AudioVisual Technology Upgrade Report March 11, 2003 - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

AudioVisual Technology Upgrade Report March 11, 2003

Description:

Video projector image is significantly degraded ... District contracted with Dan Dillingham Consulting and Design Services. Assessment of needs ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 17
Provided by: Dave147
Category:

less

Transcript and Presenter's Notes

Title: AudioVisual Technology Upgrade Report March 11, 2003


1
Audio-Visual Technology Upgrade
Report March 11, 2003
2
Current system problems
  • Equipment is unreliable
  • Video projector image is significantly degraded
  • One computer is unable to project to audience or
    Board
  • Video camera has limitations
  • 35mm video slide projector produces poor quality
    images
  • Lighting cannot be adequately controlled
  • Inadequate grounding causes humming
  • (Temporary repairs completed in November)

3
Purpose of upgrades
  • To enhance the integration of electronic
    technologies into Board meetings
  • To increase efficiency of the Board Room for the
    Board, public and staff
  • To be more user-friendly

4
Assessment of needs
  • Staff from the Office of Communications and
    Governmental Affairs, Information Resources, and
    Operations and Land Resources evaluated the needs
    and researched options
  • Research was conducted at the federal courthouses
    in Tallahassee and Gainesville, an FDEP meeting
    room in Tallahassee, Board rooms at SFWMD and
    SWFWMD, and Alachua Countys Emergency Operations
    Center
  • District contracted with Dan Dillingham
    Consulting and Design Services

5
Sound system
  • Sound system upgrades to include
  • Recessed ceiling speakers to evenly distribute
    sound
  • Desk microphones to make voices audible
  • Ceiling microphones to cover seating areas
  • Automatic microphone mixer, amplifier and
    equalizers to enhance sound

6
Projection system
Existing screen and projector would be replaced
to
  • Provide brighter image capable of projecting
    image without dimming lights
  • Improve movement between Board seating and wall

7
Presentation cart lectern
New cart, to be used by District staff and the
public, to include
  • Annotation, document camera, VCR, PC, laptop
    inputs, Internet access, auxiliary inputs
  • Wiring in two locations for presentation and
    meeting format flexibility
  • User-friendly equipment to allow presenter to
    control presentation alone or in conjunction with
    technical assistant

8
Control system
  • Increase capacity and functionality for new
    devices
  • Allow complete monitoring and control
  • Increase efficiency

New control system and touch panels will
9
Control room
  • Capacity and functionality would be improved by
  • Adding switcher
  • Adding processors to provide scaling and
    connections for future video streaming option
  • Enhancing camera controls (repositioning four
    existing cameras and adding two additional
    cameras)

10
Electrical connections
  • Additions to include
  • 22 new electrical connections
  • Two new 20-amp circuits
  • Duplex receptacle at desktop to provide power
    connection
  • Wire tray under desktop to provide cable and wire
    management for power, data, AV and future needs

11
Improved lighting
  • Increase light needed on Board and staff
    positions
  • Improve quality of video camera images
  • Work with existing lighting power panel
  • Provide control of groups of lights

In combination with control system, new lighting
system will
12
Lighting control system
  • Enhanced system will
  • Add capacity required for recommended lighting
  • Be integrated with control system
  • Improve quality of video and room appearance

13
Board members work space
Enhancements for Board members would include
  • Addition of LCD flat panel monitors
  • Addition of laptop docking stations and keyboards
    for Board members
  • Addition of privacy rail
  • Replacement of microphones (included with sound
    system upgrades)

14
Conference rooms
  • Possible changes include
  • Adding a fixed projector and screen, and laptop
    connections to Rooms 136A and B
  • Adding a fixed projector and laptop connections
    to Room 158

15
Estimated budget
  • Sound system 30,974
  • Projection system 16,238
  • Boardroom control system 18,716
  • Video control system 24,418
  • Presentation cart 19,984
  • Electrical system 10,660
  • Lighting system 43,145
  • Wiring 8,435
  • Millwork, monitors, docking stations 40,493
  • Permits, bonds, insurance, general
    contractor 42,436
  • Total 255,499
  • The above costs are estimates, and the project
  • is anticipated to be within the 240,000 budget.

16
Thank you
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com