Title: MS4801 Project Management
1MS4801 Project Management
- Week 6
- Estimating (continued), Risk Analysis Schedule
Control
Great deeds are usually wrought at great risk.
- Herodotus, Greek historian
2Macro vs. Micro Estimating
Best approach is to do both
3Estimating Time and Costs
- Macro Approaches
- 1) Ratio methods e.g., 2,700 sq ft _at_ 100
- 2) Apportion methods historical dependency,
time/costs apportioned to deliverables (e.g.,
slide 8) - 3) Function point methods software industry,
inputs, outputs, inquiries, files,
interfaces - 4) Learning curves repeated tasks weighted more
heavily when initially completed
4See learning curve tables
- 50 to manufacture ONE flying pig (5 pigs 250)
- 60 learning curve
- 5th .3054 x 5015.27
- Cost to manufacture five flying pigs
- 50 x 2.71135.50
5(No Transcript)
6(No Transcript)
7Norwegian Satellite Development Company
- Cost estimates for World Satellite Telephone
Exchange Project - NSDC has a contract to produce eight satellites
to support a worldwide telephone system ( for
Alaska Telecom, Inc.) that allows individuals to
use a single, portable telephone in any location
on earth to call in and out. NSDC will develop
and produced the eight units. NSDC has estimated
that the RD costs will be 12,000. Material
costs are expected to be 6,000. They have
estimated the design and production of the first
satellite will require 1,000 labor hours and an
80 improvement curve is expected. Skilled labor
cost is 30 per hour. Desired profit for all
projects is 25 of total costs. -
- A. How many labor hours should the eighth
satellite require? - B. How many labor hours for the whole project of
eight satellites? - C. What should NSCD estimate as the total cost
for this project?
RD 12,000 Materials 6,000 Labor 5346x30
160,380 COSTS178,380 25 PROFIT44,595 TOTAL
PROJECT ESTIMATE 222,975
1000 labor hours x.512 512 labor hours for the
8th unit
1000 labor hours for per unit x 5.346 5346
total for 8 units
8Estimating Time and Costs
- Micro approaches
- 1) Template method use when project is similar
to past project - 2) Parametric procedures applied to specific
tasks like the macro ratio method, but applied
to individual tasks - 3) Detailed estimates for the WBS most reliable
method (go to example) - 4) Phase estimating begins with macro approach
then refines as phases of project completed (go
to example)
9Refining estimates
- Some PMs adjust project costs up by 20 because
- Interaction costs are hidden
- Normal conditions are a starting point, but
seldom reality - Things go wrong on projects
- Changes in project scope and plans occur
10Apportion Method
Return to Slide 3
11Phase Estimating
Return to Slide 6
12WBS Estimate
Return to Slide 6
13Risk Assessment Process
- Use brainstorming
- Do not focus on consequences, rather focus on
events that cause - Focus on whole project rather than parts of the
project - Use WBS to be sure nothing is missed
- Step 1 Risk identification
- Step 2 Risk assessment
- Step 3 Risk response development
- Contingency planning
- Contingency funding
- Step 4 Risk response control
- Change control management
- Risk Assessment Forms
- GO TO 13
- Mitigating Risk reduce likelihood / reduce
impact - Transfer Risk costs
- Share Risk
- Retain Risk
- GO TO 14
Go to Response Control
14Risk Assessment FormMS Office 97 to XP
Go to next slide
15Risk Severity Matrix
Return to Slide 12
16Risk Response Matrix
17Step 4 Risk Response Control
18Alaska Fly-Fishing Expedition
19Schedule Control
20Project Control Process
- The key to effective project control is to
measure actual progress and compare it to planned
progress on a timely and regular basis and to
take necessary corrective action immediately. - Establish a regular reporting period.
- During each reporting period, collect
- data on actual performance
- information on any changes to project scope,
schedule and budget. - If changes are incorporated, a new plan must be
established.
5
21(No Transcript)
22Effects of Actual Schedule Performance
- Actual finish times (AFT) of completed activities
will determine the earliest start and earliest
finish times for the remaining activities.
6
23(No Transcript)
24Incorporating Project Changes into the Schedule
- Changes might be initiated by the customer or the
project team, or they might be the result of an
unanticipated occurrence. - The degree of impact may depend on when the
changes are requested. - When the customer requests a change, additional
costs might need to be charged.
7
25Updating the Project Schedule
- An updated project schedule can be calculated
based on actual finish times of completed
activities
8
26Approaches to Schedule Control Four Steps
- Analyze the schedule
- Decide what corrective actions should be taken,
if any - Revise the plan
- Recalculate the schedule
9
27Approaches to Schedule Control
- A change in the estimated duration of any
activity will cause a corresponding change in the
slack for that path. - When a path of activities has negative slack,
focus on - Activities that are near term.
- Activities that have long estimated durations.
10
28Reducing the Estimated Durations
- Apply more resources.
- Assign a person with greater expertise to perform
or help with the activity. - Reduce the scope or requirements for an activity.
- Totally eliminate some activities.
- Increase productivity through improved methods or
technology.
11
29Approaches to Schedule Control
- Reducing durations of activities usually results
in an increase in costs or a reduction in scope. - The key is to effectively address paths with
negative or deteriorating slack values as soon as
they are identified.
12