Title: Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path
1Update on Q2 Main linac starting gradient,
upgrade gradient, and upgrade path
- Results of WG5 discussions after feedback from
plenary on Tuesday - New Option 2 (16 MV/m gt 28 MV/m)
- Enhanced upgrade scenario explorations for
options 1 2
2Three Upgrade Options (with New Names)
- 1 (same as last time)Highest acceptable
riskbased on 10 margin - Build tunnel long enough (41km) for one TeV, but
install only 500 GeV worth of cryomodules in
first 22 km of tunnel for 500 GeV phase. - 35 MV/m installed gradient, 31.5 MV/m operating
gradient for 500 GeV (gradient choice rationale
discussed earlier). - Fill second part of tunnel (19 km) with 36 MV/m
cavities (gradient choice discussed earlier),
install more RF/refrigeration - 2 NEW Lower riskbased on 20 margin
- 500 GeV phase Build tunnel long enough for one
TeV (41 km). Populate 24.4 km of tunnel with
cavities (35 MV/m installed gradient ) Operate
cavities at 20 margin (i.e. 28 MV/m). Increase
gradient to 31.5 MV/m over Phase I lifetime,
energy climbs to 560 GeV. - Upgrade Add 36 MV/m cavities in remaining 16.6
km, and add RF and refrigeration for upgrade. - 3 Half-Tunnel (same as last time)
- Build first half of tunnel for 500 GeV (22km)
and fill it with full gradient cavities (35 MV/m
installed gradient, 31.5 MV/m operating gradient,
discussed later). - Build second half of tunnel (19km) and add 36
MV/m cavities and RF/refrigeration for upgrade.
3Pros/cons of upgrade paths
- Initial cost
- best 3 (half-tunnel) worst Option 2
(20margin) - Cryomodules RF Refrigeration 2Tunnel
guiding model costs - Option 1 1.16, Option 2 (1.6) 1.22, Option 3
1.0 - Option 2 is less risky, most flexible for physics
through higher initial energy reach - Upgrade cost
- best Option 2 (20 margin) worst Option 3
(half-tunnel). - Option 1 0.7, Option 2 (0.4) 0.63, Option 3
0.9 - Total cost (initial upgrade)
- worst 3 (20 margin)
- . Option 1 1.85, Option 2 (1.97) 1.85,
Option 3 1.9
4WG5 Preferred Choice still is
Option 1 (10 margin)
- But Option 1 and Option 2 are getting closer !
- Cost Model estimates Option 2 (20margin) 1.05 x
Option 1 (10 margin) - ( Linac RF Cryo 2tunnels)
- Cost Model estimates Option 1 1.16 x Option 3
- Option 3 (Half-tunnel) Upgrade viability may be
questionable, physics impact of digging new
tunnel in vicinity of machine (this is a higher
level discussion topic than WG5)
5A More Optimistic Upgrade ScenarioBased on
Weeding out Scheme (Still under discussion)
- 1 ..Highest acceptable risk..based on 10
margin - Build tunnel (41km 38.5 km) for one TeV, but
install only 500 GeV worth of cryomodules in
first 22 km of tunnel. - 35 MV/m installed gradient, 31.5 MV/m operating
gradient for 500 GeV (gradient choice rationale
discussed earlier). - Upgrade Fill second part of tunnel (19 km 16.5
km) with 36 MV/m cavities (gradient choice
discussed later), install more RF/refrigeration. - Replace the lowest performing cryomodules during
upgrade with new cryomodules so that all Phase I
modules perform at 35 MV/m..anticipate replacing
10 of existing cryomodules. - Note total tunnel length shortened by 2.5 km
- 2 Lower riskbased on 20 margin
- Build tunnel long enough for one TeV (38.5 km).
Populate 24.4 km tunnel with cavities in phase1
(35 MV/m installed gradient ) Operate cavities at
20 margin (at 28 MV/m) in 500 GeV Phase 1.
