Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path

1 / 15
About This Presentation
Title:

Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path

Description:

Option 3 (Half-tunnel): Upgrade viability may be questionable, physics impact of ... If so, upgrade is not viable. Need to move certain installed systems (e.g ... –

Number of Views:113
Avg rating:3.0/5.0
Slides: 16
Provided by: helene78
Category:

less

Transcript and Presenter's Notes

Title: Update on Q2 Main linac starting gradient, upgrade gradient, and upgrade path


1
Update on Q2 Main linac starting gradient,
upgrade gradient, and upgrade path
  • Results of WG5 discussions after feedback from
    plenary on Tuesday
  • New Option 2 (16 MV/m gt 28 MV/m)
  • Enhanced upgrade scenario explorations for
    options 1 2

2
Three Upgrade Options (with New Names)
  • 1 (same as last time)Highest acceptable
    riskbased on 10 margin
  • Build tunnel long enough (41km) for one TeV, but
    install only 500 GeV worth of cryomodules in
    first 22 km of tunnel for 500 GeV phase.
  • 35 MV/m installed gradient, 31.5 MV/m operating
    gradient for 500 GeV (gradient choice rationale
    discussed earlier).
  • Fill second part of tunnel (19 km) with 36 MV/m
    cavities (gradient choice discussed earlier),
    install more RF/refrigeration
  • 2 NEW Lower riskbased on 20 margin
  • 500 GeV phase Build tunnel long enough for one
    TeV (41 km). Populate 24.4 km of tunnel with
    cavities (35 MV/m installed gradient ) Operate
    cavities at 20 margin (i.e. 28 MV/m). Increase
    gradient to 31.5 MV/m over Phase I lifetime,
    energy climbs to 560 GeV.
  • Upgrade Add 36 MV/m cavities in remaining 16.6
    km, and add RF and refrigeration for upgrade.
  • 3 Half-Tunnel (same as last time)
  • Build first half of tunnel for 500 GeV (22km)
    and fill it with full gradient cavities (35 MV/m
    installed gradient, 31.5 MV/m operating gradient,
    discussed later).
  • Build second half of tunnel (19km) and add 36
    MV/m cavities and RF/refrigeration for upgrade.

3
Pros/cons of upgrade paths
  • Initial cost
  • best 3 (half-tunnel) worst Option 2
    (20margin)
  • Cryomodules RF Refrigeration 2Tunnel
    guiding model costs
  • Option 1 1.16, Option 2 (1.6) 1.22, Option 3
    1.0
  • Option 2 is less risky, most flexible for physics
    through higher initial energy reach
  • Upgrade cost
  • best Option 2 (20 margin) worst Option 3
    (half-tunnel).
  • Option 1 0.7, Option 2 (0.4) 0.63, Option 3
    0.9
  • Total cost (initial upgrade)
  • worst 3 (20 margin)
  • . Option 1 1.85, Option 2 (1.97) 1.85,
    Option 3 1.9

4
WG5 Preferred Choice still is
Option 1 (10 margin)
  • But Option 1 and Option 2 are getting closer !
  • Cost Model estimates Option 2 (20margin) 1.05 x
    Option 1 (10 margin)
  • ( Linac RF Cryo 2tunnels)
  • Cost Model estimates Option 1 1.16 x Option 3
  • Option 3 (Half-tunnel) Upgrade viability may be
    questionable, physics impact of digging new
    tunnel in vicinity of machine (this is a higher
    level discussion topic than WG5)

5
A More Optimistic Upgrade ScenarioBased on
Weeding out Scheme (Still under discussion)
  • 1 ..Highest acceptable risk..based on 10
    margin
  • Build tunnel (41km 38.5 km) for one TeV, but
    install only 500 GeV worth of cryomodules in
    first 22 km of tunnel.
  • 35 MV/m installed gradient, 31.5 MV/m operating
    gradient for 500 GeV (gradient choice rationale
    discussed earlier).
  • Upgrade Fill second part of tunnel (19 km 16.5
    km) with 36 MV/m cavities (gradient choice
    discussed later), install more RF/refrigeration.
  • Replace the lowest performing cryomodules during
    upgrade with new cryomodules so that all Phase I
    modules perform at 35 MV/m..anticipate replacing
    10 of existing cryomodules.
  • Note total tunnel length shortened by 2.5 km
  • 2 Lower riskbased on 20 margin
  • Build tunnel long enough for one TeV (38.5 km).
    Populate 24.4 km tunnel with cavities in phase1
    (35 MV/m installed gradient ) Operate cavities at
    20 margin (at 28 MV/m) in 500 GeV Phase 1.
    Increase gradient of installed cavities to 31.5
    MV/m over Phase I, energy climbs to 563 GeV.
  • Upgrade Add 36 MV/m cavities in 14.1 km, and
    add RF and refrigeration for upgrade.
  • Replace the lowest performing cryomodules during
    upgrade with new cryomodules so that all Phase I
    modules perform at 35 MV/m..anticipate replacing
    10 of existing cryomodules.
  • Note total tunnel length shortened by 2.5 km

