Title: Transitioning to Accelerated Bridge Construction ABC as Standard Practice
1Transitioning to Accelerated Bridge Construction
(ABC) as Standard Practice
- by
- Mary Lou Ralls, P.E.
- Ralls Newman, LLC
- Prefabricated Bridge Elements Systems (PBES)
for ABC - WASHTO-X Videoconference
- June 17, 2008
2What is Accelerated Bridge Construction?
- Building the bridge more quickly than your
conventional practice, while maintaining quality - What that means to you depends on where you are
now - ABC spans the entire process, from planning
through construction
3Examples of ABC - Planning
- Early owner meetings with contractors suppliers
to innovate - Right-of-way acquisition utility relocations
before advertising project - Early environmental clearance permitting
- Innovative contracting strategies in contract
documents (e.g., AB bidding, lane rental,
incentive/disincentive clauses)
4Examples of ABC Planning, contd.
- Electronic shop drawing submittal approval
process - Procurement of materials before advertising
project (e.g., prestressed concrete girders,
structural steel girders)
5Examples of ABC - Design
- Prefabrication of bridge components or entire
bridge - Geotechnical engineering enhancements (e.g.,
mechanically-stabilized earth walls instead of
conventional cantilever retaining walls
reinforced or lightweight backfills)
6Examples of ABC - Construction
- Allowing contractor options to innovate
- Use of innovative equipment (e.g., self-propelled
modular transporters SPMTs to move entire
bridge launching, pivoting, or skidding
equipment) - Concurrent onsite engineering operations (e.g.,
building abutments interior supports
simultaneously)
7Accelerated Bridge Construction
- Replacement or new construction
- Uses innovative design construction methods
high performance materials - Reduces typical construction time
- Maintains or enhances quality
- Reduces traffic disruption
- Increases work-zone safety
- Produces cost-effective, long-lasting bridges
with early openings
8Prefabricated Bridges
- One ABC method
- Bridge elements or systems, or entire bridges,
built at offsite locations - Controlled offsite environment assures quality
construction - Transported to site quickly installed, e.g.,
- Girders partial-depth deck panels
- Full-depth precast deck panels
- Superstructure systems
- Substructure systems
- Totally prefabricated bridges
9Typical Prefabricated Elements
Partial-depth Deck Panels
Girders
10Reduced Number of Superstructure Components by
Use of High Performance Materials
conventional 0.5-inch diameter strands
normal-strength concrete
0.6-inch diameter strands high-strength HPC
concrete
7 conventional beams Span No. 1 North Concho
Westbound Mainlanes San Angelo, Texas
4 HPC beams Span No. 1 North Concho Eastbound
Mainlanes San Angelo, Texas
11Dead Run and Turkey Run Bridges on George
Washington Memorial Parkway, Virginia 1998
Weekend deck replacement
12State Route 433 Lewis and Clark Bridge over
Columbia River, WA/OR 2004
Deck replaced with full-width, full-depth precast
deck panels
SPMTs with frame carrying panel
with no impact to rush-hour traffic
After deck replacement
13Superstructure Replacement of I-95 Bridge over
James River, Virginia - 2002
Prefabricated Superstructure System
required partial lane closures only
with no lane closures during rush-hour traffic
144500 South Bridge over I-215E, Utah - 2007
- Prefabricated Superstructure
- driven into position with SPMTs
- I-215 closed over a weekend
- 4500 South closed only 10 days
15Newark InternationalAirport Monorail, New
Jersey 2001
Prefabricated Substructure
16I-287 Cross WestchesterExpressway Viaducts,New
York 1999
Precast Concrete Substructure
17State Highway 86 Bridge over Mitchell Gulch,
Colorado 2002
Precast concrete abutments, wingwalls, superstruct
ure units with railing, steel H piles
Early Saturday morning
Saturday afternoon
Saturday afternoon
18Mill Street Bridge over Lamprey River, New
Hampshire 2004
Precast reinforced concrete substructure after
erection, prior to placing backfill
Placing spread footing segments
- 10 footing segments
- 11 abutment/wingwall segments
- 7 prestressed HPC box beams
Erection of pretensioned concrete box beams
19So, what doesprefabricated bridges for
ABCmean to you in your city,or your county,or
your state?