Increase gradient of installed cavities to 31.5
MV/m over Phase I, energy climbs to 563 GeV. - Upgrade Add 36 MV/m cavities in 14.1 km, and
add RF and refrigeration for upgrade. - Replace the lowest performing cryomodules during
upgrade with new cryomodules so that all Phase I
modules perform at 35 MV/m..anticipate replacing
10 of existing cryomodules. - Note total tunnel length shortened by 2.5 km
6Estimated Cost Impact
- Upgrade cost
- Option 1 0.7 0.66, Option 2 0.63 0.57,
Option 3 0.9 0.82 -
- Total cost (initial upgrade)
- Option 1 1.85 1.82, Option 2 1.85 1.78,
Option 3 1.9 1.82 - (Includes cost of replacement modules)
7Attractive Features of Weeding Concept
- Low gradient cryomodules identified during Phase
I running - Keep cavity and cryomodule production factory
running at low rate to produce 10 replacement
modules over lifetime of 500 GeV Phase - About 100 - 120 modules (1200 - 1500 cavities)
- Avoids factory production halt and start up
problems for upgrade production
8Requests to Other Groups
- What is the effect of 10, 20 margin on
reliability? - What is the effect of 10 or 20 margin on cost?
- Guiding model suggests 10 extra margin has
initial project cost penalty of 5 (on linac cost
only). - All costs need more detail analysis
- How attractive is the weeding out scheme in
feasibility, cost, and upgradability ?
9END
10Pros/cons of upgrade paths, cont
- Initial schedule
- Best 3 half-tunnel, worst 2 lower risk
- Option 3 takes longer to start up due to largest
module production and installation - Upgrade schedule
- best 2 lower risk worst 3 half-tunnel.
- Option 2 The extra RF to upgrade half-gradient
can be installed while ILC is running if there
are 2 tunnels. - Option 2 does not require interruption for module
production and installation, - Option 2 does not take advantage of gradient
advances to come - Upgrade viability
- worst 3 half-tunnel. Has civil
construction. Need to check if tunnel boring
machines vibrate the ground too much to allow
tunneling during running. If so, upgrade is not
viable. - Need to move certain installed systems (e.g
undulators)
11 Cavity Gradient/ Shape - 500GeV
- Shape Options (to be discussed by Saito)
- TESLA
- Low-Loss
- Re-entrant
- Superstructure
- Pros/Cons (to be discussed by Saito)
12Cavity gradient/ shape - 500GeVRepeat of Friday
Summary - Proch
- Preferred Choice TESLA shape
- Performance and cost best understood
- Gradient Choice 31.5MV/m
- Based upon
- Critical field 41MV/m (TESLA shape)
- Practical limit in multi-cells 90 critical
field 37MV/m (5 sigma spread) - Lower end of present fabrication scatter ( 5)
- TESLA shape 35 MV/m
- Vert dewar acceptance criteria 35MV/m or more
(some cavities must be reprocessed to pass this) - Operating gradient 90 x installed gradient
31.5MV/m - Allows for needed flexibility of operation and
commissioning - Gives operating overhead for linac and allows
individual module ultimate performance. - Choice of operating gradient does not include
fault margin - e.g 2 - 5 additional cryomodules to be
determined by availability considerations
13Further Comments onstarting cavity gradient -
500GeV
- RD to address remaining risk
- Significant RD necessary to achieve the
specified module gradient and spread. - System tests and long-term tests of 35 MV/m
modules needed as spelled out by R1 and R2 of TRC
- RD needed in BCD cavity processing BCD
material (though other RD efforts may prove
beneficial e.g. single crystal) - This RD effort needs to be organized
internationally, Discussions underway - Must also address how to industrialize the
processing for reliable and reproducible
performance
14Upgrade gradient choice(depends on shape)
discussed on Friday Summary - Proch
- Theoretical RF magnetic limit
- Tesla shape 41 MV/m
- LL,RE shape 47 MV/m
- Practical limit in multi-cell cavities -10
- TESLA shape. 37 MV/m
- LL, RE shape expected 42.3 MV/m
- Lower end of present fabrication scatter (- 5)
- TESLA shape 35 MV/m
- LL, RE shape 40 MV/m
- Operations margin -10
- TESLA shape 31.5 MV/m
- LL, RE shape 36 MV/m
15Assume cavities can reach avg of 90 of limit
with 5rms in Vert dewar
Most Tesla cavities should be able to reach
35MV/m accept Most LL/RE cavities should be able
to reach 40 MV/m accept But note there is a low
energy tail that fails
36.9/-1.85MV/m
42.3/-2.12MV/m
41
47
31.5
37
35
s5
10
Eacc MV/m