No Quiz today - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

No Quiz today

Description:

Also called Screening estimate, or order-of-magnitude estimate. Performed by Owner or Consultant ... below, make an order of magnitude estimate of the cost of ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 26
Provided by: mohamed6
Category:
Tags: quiz | today

less

Transcript and Presenter's Notes

Title: No Quiz today


1
No Quiz today
Lectures will be available onwww.eng.fsu.edu/mg
afy
2
Construction EngineeringCCE 4004
  • Lecture 5
  • Cost Estimating

3
Introduction
  • What is a cost estimate?
  • It is a prediction of probable cost
  • It is figuring out how to put the pieces together
    in the most economical manner
  • Estimating is both art and science
  • Identifying and quantifying the pieces of the
    takeoff
  • Identifying construction methods
  • Engineering - Will it be stable during
    construction?
  • Predicting the productivity rate

4
Bidding v. Estimating
  • Bidding is NOT the same as estimating
  • When we bid
  • We want to develop the lowest price without
    losing money
  • When we estimate
  • We want to develop the expected REAL cost of the
    work
  • Identify RISK

5
Types of Estimates
  • Feasibility estimate
  • Also called Screening estimate, or
    order-of-magnitude estimate
  • Performed by Owner or Consultant
  • Target Accuracy (/- 25 - 30)
  • Known Information
  • Building or Project Type
  • Hospital, School, Office, Hotel. etc.,
  • Relative Size
  • 140-150,000 sf., 3 story etc.,
  • Location
  • Community, focused area or a specific site.
  • Rough Quality Level or Relative Complexity

6
Types of Estimates
  • Conceptual or preliminary estimate
  • Performed by project architect
  • Target accuracy (/- 20 - 25)
  • Known information
  • Site, building type size
  • Possible main materials finishes
  • Degree of complexity rough quality
  • Unknowns
  • How it is to be put together (labor)
  • Specific detailed site information

7
Types of Estimates
  • Engineers estimate
  • Performed by the project architect / engineer
  • Target accuracy (/- 5 - 10)
  • Known information
  • Complete design info is available
  • Construction drawings project technical specs
  • Unknowns
  • Some sub-surface conditions
  • Exact labor material rates of contractor (G.C.
    mark-up, motivation, market 15-20)

8
Types of Estimates
  • Detailed cost estimate
  • Performed by general contractor subs
  • Target accuracy (must be exact)
  • Known information
  • Complete design info is available
  • Construction drawings project technical specs
  • Unknowns
  • Some sub-surface conditions
  • Remaining questions directed to A/E

9
Approaches to Cost Estimation
  • Production Function
  • Relationship between the volume of construction
    and a factor of production such as labor
  • Empirical Cost Inference
  • Relationship between the cost and a few important
    attributes of the facility/ system
  • Unit costs for bill of quantities
  • A unit cost is assigned to each of the facility
    components or tasks as represented by the bill of
    quantities.
  • Allocation of joint costs
  • Allocations of cost from existing accounts may be
    used to develop a cost function of an operation.

10
Example
  • In making a screening estimate of an industrial
    plant for the production of batteries, an
    empirical formula based on data of a similar
    buildings completed before 1987 was proposed
  • C (16,000)(Q 50,000)1/2
  • where
  • Q is the daily production capacity of batteries
    and
  • C is the cost of the building in 1987 dollars.

11
Example (contd)
  • If a similar plant is planned for a daily
    production capacity of 200,000 batteries, find
    the screening estimate of the building in 1987
    dollars.
  • Solution
  • C (16,000)(200,000 50,000)1/2
  • 8,000,000 (in 1987 dollars)

12
Approaches to Cost Estimation
  • Production Function
  • Relationship between the volume of construction
    and a factor of production such as labor
  • Empirical Cost Inference
  • Relationship between the cost and a few important
    attributes of the facility/ system
  • Unit costs for bill of quantities
  • A unit cost is assigned to each of the facility
    components or tasks as represented by the bill of
    quantities.
  • Allocation of joint costs
  • Allocations of cost from existing accounts may be
    used to develop a cost function of an operation.

13
Cost Indices
  • A price index is a weighted aggregate measure of
    constant quantities of goods and services
    selected for the package.

14
Cost Indices (contd)
  • The input price indices of labor and/or material
    reflect the price level changes of such input
    components of construction
  • the output price indices, where available,
    reflect the price level changes of the completed
    facilities.
  • the construction cost index and the building cost
    index are reported periodically in the
    Engineering News-Record (ENR).