6
Estimated Cost Impact
  • Upgrade cost
  • Option 1 0.7 0.66, Option 2 0.63 0.57,
    Option 3 0.9 0.82
  • Total cost (initial upgrade)
  • Option 1 1.85 1.82, Option 2 1.85 1.78,
    Option 3 1.9 1.82
  • (Includes cost of replacement modules)

7
Attractive Features of Weeding Concept
  • Low gradient cryomodules identified during Phase
    I running
  • Keep cavity and cryomodule production factory
    running at low rate to produce 10 replacement
    modules over lifetime of 500 GeV Phase
  • About 100 - 120 modules (1200 - 1500 cavities)
  • Avoids factory production halt and start up
    problems for upgrade production

8
Requests to Other Groups
  • What is the effect of 10, 20 margin on
    reliability?
  • What is the effect of 10 or 20 margin on cost?
  • Guiding model suggests 10 extra margin has
    initial project cost penalty of 5 (on linac cost
    only).
  • All costs need more detail analysis
  • How attractive is the weeding out scheme in
    feasibility, cost, and upgradability ?

9
END
10
Pros/cons of upgrade paths, cont
  • Initial schedule
  • Best 3 half-tunnel, worst 2 lower risk
  • Option 3 takes longer to start up due to largest
    module production and installation
  • Upgrade schedule
  • best 2 lower risk worst 3 half-tunnel.
  • Option 2 The extra RF to upgrade half-gradient
    can be installed while ILC is running if there
    are 2 tunnels.
  • Option 2 does not require interruption for module
    production and installation,
  • Option 2 does not take advantage of gradient
    advances to come
  • Upgrade viability
  • worst 3 half-tunnel. Has civil
    construction. Need to check if tunnel boring
    machines vibrate the ground too much to allow
    tunneling during running. If so, upgrade is not
    viable.
  • Need to move certain installed systems (e.g
    undulators)

11
Cavity Gradient/ Shape - 500GeV
  • Shape Options (to be discussed by Saito)
  • TESLA
  • Low-Loss
  • Re-entrant
  • Superstructure
  • Pros/Cons (to be discussed by Saito)

12
Cavity gradient/ shape - 500GeVRepeat of Friday
Summary - Proch
  • Preferred Choice TESLA shape
  • Performance and cost best understood
  • Gradient Choice 31.5MV/m
  • Based upon
  • Critical field 41MV/m (TESLA shape)
  • Practical limit in multi-cells 90 critical
    field 37MV/m (5 sigma spread)
  • Lower end of present fabrication scatter ( 5)
  • TESLA shape 35 MV/m
  • Vert dewar acceptance criteria 35MV/m or more
    (some cavities must be reprocessed to pass this)
  • Operating gradient 90 x installed gradient
    31.5MV/m
  • Allows for needed flexibility of operation and
    commissioning
  • Gives operating overhead for linac and allows
    individual module ultimate performance.
  • Choice of operating gradient does not include
    fault margin
  • e.g 2 - 5 additional cryomodules to be
    determined by availability considerations

13
Further Comments onstarting cavity gradient -
500GeV
  • RD to address remaining risk
  • Significant RD necessary to achieve the
    specified module gradient and spread.
  • System tests and long-term tests of 35 MV/m
    modules needed as spelled out by R1 and R2 of TRC
  • RD needed in BCD cavity processing BCD
    material (though other RD efforts may prove
    beneficial e.g. single crystal)
  • This RD effort needs to be organized
    internationally, Discussions underway
  • Must also address how to industrialize the
    processing for reliable and reproducible
    performance

14
Upgrade gradient choice(depends on shape)
discussed on Friday Summary - Proch
  • Theoretical RF magnetic limit
  • Tesla shape 41 MV/m
  • LL,RE shape 47 MV/m
  • Practical limit in multi-cell cavities -10
  • TESLA shape. 37 MV/m
  • LL, RE shape expected 42.3 MV/m
  • Lower end of present fabrication scatter (- 5)
  • TESLA shape 35 MV/m
  • LL, RE shape 40 MV/m
  • Operations margin -10
  • TESLA shape 31.5 MV/m
  • LL, RE shape 36 MV/m

15
Assume cavities can reach avg of 90 of limit
with 5rms in Vert dewar
Most Tesla cavities should be able to reach
35MV/m accept Most LL/RE cavities should be able
to reach 40 MV/m accept But note there is a low
energy tail that fails
36.9/-1.85MV/m
42.3/-2.12MV/m
41
47
31.5
37
35
s5
10
Eacc MV/m
Write a Comment
User Comments (0)
About PowerShow.com