Effective Project Management - PowerPoint PPT Presentation

About This Presentation
Title:

Effective Project Management

Description:

Activities are made up of tasks ... description of how the tasks that make up the activity will actually be done ... Time to come up to speed. 100% ... – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 43
Provided by: barbar59
Category:

less

Transcript and Presenter's Notes

Title: Effective Project Management


1
Effective Project Management
  • Barbara Stone
  • September 27, 2007

2
Agenda
  • Elevator Speeches
  • Prioritization
  • Evaluation of alternatives
  • Approach to project
  • WBS
  • Define
  • Sequence
  • Duration
  • Schedule

3
Elevator speeches
  • You are Standing
  • Informal
  • Informative
  • Brief
  • Include Business issue you are tackling
  • How company benefits
  • Why you are excited to take part
  • What the listener can do
  • if you need something

4
Elevator speech
  • http//www.creativekeys.net/PowerfulPresentations/
    article1024.html
  • Prepared presentation
  • Articulates in 3-4 minutes
  • Who are you helping
  • With what problem
  • How company benefits
  • Practicing is a good idea

5
Scope planninghigh-levelskills analysis
Charterbusiness casefeasibility studyproduct
description
Scope statement
Scope definitionassumptionsscope
in/outalternatives
WBS
Risk Mgmtplanning
ActivityDefinition
Costbudgeting
Resourceplanning
Costestimating
Cost baselineTime-phased budget
Risk Mgmtplan
Resourcerequests
Activitydurationestimating
Activitysequencing
CommunicationPlan
Schedule development
Networkdiagram
Project schedule
Project Plandevelopment
Project plan
6
Prioritization
  • Waterfall
  • Timing determines likelihood
  • Developers instead of customer
  • Agile
  • Value determines likelihood
  • Reassessed throughout project

7
Kano
8
Kano conclusions
9
Alternatives review decision
  • There may be multiple ways to fulfill the
    Requirements
  • Eliminate alternatives that dont meet external
    constraints
  • Evaluate remaining alternatives against selected
    criteria
  • time/budget requirements
  • Team skillset and interest
  • Other criteria as team requires

10
Traditional, agile, extreme?
11
Cone of uncertainty
12
Project sizing
13
PMBOK process to create project schedule
These processes can be combined, and iterative,
if need be
14
  • The what

15
Work Breakdown Structure
  • A hierarchical description of the work that must
    be done to complete the project as defined in the
    Project Overview Statement.
  • Inputs
  • POS
  • Requirements Document
  • Terms
  • Activity Chunk of work
  • Tasks Smaller chunk of work. Activities are
    made up of tasks
  • Work Package Complete description of how the
    tasks that make up the activity will actually be
    done

16
Uses for the WBS
  • Thought Process Tool
  • Architectural Design Tool
  • Planning Tool
  • Project Status Reporting Tool

17
(No Transcript)
18
(No Transcript)
19
Activity Definition
  • Decomposing the task areas / sub-projects
  • tasks in appropriate level of detail what
    does this mean for your project? Think about
  • experience of your team
  • possibly duration of task
  • of people performing the task if hand-off,
    new task
  • Only needs single person to oversee work
  • Team creating the WBS should have appropriate
    level of expertise to assign approximate duration
    to each task(because they will, later).

20
Brainstorming
  • Recorder writes all ideas where visible to team
  • Allows people to build on others ideas
  • Participant knows his/her contribution is
    valuable heard
  • Facilitator
  • All ideas accorded consideration no editing
  • keeps discussion focused
  • Sets time limits

21
Affinity diagram (Ishikawa)
22
Mind-mapping user story nodes
23
Adding task details
24
Tips
  • Person who has experience in doing something
    similar better at defining sub-tasks and
    duration. No team member with experience? Adds
    to risk needs safety Try to get someone with
    experience to help with planning if you cannot
    have them on the team for execution
  • May not know all detail as work through the
    plan and the project, scope will shift
    hopefully only slightly

25
Activity Sequencing
  • Process of determining both order and possible
    overlap of tasks - start with task constraints
  • Examples
  • Task A needs to be complete before task B may
    start
  • Tasks C, D, E may be done in parallel, but all
    must be complete before task F may begin
  • Task X may not begin until milestone Y has
    occurred
  • Task Q must start at the same time as task R

26
PERT activity on arc
27
PERT activity on node
28
Activity duration estimating
  • An art, with a little bit of science
  • Best estimators are those who have done similar
    work
  • Beware of confusing duration and effort
  • The duration of most activities will be
    significantly influenced by the resources
    assigned to them

29
PMBOK Activity Duration Estimating
Inputs
Tools/Techniques
Outputs
  1. Activity List
  2. Constraints
  3. Assumptions
  4. Resource Requirements
  5. Resource capabilities
  6. Historical information
  7. Identified risks
  • Expert judgment
  • Analogous estimating
  • Quantitatively based
  • durations
  • Reserve time
  • (contingency safety)
  • Activity duration
  • estimates
  • Basis of estimates
  • Activity list update

30
Pert (one network diagram technique)
  • Task Duration
  • O most optimistic estimate
  • M most likely estimate
  • P most pessimistic estimate
  • Formula

O4MP6
Sample Optimistic Most Likely Pessimistic Risk
adjusted 1 week 3 weeks 6 weeks 3 weeks 16
weeks 17 weeks 30 weeks 19 weeks
31
Sizing
32
Story points
33
How much, how fast
34
Planning poker

35
  • Youve been infected with spy wear and suspect
    its a root kit have to do a clean install

36
Six Criteria to Test for WBS Completeness
  • Status/Completion is measurable
  • The activity is bounded
  • The activity has a deliverable
  • Time and cost are easily estimated
  • Activity duration is within acceptable limits
  • Work assignments are independent
  • Seventh Criteria Project managers judgment
    that the WBS is not complete

37
Exceptions to the Completion Criteria Rule
  • Stopping Before Completion Criteria Are Met
  • Decomposing Beyond Completion of the Criteria

38
Factoring in constraints
  • Factor if multiple working on task together?
    discuss XP example.
  • Also factor if do not have resource 100 of time.
    Why this is a bad idea.
  • Adding Project Management factor
  • Do Jodie and Barbara do this?

39
Putting it all together
  • Tasks
  • Duration
  • Sequencing
  • Start date
  • Project Schedule
  • Does it meet Deadline / Scope / constraints?

40
Gantt chart
  • Does not show task interdependencies or resources
    assigned
  • Do not help organize project as effectively as
    WBS network diagrams
  • Completed after WBS
  • Effectively show progress time

41
Agile
42
Common scheduling pitfalls
  • Planned downtime calendar events, team needs
  • External interfaces contractors, external teams
  • Constraints duration, access, etc.
  • Time to come up to speed
  • 100 optimization
  • Just plain missed it
Write a Comment
User Comments (0)
About PowerShow.com