15
Historical Cost Data
  • the following types of information are available
  • Catalogs of vendors' Data (Sweets' Catalog-
    McGraw-Hill )
  • Periodicals (ENR - McGraw-Hill, Cost Engineering)
  • Commercial cost reference manuals (R.S. Means,
    Dodge Manual for Building Construction)
  • Digests of actual project costs (Dodge Digest of
    Building Costs and Specifications, ENR weekly)

16
Parametric Estimation
  • The application of the single parameter cost
    function for estimates are
  • Exclude special local conditions in historical
    data
  • Adjust for size or capacity
  • Adjust for inflation index
  • Adjust for local index of construction costs
  • Adjust for different regulatory constraints
  • Adjust for local factors for the new facility

17
Adjust for size or capacity
  • Cost of unit A Cost of unit B (capacity of unit
    A/capacity of unit B) x
  • Where
  • X is the cost capacity factor
  • Example The cost of a 320 (ft3/hr) process unit
    is 675,000. From historical cost records, the
    capacity ratio factor is 0.72. Estimate the cost
    of similar process unit with a capacity of 450
    ft3/hr.
  • Cost of unit A (675,000)( 450/320)0.72
  • 862,797

18
Adjust for inflation index
  • Cost (_at_ t n) Cost (_at_t) (1i)n
  • Where I is the expected inflation rate
  • Example the screening estimate of an industrial
    plant for the production of batteries is 120
    million in 2001 dollars, if the inflation rate is
    expected to be 8 per year , find the cost in
    2004 dollars.
  • Cost (120)(1.08)3 151.2 million in 2004
    dollars

19
Adjust for local index of construction costs
  • The total construction cost of a refinery in
    Tallahassee, Fl was 100 million. It is proposed
    that a similar refinery will be built in Los
    Angeles, CA. if the location index was 0.92 for
    Tallahassee, FL and 1.14 for Los Angeles, CA,
    make an order of magnitude estimate of the cost
    of the proposed plant.
  • Cost of CA plant (100)(1.14/0.92)
    126.67 million

20
Parametric Estimation Example
  • The total construction cost of a refinery with a
    production capacity of 200,000 bbl/day in Gary,
    Indiana, completed in 1999 was 100 million. It
    is proposed that a similar refinery with a
    production capacity of 300,000 bbl/day be built
    in Los Angeles, California, for completion in
    2003. For the additional information given below,
    make an order of magnitude estimate of the cost
    of the proposed plant.

21
Example (contd)
  • In the total construction cost for the Gary,
    Indiana, plant, there was an item of 5 million
    for site preparation which is not typical for
    other plants.
  • The variation of sizes of the refineries can be
    approximated by the exponential rule, Equation
    (5.4), with m 0.6.
  • The inflation rate is expected to be 8 per year
    from 1999 to 2003.

22
Example (contd)
  • The location index was 0.92 for Gary, Indiana and
    1.14 for Los Angeles in 1999. These indices are
    deemed to be appropriate for adjusting the costs
    between these two cities.
  • New air pollution equipment for the LA plant
    costs 7 million in 2003 dollars (not required in
    the Gary plant).
  • The contingency cost due to inclement weather
    delay will be reduced by the amount of 1 of
    total construction cost because of the favorable
    climate in LA (compared to Gary).

23
Solution
  • On the basis of the above conditions, the
    estimate for the new project may be obtained as
    follows
  • Typical cost excluding special item at Gary, IN
    is 100 million - 5 million 95 million
  • Adjustment for capacity based on the exponential
    law yields (95)(300,000/200,000)0.6
    (95)(1.5)0.6 121.2 million
  • Adjustment for inflation leads to the cost in
    2003 dollars as (121.2)(1.08)4 164.6 million

24
Solution (contd)
  • Adjustment for location index gives
    (164.6)(1.14/0.92) 204.6 million
  • Adjustment for new pollution equipment at the LA
    plant gives 204.6 7 211.6 million
  • Reduction in contingency cost yields
    (211.6)(1-0.01) 209.5 million
  • Since there is no adjustment for the cost of
    construction financing, the order of magnitude
    estimate for the new project is 209.5 million.

25
More Examples!!!
Write a Comment
User Comments (0)
About PowerShow.com