MS4801 Project Management - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

MS4801 Project Management

Description:

MS4801 Project Management – PowerPoint PPT presentation

Number of Views:798
Avg rating:3.0/5.0
Slides: 30
Provided by: bia90
Category:

less

Transcript and Presenter's Notes

Title: MS4801 Project Management


1
MS4801 Project Management
  • Week 6
  • Estimating (continued), Risk Analysis Schedule
    Control

Great deeds are usually wrought at great risk.
- Herodotus, Greek historian
2
Macro vs. Micro Estimating
Best approach is to do both
3
Estimating Time and Costs
  • Macro Approaches
  • 1) Ratio methods e.g., 2,700 sq ft _at_ 100
  • 2) Apportion methods historical dependency,
    time/costs apportioned to deliverables (e.g.,
    slide 8)
  • 3) Function point methods software industry,
    inputs, outputs, inquiries, files,
    interfaces
  • 4) Learning curves repeated tasks weighted more
    heavily when initially completed

4
See learning curve tables
  • 50 to manufacture ONE flying pig (5 pigs 250)
  • 60 learning curve
  • 5th .3054 x 5015.27
  • Cost to manufacture five flying pigs
  • 50 x 2.71135.50

5
(No Transcript)
6
(No Transcript)
7
Norwegian Satellite Development Company
  • Cost estimates for World Satellite Telephone
    Exchange Project
  • NSDC has a contract to produce eight satellites
    to support a worldwide telephone system ( for
    Alaska Telecom, Inc.) that allows individuals to
    use a single, portable telephone in any location
    on earth to call in and out. NSDC will develop
    and produced the eight units. NSDC has estimated
    that the RD costs will be 12,000. Material
    costs are expected to be 6,000. They have
    estimated the design and production of the first
    satellite will require 1,000 labor hours and an
    80 improvement curve is expected. Skilled labor
    cost is 30 per hour. Desired profit for all
    projects is 25 of total costs.
  •  
  • A. How many labor hours should the eighth
    satellite require?
  • B. How many labor hours for the whole project of
    eight satellites?
  •  C. What should NSCD estimate as the total cost
    for this project?

RD 12,000 Materials 6,000 Labor 5346x30
160,380 COSTS178,380 25 PROFIT44,595 TOTAL
PROJECT ESTIMATE 222,975
 1000 labor hours x.512 512 labor hours for the
8th unit
 1000 labor hours for per unit x 5.346 5346
total for 8 units
8
Estimating Time and Costs
  • Micro approaches
  • 1) Template method use when project is similar
    to past project
  • 2) Parametric procedures applied to specific
    tasks like the macro ratio method, but applied
    to individual tasks
  • 3) Detailed estimates for the WBS most reliable
    method (go to example)
  • 4) Phase estimating begins with macro approach
    then refines as phases of project completed (go
    to example)

9
Refining estimates
  • Some PMs adjust project costs up by 20 because
  • Interaction costs are hidden
  • Normal conditions are a starting point, but
    seldom reality
  • Things go wrong on projects
  • Changes in project scope and plans occur

10
Apportion Method
Return to Slide 3
11
Phase Estimating
Return to Slide 6
12
WBS Estimate
Return to Slide 6
13
Risk Assessment Process
  • Use brainstorming
  • Do not focus on consequences, rather focus on
    events that cause
  • Focus on whole project rather than parts of the
    project
  • Use WBS to be sure nothing is missed
  • Step 1 Risk identification
  • Step 2 Risk assessment
  • Step 3 Risk response development
  • Contingency planning
  • Contingency funding
  • Step 4 Risk response control
  • Change control management
  • Risk Assessment Forms
  • GO TO 13
  • Mitigating Risk reduce likelihood / reduce
    impact
  • Transfer Risk costs
  • Share Risk
  • Retain Risk
  • GO TO 14

Go to Response Control
14
Risk Assessment FormMS Office 97 to XP
Go to next slide
15
Risk Severity Matrix
Return to Slide 12
16
Risk Response Matrix
17
Step 4 Risk Response Control
18
Alaska Fly-Fishing Expedition
  • See handout

19
Schedule Control
  • WEEK 6, Chapter 7

20
Project Control Process
  • The key to effective project control is to
    measure actual progress and compare it to planned
    progress on a timely and regular basis and to
    take necessary corrective action immediately.
  • Establish a regular reporting period.
  • During each reporting period, collect
  • data on actual performance
  • information on any changes to project scope,
    schedule and budget.
  • If changes are incorporated, a new plan must be
    established.

5
21
(No Transcript)
22
Effects of Actual Schedule Performance
  • Actual finish times (AFT) of completed activities
    will determine the earliest start and earliest
    finish times for the remaining activities.

6
23
(No Transcript)
24
Incorporating Project Changes into the Schedule
  • Changes might be initiated by the customer or the
    project team, or they might be the result of an
    unanticipated occurrence.
  • The degree of impact may depend on when the
    changes are requested.
  • When the customer requests a change, additional
    costs might need to be charged.

7
25
Updating the Project Schedule
  • An updated project schedule can be calculated
    based on actual finish times of completed
    activities

8
26
Approaches to Schedule Control Four Steps
  • Analyze the schedule
  • Decide what corrective actions should be taken,
    if any
  • Revise the plan
  • Recalculate the schedule

9
27
Approaches to Schedule Control
  • A change in the estimated duration of any
    activity will cause a corresponding change in the
    slack for that path.
  • When a path of activities has negative slack,
    focus on
  • Activities that are near term.
  • Activities that have long estimated durations.

10
28
Reducing the Estimated Durations
  • Apply more resources.
  • Assign a person with greater expertise to perform
    or help with the activity.
  • Reduce the scope or requirements for an activity.
  • Totally eliminate some activities.
  • Increase productivity through improved methods or
    technology.

11
29
Approaches to Schedule Control
  • Reducing durations of activities usually results
    in an increase in costs or a reduction in scope.
  • The key is to effectively address paths with
    negative or deteriorating slack values as soon as
    they are identified.

12
Write a Comment
User Comments (0)
About PowerShow.com