Requests for Intervenor Status
  • Zoning Petition ZP 702
  • Maine Mountain Power LLC
  • June 7, 2006

2
Requests for Intervenor Status
  • Sixteen requests
  • Neutral, or position unstated 8
  • Opposition stated 6
  • NPS as a government agency
  • Support stated 2

3
Neutral or Position Unstated
  • Maine Audubon
  • Natural Resources Council of Maine
  • Conservation Law Foundation
  • Central Maine Power
  • Independent Energy Producers of Maine
  • Maine Interfaith Power and Light
  • Coalition to Reduce Dependence on Foreign Oil
  • TransCanada

4
Position Stated
  • Opposed
  • Appalachian Trail Conservancy
  • Maine Appalachian Trail Club
  • Appalachian Mountain Club
  • Friends of the Western Mountains
  • Western Mountains Foundation
  • National Park Service
  • Support
  • Maine Energy Investment Corporation
  • Ed Holt Associates, Inc.

5
Chapter 5 Relevant Criteria
  • Section 5.13(1) of the Commissions Land Use
    Districts and Standards
  • The Commission may allow parties to offer
    testimony and evidence, and to cross-examine
  • Or, the Commission may allow parties to
    participate in a limited manner
  • Requests after deadline may be allowed
  • Intervenors may be consolidated with other
    Intervenors
  • Section 5.15 of the Commissions Land Use
    Districts and Standards Government agencies may
    participate as Intervenors

6
Staff Recommendation
  • Staff recommends that the Commission grant
    Intervenor status to all parties requesting such
    status in the proceedings for the proposed
    Redington Wind Farm, Zoning Petition ZP 702,
    submitted by Maine Mountain Power, LLC.
  • Staff further recommends that the Intervenors be
    consolidated to the greatest extent possible.