20One Example TexasPrefabricated Bridges for ABC
- Extensive sets of conventional bridge standards
(google TxDOT bridge standards) - Pretensioned concrete beam standards
- I-beams
- Slab beams
- Box beams
- U-beams
- Structural steel I-beam standards
- Partial-depth precast deck panel standards
- Other supplemental bridge standards
21One Example TexasPrefabricated Bridges for ABC,
contd.
- ABC standards
- Pretensioned concrete double-T beams updated
2006 - Pretensioned concrete decked slab beams
released 2008 - Project-specific prefab for ABC
- Full-depth deck panels
- Precast bent caps
- Prefabricated superstructures
- Totally prefabricated bridges
22What doesABC as Standard Practicemean?
23ABC as standard practice means considering ABC at
the initial planning stage of each project
- Use FHWA Framework for Prefabricated Bridge
Elements and Systems (PBES) Decision-Making - http//www.fhwa.dot.gov/bridge/prefab
- or
- Develop your own decision-making tool
- Example Utah DOT Decision Chart
And having a business model in place to use ABC
as appropriate
24- FHWA
- Decision-
- Making
- Framework
- 3 formats
- Flowchart
- Matrix Questions
- (yes-no-maybe)
- QA Discussion
25RAPID ONSITE CONSTRUCTION FACTORS Traffic Volume
/ Emergency / Commerce / User Delay ???
26OTHER FACTORS Worker Safety / Wetlands-Air
Quality-Noise / Endangered Species / Multiple
Similar Sections ???
27PBES CONSTRUCTION COSTS LESS ???
28Decision-Making MatrixExample Questions
FHWA Decision-Making Framework
29FHWA Decision-Making Framework
30Utah DOT Decision Chart
31How do you transition to ABC as Standard
Practice?
32One Example Utahs Transitionto ABC as Standard
Practice
- Developed decision-making chart
- Completed project-specific prefabricated ABC,
e.g., - Full-depth deck panels
- Precast bent caps
- Prefabricated superstructure installed with SPMTs
- Conducted domestic scanning tours
- Identified a program of ABC projects
- Requested demonstration project funding
33I-80 State Street to 1300 EastMultiple
Structures, Salt Lake City
- Anticipated 2008 Move Dates for SPMT Program of
Projects
- June 21-June 26 - Highland Drive
- June 26-July 1 - 900 East Bridge
- July 5-July 10 - 600 East Ramp Bridge
- July 15-July 19
- 600 East Bridge
- 700 East Bridge
- July 19-July 24 - 500 East Bridge
- July 28-August 1 - 300 East Bridge
34One Example Utahs Transitionto ABC as Standard
Practice, contd.
- Involved nationally
- Developed first 2 sets of draft prefabricated ABC
standards, specifications, design aids - Full-depth precast deck panels
- Use of SPMTs to move superstructure spans
- Hosted workshop with national experts local
industry to receive recommendations - First 2 draft products
- Transitioning to ABC as standard practice by 2010
35One Example Utahs Transitionto ABC as Standard
Practice, contd.
- Revised first 2 sets of ABC standards products
- Hosted local industry feedback meeting to further
refine products to meet local needs - Updated products incorporated into upcoming
projects - Maintaining communication with industry update
standards products as needed
36One Example Utahs Transitionto ABC as Standard
Practice, contd.
- Initiated development on 2nd round of
prefabricated ABC standards products, including
precast - Pretensioned girders
- Parapets
- Bent caps
- Columns
- Footings
- Approach slabs
37One Example Utahs Transitionto ABC as Standard
Practice, contd.
- Assessing implementing strategies to enhance
performance of ABC by accelerating other areas,
e.g., - Project delivery (shortening time from funded
concept to final constructed project) - Decision making during design construction
- Construction of critical path non-bridge parts of
projects - Continuing to consider workshop recommendations
on transitioning to ABC
38One Example Utahs Transitionto ABC as Standard
Practice, contd.
39One Example Utahs Transitionto ABC as Standard
Practice, contd.
- Communicating with the public
4500 South Bridge over I-215E Installed in One
Weekend
40Summary on Transitioning toABC as Standard
Practice
- Become educated nationally internationally
- Develop business model, including decision-making
tool program of work - Seek funding for demonstration projects
- Standardize prefabrication details
- Use innovative contracting strategies
- Educate communicate internally, with industry,
with the public
41Prefabricated bridges for Accelerated Bridge
Construction help transportation agenciesachieve
their MissionTo efficiently and
effectivelymove people, goods, and services
42Prefabricated Bridges For Accelerated Bridge
Construction
Thank You