task more quickly
  • Reduce length of critical path
  • Make up for delays on critical path
  • Release resource more quickly
  • Additional Cost Crash Cost
  • Compare activities based on crash cost per day

4
Crashing Example
Must be 4 or 6 days only
5
Example Before Crashing
6
Choosing Activity to Crash
  • Look at critical path
  • Choose activity that has lowest crash cost per
    day
  • May need to consider other dependencies
  • Need to re-verify critical path after each
    crashing

7
Crashing Example
Path A-B 15 days Path A-C 15 days
Crash Costs A 30/day B 20/day C
25/day
8
Excel Solver
  • Target Cell
  • Value you want to minimize or maximize
  • Changing Cells
  • Parameters that can vary
  • Constraints
  • Conditions that cant be violated

9
Excel Solver for Crashing
  • Target Cell
  • Crashing costs ? Minimize
  • Changing Cells
  • Amount of crashing to do
  • Time each event occurs
  • Constraints
  • Amount each activity can be crashed
  • Precedence relationships
  • Completion Deadline
  • Nonnegativity

10
Fast-Tracking
  • Another type of expediting
  • Primarily in construction industry
  • Building phase starts before design and planning
    phases are done
  • Typically used when large portion of work is
    routine

11
Resource Loading
  • Schedule of resource usage
  • Amount of resources required
  • Associated activity
  • Required times
  • Usually a list or table

12
Ex Action Plan with Resources
13
Workforce Capacity Analysis
  • Concerns
  • Having enough hours available to complete project
  • Not having unused capacity
  • Uncertainty in
  • Hours required
  • Hours available

14
Determining Workforce Capacity
  • Calculate hours available
  • workers x hours/day x days
  • Consider holidays, vacations
  • Compare with workload required
  • Dealing with overloads
  • Shift activities to slow times
  • Overtime

15
Capacity Available vs. Required
16
Allocating Resources
  • Begin with PERT/CPM Schedule
  • Activities examined
  • Period-by-period
  • Resource-by-resource
  • If Demand exceeds Supply
  • Consider tasks individually
  • Assign resources based on priority

17
Constrained Resources
  • Scarcity of resources rarely applies to resources
    in general
  • Examples of Priority Rules
  • As soon as possible
  • As late as possible
  • Shortest task duration first
  • Minimum slack first
  • Most critical followers
  • Most successor
  • Most resources first

18
Choosing a Priority Rule
  • Schedule Slippage
  • Amount project would be delayed
  • Resource Utilization
  • Extent that resources are overworked or
    underworked
  • In-Process Inventory
  • Amount of unfinished work

19
Resources for Multiple Projects
  • Projects compete for resources
  • Not efficient to have separate resources for each
    project
  • Knowledge/skill required may not be available
    elsewhere
  • Use Pseudoactivities
  • Link several projects together
  • Characteristics
  • Do have duration
  • Do not require any resources
  • Allows set of projects to be treated like a
    single project

20
Life Cycle Resource Allocation
  • S-Shaped Life Cycle
  • Less impact when resources are withdrawn at end
  • J-Shaped Life Cycle
  • Significant impact when resources are withdrawn
    at end

21
Goldratts Critical Chain
  • Theory of Constraints
  • The Goal (1992)
  • Improvements in a process should focus on the
    bottleneck activities
  • Critical Chain (1997)

22
Critical Chain (1997)
  • Applies Goldratts Theory of Constraints to
    project management
  • Many people have same problems on projects
  • Unrealistic due dates
  • Too many changes
  • Resources and data not available
  • Unrealistic budget
  • These issues caused by need to make trade-offs
  • Goldratts Question
  • To what extent are these problems caused by human
    decisions and practices?

23
Three Project Scenarios
24
Multitasking
  • Example Two Small Projects

Alternate Gantt Charts
25
Common Chain of Events
  • Underestimate time needed to complete project
  • Assuming known activity times
  • Assuming independent paths
  • Project team members inflate time estimates
  • Work fills available time
  • Student syndrome ? Work up to due date
  • Early completions not reported

26
Common Chain of Events (contd)
  • Safety time misused
  • Results in missed deadlines
  • Complicates prioritizing of activities
  • Lack of clear priorities results in poor
    multitasking
  • Increases task durations
  • Uneven demand on resources
  • More projects undertaken to ensure all resources
    fully utilized
  • Leads to poor multitasking

27
Reversing the Cycle
  • Reduce number of projects assigned to each
    individual
  • Schedule start of new projects based on
    availability of bottleneck resources
  • Reduce amount of safety time added to individual
    tasks

28
The Critical Chain
  • Longest chain of consecutively dependent events
  • Consider precedence relationships
  • Consider resource dependencies
  • Use Buffers
  • Project buffer
  • Feeding buffer
Write a Comment
User Comments (0)
About PowerShow.com